RESOLVED (1) To approve the release of council capital investment to deliver inclusive growth in Harlesden. Details of the total sum and the breakdown of the capital investment are contained within Appendix 1. (2) To approve £0.5m of revenue to take forward capacity building in Harlesden Town Centre with the local business community and stakeholders, having noted that the council had bid for an additional £0.5m from the GLA Good Growth Fund to increase this capacity building fund. (3) To support the Methodist Church to bid for £0.5m of Neighbourhood Community Infrastructure Levy (NCIL), having noted that the council had also bid for £0.5m from the GLA Good Growth Fund to increase the project fund to £1m to deliver the full scope of the proposed project for this asset. (4) To note that without the sources of funding identified above the proposed works to the Methodist Church cannot take place. If part of the total required funding is not secured , then work will need to be undertaken by the Church to select which works are prioritised.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
Report from the Strategic Director of Regeneration and Environment
Inclusive Growth in Harlesden Town Centre
Wards Affected: Harlesden Key or Non-Key Decision: Non-Key Yes, Appendix 1 (Exempt): Breakdown of capital expenditure.
Part 1, Schedule 12A of 1972 Local Government Act - Part Exempt: Information relating to the financial or business affairs of any particular person (including the authority holding that information)
Eight:
Appendix 1: Breakdown of capital expenditure [Exempt] Appendix 2: Community Consultation Appendix 3: Picture Palace concept drawings No. of Appendices: Appendix 4: Harlesden Methodist Church concept drawings Appendix 5: Long term proposals Appendix 6: Designworks concept drawings Appendix 7: Map of Harlesden sites Appendix 8: Guidance Notes, Town Centre property acquisitions Background Papers: N/A Report Authors:
Nigel Chapman - Operational Director - Integration and Improvement Glenn Miller - Head of Property Sadie East - Head of Transformation Pascoe Sawyers - Head of Strategy and Partnerships Stephanie Wilson - Libraries, Arts and Heritage Manager Lois Stonock - Executive Director, LBoC
2 Contents
Section title Page Paragraph number reference
Purpose of Report 4 1.0 Recommendations 4 2.0 Detail 4 3.0 Background 4 3.1 Current Day Harlesden 5 3.5 Vision for the future of Harlesden 5 3.8 Analysis of current needs 6 3.14 Responding to demand 8 3.16 Phase 1: current projects 8 3.19 Phase 2: short term proposals 9 3.20 Picture Palace 9 3.21 Harlesden Methodist Church 10 3.33 Phase 3: long term proposals 11 3.39 Designworks 12 3.41 Strategic alignment 13 3.49 Funding for phases 2 and 3 13 3.50 Guidance notes for acquisitions in Town Centres 14 3.55 Next Steps 14 3.59 Financial implications 15 4.0 Legal implications 16 5.0 Equalities and Diversity 17 6.0 Appendix 1: Breakdown of capital expenditure [EXEMPT] n/a n/a Appendix 2: Community Consultation n/a n/a Appendix 3: Picture Palace concept drawings n/a n/a Appendix 4: Harlesden Methodist Church concept drawings n/a n/a Appendix 5: Longer term proposals n/a n/a Appendix 6: Designworks concept drawings n/a n/a Appendix 7: Map of Harlesden sites n/a n/a Appendix 8: Guidance Notes - Town Centre property acquisitions n/a n/a
3 1.0 Purpose of the Report
1.1To set out an aspirational vision for Harlesden to create a town centre fit for the future, supported by an evidence base of need and delivered through excellent design, capital investment, and local capacity building.
1.2To illustrate how both short and long-term capital investment can unlock a range of holistic benefits for Harlesden, building on existing services, programmes and investment delivered by the council and local Voluntary and Community Sector (VCS) to date.
1.3Setting these proposals in the context of wider aspirations for Harlesden, to ensure a coordinated approach to investment and the development of the local offer for the community, businesses and visitors.
1.4To share the strong evidence base of need in Harlesden that has been compiled following significant community consultation and specialist urban design research.
1.5To propose a new guidance document which provides a decision making framework for property acquisitions in town centres that can support diversification of Brent’s high streets.
2.0Recommendation(s)
2.1To approve the release of council capital investment to deliver inclusive growth in Harlesden. Details of the total sum and the breakdown of the capital investment are contained within Appendix 1.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.