Resolved
Granted planning permission as recommended.
Planning Committee decided this item on Wednesday 18 December 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Granted planning permission as recommended.
COMMITTEE REPORT Planning Committee on 18 December, 2019 Item No 05 Case Number 19/2459
SITE INFORMATION
RECEIVED 9 July, 2019
WARD Wembley Central
PLANNING AREA
LOCATION 435-441 & 441A High Road, Wembley, HA9 7AB
PROPOSAL Demolition and redevelopment to provide a building of upto 8 storeys comprising 44 flats with basement level, retail space (Use Class A1) and community centre (Use Class D1) on ground and first floors, new vehicular access onto London Road, provision of car and cycle parking and refuse storage Please see Condition 2. PLAN NO’S
LINK TO DOCUMENTS When viewing this on an Electronic Device ASSOCIATED WITH THIS PLANNING Please click on the link below to view ALL document associated to case APPLICATION <https://pa.brent.gov.uk/online-applications/applicationDetails.do?activeTab=documents&keyVal=DCAPR_146077>
When viewing this as an Hard Copy
Please use the following steps
1. Please go to pa.brent.gov.uk 2. Select Planning and conduct a search tying "19/2459" (i.e. Case Reference) into the search Box 3. Click on "View Documents" tab
DocRepF Document Imaged Ref: 19/2459 Page 1 of 29 RECOMMENDATIONS 1 That the Committee resolve to GRANT planning permission subject to:
A. The prior completion of a legal agreement to secure the following planning obligations:
1. Payment of the Council’s legal and other professional costs in (a) preparing and completing the agreement and (b) monitoring and enforcing its performance
2. Notification of material start 28 days prior to commencement.
3. Affordable Housing – Provision of four Discount Market Rent (DMR) units with rents equivalent to London Living Rent levels. The DMR units will comprise of three x 1 bedroom units and one x 2 bedroom unit. Nomination agreement to be secured for key worker prioritisation for the affordable units under the 'Marketing & Lettings Plan'
4. Pre implementation financial review mechanism if construction works do not commence within 24 months of the committee resolution to grant permission, to reasonably capture any improvement in viability for deferred affordable housing planning obligations. Post implementation financial review mechanism to be submitted upon disposal of 60% of Open Market Dwellings or 6 months prior to anticipated date of practical completion, whichever is the earliest
5. Financial contribution of £12,000 towards replacement tree planting of six trees
6. Training and employment of Brent residents - Prior to a material start to inform in writing Brent Works of the projected amount of construction jobs, training opportunities and provide a copy of the Schedule of Works. And, prior to a Material Start to prepare and submit for the Council’s approval an Employment Training Plan for the provision of training, skills and employment initiatives for residents of the Borough relating to the construction phase of the Development and in relation to the operational phase of the Development.
7. Carbon Off-setting – Pre-construction: submission of revised Energy Assessment to achieve London Plan Policy 5.2 standards, initial financial contribution to Brent’s carbon offsetting scheme. Post-completion: submission of revised Assessment, final financial contribution.
That the Head of Planning is delegated authority to negotiate the legal agreement indicated above.
B. That the Head of Planning is delegated authority to issue the planning permission and impose conditions and informatives to secure the following matters:
Conditions
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
19/2459 435 441 & 441A High Road, Wembley, HA9 7ABReport | 778 KB | DownloadRead as text |
Follow Planning Committee at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Aug 2026 | Apologies for AbsenceApologies for absence were received from Councillor Gallagher with Councillor Ahmadi-Moghaddam substituting. Apologie... | Decided | Open |
| 5 Aug 2026 | Declarations of interestsNo declarations of interest were made during the meeting. | Decided | Open |
| 5 Aug 2026 | Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the... | Approved | Open |
| 5 Aug 2026 | 26/0225 - Brent NHS Primary Care Trust, Wembley Centre For Health & Care, 116 Chaplin Road, Wembley, HA0 4UZGranted planning permission subject to: (1) The prior completion of a satisfactory legal agreement; and (2) The condi... | Agreed | Open |
| 5 Aug 2026 | Any Other Urgent BusinessThere was no other urgent business. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.