Resolved
Cabinet noted the overall capital financial position.
Cabinet noted this item on Tuesday 14 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Cabinet noted the overall capital financial position.
1.1This report sets out the current forecasts of capital expenditure against the budget for 2019/20, highlights the key achievements of the programme, notes any budget changes since initial approval and sets out the various elements of financing.
1.2The programme is forecasting to spend £229.1m across all schemes against a budget of £246.7m, which equates to a 93% spend.
1.3The underspend of £17.6m primarily relates to:
- an underspend of £17.9m in housing and £0.7m in Public Realm; - offset by an overspend of £1.6m in South Kilburn and other small combined; and - variances totalling £0.6m underspend.
1.4The key risks to the programme are summarised in Appendix 2.
1.5Table 1 summarises the overall capital position. Table 1
Executive Cost Summary - 2019/ 20 Predicted Outturn Performance 92.88%
Original Revised Commitme Previous Current FY £m YTD Spend budget Budget nts Fcst Fcst Variance Totals 257.59 246.70 54.19 49.45 289.44 229.13 - 17.57 Corporate Landlord 52.16 50.55 1.36 3.10 50.77 50.64 0.09 Regeneration 1.73 2.02 0.08 1.45 6.87 1.86 - 0.16 St Raphael's 0.86 0.99 0.28 0.15 0.76 0.73 - 0.26 HCIB - HRA 36.45 100.73 9.84 11.72 90.90 92.28 - 8.45 HCIB - GF 121.50 23.19 28.13 6.42 22.88 22.10 - 1.09 PRS I4B 21.55 29.75 0.00 12.17 21.36 21.39 - 8.36 Schools 7.21 10.72 1.77 4.92 14.50 10.45 - 0.27 South Kilburn 3.85 8.77 0.34 5.73 8.77 10.40 1.63 Public Realm 12.27 19.99 12.39 3.81 16.89 19.28 - 0.71
2.1To note the overall capital financial position.
3.0Detail
Corporate Landlord
Spend Position, Forecast and Key Achievements
3.1The 2019/20 forecast for Corporate Landlord is a £0.1m overspend. The variance is due to IT which is forecasting a pressure of £0.5m, offset by a property and energy underspend of £0.4m.
3.2The IT overspend comprises £0.2m from the prior year and £0.3m that has arisen in 2019/20 on to the laptop rollout project. The reason for the in-year overspend is initial scoping for the number of devices needed, which did not include some newly recruited roles.
3.3It is possible that a further £0.2m expenditure will be incurred for this project, for which a paper would be brought to Capital Programme Board (CPB) in December.
3.4The minor works budget in property management is forecasting a £0.3m underspend as fewer than anticipated repairs have been required and there are combined underspends of £0.1m across other property and energy budgets.
3.5The rollout of new devices across Brent staff is now substantially complete, with staff better able to work remotely and with equipment more suited to the needs of their service. 3.6 The Digital Strategy project has an ambitious plan to fully embrace digital innovation in Council services. The programme has realised many achievements to date including implementation of improved digital systems for Brent Customer Services, realising a £1m saving, piloting of Robotic Process Automation (RPA) in Brent services and significant improvements to the Council’s website performance. In October 2019, Cabinet approved the strategy and business case for the period 2019-2023.
Regeneration
Spend Position, Forecast and Key Achievements
3.7The £0.2m underspend is mainly due to delays on the Bridge Park Regeneration project.
3.8The Council has used Strategic Community Infrastructure Levy (CIL) funds to deliver significant improvements to Olympic Way to make the area safer, more attractive and offer much-improved amenities to local residents.
St Raphael’s Estate Regeneration
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
12a. Appendix 1- financial summariesAppendix | 101 KB | Download |
PDF |
12b. Appendix 2- Risks to the delivery of the Capital ProgrammeAppendix | 628 KB | Download |
PDF |
Quarter 3 Capital Budget Monitoring ReportReport | 135 KB | DownloadRead as text |
Follow Cabinet at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... | Decided | Open |
| 9 Nov 2026 | Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... | Decided | Open |
| 9 Nov 2026 | Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... | Approved | Open |
| 9 Nov 2026 | Matters Arising (if any)None identified. | Decided | Open |
| 9 Nov 2026 | Petitions (if any)There were no petitions presented at the meeting. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.