Cabinet RESOLVED to: (1) approve the award of a contract for the supply of electricity to NPower Limited for two years as from 1 st October 2020 via a call-off from LASER Framework Y18003, (2) approve the award of a contract for the supply of gas to Total Gas and Power for two years from 1 st October 2020 via a call-off from the LASER Framework Y18002; and (3) approve, alternatively to the recommendations at (1) and (2) above, the award of contracts for gas and electricity to the next ranked Suppliers on Lot 1 of each of the Frameworks referred to in section 5 of the report, if NPower Limited or Total Gas and Power cannot, or do not accept the offer of a Council contract. Such award shall be in accordance with the offer and award process described in section 5 of the report ; (4) approve the Council’s entry into an Access Agreement with Kent County Council referred to in section 5 of the report, to enable its participation and purchase of gas and electricity from the Frameworks referred to in (1) and (2) above.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report requests authority to award contracts as required by Contract Standing Order 88. This report describes the reasons for the award of those contracts as referred to within paragraphs 2.1, 2.2 and 2.3 of this report, and for the Council’s entry into the Access Agreement referred to at paragraph 2.4. The report also summarises the process required to procure and award those contracts.
2 Recommendation(s)
Cabinet is asked to:
2.1approve the award of a contract for the supply of electricity to NPower Limited for two years as from 1st October 2020 via a call-off from LASER Framework Y18003, and
2.2approve the award of a contract for the supply of gas to Total Gas and Power for two years from 1st October 2020 via a call-off from the LASER Framework Y18002; and 2.3 that alternatively to the recommendations at paragraphs 2.1 and 2.2, Cabinet approves the award of contracts for gas and electricity to the next ranked Suppliers on Lot 1 of each of the Frameworks referred to at paragraph 5, if NPower Limited or Total Gas and Power cannot, or do not accept the offer of a Council contract. Such award shall be in accordance with the offer and award process described in Section 5 of this report; and
2.4that Cabinet approves the Council’s entry into an Access Agreement with Kent County Council referred to in section 5 below, to enable its participation and purchase of gas and electricity from the Frameworks referred to at paragraphs 2.1 and 2.2 above.
Summary
3.1Brent Council’s current energy contract expires in Sept 2020. Officers are proposing to call off from the LASER framework again, but this time for two rather than four years.
3.2This shorter time frame is in order to give Brent the opportunity to make substantial changes to its purchase of energy sooner. In particular, the Council’s energy procurement will be part of the plan to achieve net zero carbon for the Council’s own estate and operations by 2030.
3.3The Council’s own estate and operations, including Council buildings, street lighting and fleet, makes up 1% of overall borough carbon emissions. The Council is committed to playing its part and leading the way on the climate emergency. We will do everything we can to reduce carbon emissions from our own buildings and fleet.
3.4It is suggested that calling off from the LASER framework again for a short period is preferable to making large changes at this point:
(i) to provide continuity at a time of global uncertainty due to the coronavirus pandemic and uncertainty in local government funding;
(ii) to fit in with the wider work of Brent’s Climate and Ecological Emergency; and
(iii) to allow time to see the results of the first local authority investments in green Power Purchase Agreements which look promising as a potential way of affordably purchasing green energy.
3.5In these two years, the Council will:
(i) focus on further reducing its energy usage in order to reduce its carbon footprint, and make it possible to potentially pay higher unit costs for better green credentials at the next reprocurement of energy;
(ii) explore innovative ways of reducing our energy’s carbon footprint and closely follow developments in the energy market; (iii) potentially switch to a Power Purchase Agreement mid-way through the contract (the Laser Framework allows this) once the market is more established.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.