Cabinet RESOLVED to: (1) Note, subject to the clarification provided regarding the reference to William Dunbar/William Saville Houses in section 5.6.2 of the report, the contents of the report and progress to date in delivering both the New Council Homes Programme (NCHP) and other programmes and projects in place to deliver a total of 5,000 new affordable homes in the borough by 2024. (2) Note the steps being taken as set out principally in sections 6 and 7 of the report to add value to the programme, specifically in relation to stakeholder engagement and landscaping.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report provides an update on progress made towards delivering against the Council’s housing target of 5,000 new affordable homes over the five year period (2019 – 2024), 1,000 of which will be through the New Council Homes Programme (NCHP).
1.2In December 2019, it was agreed that Cabinet would receive six monthly reports updating progress since the previous meeting and outlining key decisions required enabling the programme to continue until the next meeting six months hence. This report provides information on the progress in respect of procurement decisions made at Cabinet in December 2019 and the next stages in the development programme.
1.3This report also provides a summary of the additional developments being assessed and progressed, with an indication of key issues, practical considerations and steps being taken moving forward. 2.0 Recommendation(s)
2.1Cabinet is asked to:
2.1.1 Note the contents of this report and progress to date in delivering both the New Council Homes Programme (NCHP) and other programmes and projects in place to deliver a total of 5,000 new affordable homes in the borough by 2024.
2.1.2 Note the steps being taken as set out principally in Sections 6 and 7 to add value to the programme, specifically in relation to stakeholder engagement and landscaping.
3.0Introduction
3.1Delivering 5,000 genuinely affordable homes within a five year period is an ambitious target. However, the Council has built and continues to build the necessary delivery infrastructure and relationships, to achieve the target. The Council recognises the importance of Registered Providers (RPs) in achieving this target and deliberately built a team to harness and support efforts by RPs to develop affordable homes in the borough. Where the Council has direct control, i.e. in the direct delivery of 1,000 Council homes, all relevant departments and teams within the Council structure, such as Property, Procurement, Planning, Legal, Finance, along with Housing, are working extremely well together to ensure delivery.
3.2Below is the current delivery position under the New Council Homes Programme:
146 new homes have been built and let 694 homes are on site 162 have been given planning consent and now going through procurement for developers 255 have been submitted for planning consent
3.3A further 19 sites are currently going through design and feasibility. The number of homes to be achieved from these sites are currently estimated to be c.140 and they are geared towards larger sized family homes. In addition, officers continue to explore new sites to be added to the pipeline, for future delivery.
Background
4.1Strategic Housing Target
4.2The Council has committed to an ambitious strategic housing target to deliver 5,000 new affordable homes over the five year period 2019- 2024. Delivery of a total of 5,000 new affordable homes includes the provision of 1,000 directly by the Council by the 31st March 2024.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.