Resolved
Resolved 1. To note the progress made to date including the elements of the accounts where further audit work is required. 2. To note the revised timetable as set out in paragraph 3.7 of the report.
Audit and Standards Advisory Committee noted this item on Wednesday 29 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved 1. To note the progress made to date including the elements of the accounts where further audit work is required. 2. To note the revised timetable as set out in paragraph 3.7 of the report.
1.1This report provides an update on the progress made to date on the audit of the Council’s 2019/20 Statement of Accounts.
2.0Recommendation(s)
2.1The Committee is asked to note the progress made to date including the elements of the accounts where further audit work is still required, and;
2.2To note the revised timetable set out in paragraph 3.7. 3.0 Detail
3.1At the May 2020 meeting of the Audit and Standards Advisory Committee officers introduced the 2019/20 draft accounts for consideration and comment. Subsequent to this, in early June formal notice was published on the Council’s website advising that the unaudited statement of accounts would be available for a period of time for any interested person to inspect and make copies of the accounts and any related documents. The formal inspection period was open for 30 days and ended on the 17 July 2020. At the time of writing there were no requests for information/clarification or objections to the 2019/20 accounts during this period.
Brent Council Accounts
3.2The audit itself commenced on 15th June 2020. Grant Thornton (GT) were provided with a copy of the draft accounts and a complete set of working papers. Officers have made steady progress in resolving audit queries, at the last count responding to over 100 queries covering all areas of the accounts. Separate to this, our auditors have undertaken a series of technical reviews of the draft statement and the queries arising from this are currently being responded to. All of which has been achieved whilst working remotely.
3.3Some of the main areas of outstanding work relates to going concern and post balance sheet events, completion of the sample testing of income, expenditure, assets and liabilities and audit quality reviews where the work of junior audit staff is reviewed by senior managers. Further details are included on a separate GT report included elsewhere on the agenda.
3.4Given the amount of audit work remaining and expected timeframes, the accounts are expected to be completed by mid-August. Formal presentation and sign off of the audited statement of accounts has therefore been deferred until the 8th September 2020 meeting.
Subsidiary Company Accounts (I4B Holdings Limited/First Wave Housing)
3.5Following the comments of the committee last year, the scheduling of the audit for i4B and FWH was brought forward to ensure completion prior to finalising the group accounts position. At the date of despatch of this report, both audits have been largely completed, with only minor queries remaining. The draft audit finding reports have been issued and were presented to the I4B and FWH board on 16 July 2020. Although the accounts of the subsidiaries are yet to be formally agreed the following paragraphs summarise the current position for both companies.
3.6Audit work is substantially complete, subject to the following outstanding matters summarised below:
Final internal quality control reviews. Financial statement review procedures, including consideration of the disclosures relating to the ‘material valuation uncertainty’ Completion of going concern reviews Timetable
3.7As noted above, subject to maintaining the current trajectory the audit of the group accounts are on course to be completed in August 2020 and will therefore be presented at the 8th September meeting of the Audit & Standards Committee.
4.1None specifically arising from this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update on Final Statement of AccountsReport | 86 KB | DownloadRead as text |
Follow Audit and Standards Advisory Committee at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2026 | Minutes of the previous meeting and action logRESOLVED that the minutes of the previous meeting of the Committee held on Tuesday 24th March 2026 be approved as a c... | Approved | Open |
| 16 Jun 2026 | Audit & Standards Advisory Committee Forward Plan & Work Programme for 2026-27It was RESOLVED to note the Committee’s Forward Plan and Work Programme for the 2026-27 Municipal Year with the dates... | Noted | Open |
| 24 Mar 2026 | Minutes of the previous meeting & Action LogIt was RESOLVED that the minutes of the previous meeting of the Committee held on Tuesday 3 February 2026 be approved... | Approved | Open |
| 24 Mar 2026 | Review of the use of RIPA PowersRESOLVED to note the contents of the report, together with the changes to the RIPA policies to reflect the Council’s ... | Noted | Open |
| 24 Mar 2026 | Annual Standards and Governance Report for 2025 (including quarterly update on gifts and hospitality)RESOLVED to: (1) Note the contents of the Annual Standards and Governance Report for 2025. (2) Recommend to the Audit... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.