Resolved
It was RESOLVED (1). To note the contents of the report. (2). That an update on school place planning for children with SEND be provided at a future meeting of the Forum. ( Action 81: Brian Grady )
Schools Forum noted this item on Thursday 17 June 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
It was RESOLVED (1). To note the contents of the report. (2). That an update on school place planning for children with SEND be provided at a future meeting of the Forum. ( Action 81: Brian Grady )
Appendix 1 - HNB Management Plan Forecast
DSG Recovery Plan Summary - April 2021 HNB Forecast is based on managing the rate of EHCP growth through Cost avoidance arising from SEND Support and the Graduated Response Programme ****"Low" model assumes a 11% increase in 2021-22 reducing to 10% in 2022-23, 9% in 2023-24 and 7% for each following year Actuals Actuals Estimates Comments Financial Year 2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 £000 £000 £000 £000 £000 £000 £000 Schools Block including 6th Form 0 536 0 0 0 0 0 Based on "LOW" Model cost avoidance due to SEN ****High Needs Block (excluding Schools Block transfer) (4,917) (6,233) (5,238) (4,044) (3,699) (2,444) (1,058) Support pilot and the Graduated Response Programme. Early Years Block (547) Central Block 634 0 0 0 0 Annual Forecast Under/(Over) Spend (4,917) (5,609) (5,238) (4,044) (3,699) (2,444) (1,058)
Cumulative (Deficit)/Surplus (4,917) (10,526) (15,764) (19,809) (23,507) (25,951) (27,009)
Mitigating Items
Improving Sufficiency of Places
- Establishing a new special school in Brent proposed 150 places. 576 576 576 1,200 Cost avoidance based on average (INMSS) cost at £46k and maximum band for maintained special school is £30k
- Increased ARPs (Primary up to 70 & Secondary up to 56) Cost avoidance based on the average top up cost of our Work with current school clusters to explore with schools how needs can 71 204 581 581 581 maintained special school of £14.5k and cost for ARP's at be best met locally, focusing on increasing SEND capacity in mainstream £9.4k through Additional Resource Provisions (ARPs) AY 2021/22- 2022/23
- Phoenix Arch - 13 increase in PAN by 2024 Cost avoidance based on average cost for Phoenix is 144 312 456 To expand their Published Admission Number (PAN) over the next 3 years £21.4k and OOB cost is £45.6k
- Alternative provision (Ashley College) Cost avoidance based on average cost at Southover In conjunction with broadening the cohort of CYP with additional needs 110 110 110 110 partnership/Special school £37.8k and cost for Ashley accessing Ashley College on site as a respite or transition provision. college is £23k
- New post 16 Skills hub Options are being considered by Brent Council with Brent CCG, FE Colleges and school partners to develop a new post 16 skills hub to help meet the TBC TBC demand for education places for young people 16-25 with SEND. Governance arrangements to be developed, potential for a collaboration/joint venture and income generation. Post 16 spend has increased from £3.5m (2019/20) to £4.5m in (2020/21).
Financial Management Assuming a 0.5% request will be made for the next few - Schools Block Transfer 1,185 1,200 1,200 1,200 1,200 years - Reduce the DSG funded SEN support services Restructure - Inclusion Service to TBC 250 250 250 250 Restructure - TBC the current VR agreed was to go towards the Deficit 70 70 70 70 70 Education Psychology 200 200 200 200 200 To be funded from the GF.
- Administrative charges 39 67 67 67 67
- Commissioning Arrangements - (E.g Pears Family School Contract) 126
Total Mitigating Items 0 0 1,691 2,677 3,198 3,367 4,135
Net Position Cumulative (Deficit)/Surplus (4,917) (10,526) (14,073) (17,131) (20,309) (22,584) (22,874)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
7a. DSG HNB Management PlanReport | 465 KB | DownloadRead as text |
PDF |
Dedicated Schools Grant High Needs Block Management Plan UpdateReport | 290 KB | Download |
Follow Schools Forum at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jun 2025 | Minutes of the Previous MeetingIt was RESOLVED to approve the minutes of the previous meeting held on Thursday 13 February 2025 as a correct record. | Approved | Open |
| 18 Jun 2025 | Updated Scheme for Financing Schools & Schools Financial Regulations 2025/26RESOLVED , with no further comments having been raised, that the maintained schools’ representatives on the Forum: (1... | Approved | Open |
| 13 Feb 2025 | Minutes of the Previous MeetingIt was RESOLVED to approve the minutes of the previous meeting held on Monday 27 January 2025 as a correct record. | Approved | Open |
| 27 Jan 2025 | Minutes of the Previous MeetingIt was RESOLVED to approve the minutes of the previous meeting held on Thursday 14 November 2024 as a correct record. | Approved | Open |
| 14 Nov 2024 | Minutes of the previous meetingIt was RESOLVED to approve the minutes of the previous meeting held on Wednesday 19 June 2024 as a correct record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.