The committee agreed to defer a decision on the application in order to: · seek further details and assurance from Thames Water in relation to the impact of the proposed development on drainage and the maintenance of the sewerage infrastructure and how these would be mitigated; · seek further details on the location of the flooding incidents identified within the Flood Risk Assessment; and · seek further details on the proposals to alleviate concerns regarding the access of construction traffic to the site via Gooseacre Lane as part of the Construction Method Statement and Logistics Plan to be secured via condition.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
Case Ref: 21/3248 Page 1 of 2 Supplementary Information 15 December, 2021
Agenda Item 04 Supplementary Information Planning Committee on 15 December, Case No. 21/3248 2021 __________________________________________________ Location Lidding Road Garages, Lidding Road, Harrow Description Demolition of the existing garages and redevelopment to provide 3 self-contained flats and 5 dwellinghouses; with associated car parking, cycle storage, refuse storage, amenity space and landscaping
Agenda Page Number: 17-46
Bat survey
Paragraph 105 states ‘As T22 is proposed to be removed and has high bat roosting potential, further surveys are required in the form of dusk emergence and dawn re-entry surveys. In the event that a roost is discovered, a Natural England licence application may be required.’
The applicant has provided a Dawn Re-entry survey carried out in September 2021. This confirms that no bat roosts were found on site. The Preliminary Bat Roost Assessment has confirmed this. The updated conclusions determine that there would be no impacts on bat roosts as a result of the development. In the event that a bat roost is found during development, works will need to cease and it may be necessary to acquire a license from Natural England.
Amended landscaping plan
Paragraphs 88-95 discuss the impact on trees. The applicant has provided an amended landscaping design which alters that path from the site to the nearby Woodcock Park so that two trees are no longer required to be removed from the scheme. Additionally, the applicant has provided clarity on the number of trees lost on the scheme. There would be a total loss of 12 individual trees with the re-provision of 33 trees. As such there would be a net gain of 21 individual trees across the site. In addition to this, 8 groups of trees and 1 hedgerow are to be removed and 3 groups of trees and 1 hedgerow are to be partially removed.
As noted in the main report, the species of new trees are considered to be acceptable by the Council’s Tree Officer.
Conditions
It is recommended that the conditions are amended as set out below, and that an additional condition is attached.
Condition 2 – Plan numbers and documents have been updated to reflect the amended details received as described below
Condition 8 (Flood Risk), 11 (Ecology) and 12 (Materials) – Trigger points amended from "Prior to the commencement of works (other than demolition or site clearance)" to "Prior to the commencement of works (other than demolition, site clearance, laying of foundations or any other below ground work)"
Condition 12 – Reference to details of bin stores removed as this has been provided on the proposed floor plans.
Condition 10 – This condition has been amended to require compliance rather than submission following receipt of the Dawn re-entry surveys and the updated Preliminary bat roost assessment. It now reads:
The measures and recommendations set out in the ‘RT-MME-154334-01 Rev B – Preliminary Ecological Appraisal (Dated October 2021)’ and RT-MME-154334-02 Rev B - Preliminary Bat Roost Assessment (Dated December 2021) shall be implemented in full throughout the development.
DocSuppF Document Imaged Ref: 21/3248 Page 1 of 2 Reason: In order to ensure that any potential effects on protected species are adequately mitigated.
Additional condition – The following additional condition is recommended requiring the approval of a CEMP:
Prior to commencement of development a Construction Ecological Management Plan shall be submitted to and approved in writing by the Council. The approved measures shall be implemented in full.
Reason: In order to ensure that any potential effects on protected species are adequately mitigated.
Reason for pre-commencement condition: Construction impacts can arise at any time from the commencement of works, and adequate controls need to be in place from this time.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.