1.1This report provides an update on progress towards delivering against the Council’s housing target of 5,000 new affordable homes over the five-year period (2019 – 2024), at least 1,000 of which will be through the Council’s own New Council Homes Programme (NCHP).
1.2In December 2019, it was agreed that Cabinet would receive six monthly reports updating progress since the previous meeting and outlining key decisions required enabling the programme to continue until the next meeting six months hence. This report provides information on the progress since the last Cabinet Report in July 2021.
1.3This report provides a summary of the numbers of affordable homes that have been delivered and are expected be delivered, as well as updating on the progress made over the last 6 months, the numbers of additional homes/developments being assessed, with an indication of key issues, practical considerations and steps being taken moving forward.
1.4In July 2021, the Cabinet paper provided an overview of the bid made by the Council for additional grant funding as part of the London Mayor’s Affordable Housing Programme (AHP) 2021-26. This paper provides details of the successful outcome enabling the Council to continue tackling London’s housing crisis and meeting the housing needs of Brent residents.
2.0Recommendation(s)
That Cabinet:
2.1Note the contents of this report and progress to date on delivering both the New Council Homes Programme (NCHP) and other programmes and projects to deliver 5,000 new affordable homes in the borough by 2024.
2.2Note the demand forecasts and that the current programme will continue to reduce the demand for permanent Council homes.
2.3Note the need for approval of a capital investment of £135.1m to progress the delivery of the New Council Homes Programme as referred to in Financial Implications at 11.3 and 11.6.
2.4Delegated authority to the Strategic Director, Community Wellbeing, in consultation with the Lead Member for Housing and Welfare Reform, to award a construction contract in respect of the Watling Garden site for the reasons set out in in paragraph 7.8-7.10 of this report.
3.1In 2016, the London Mayor produced the Building Council Homes for Londoners prospectus and made capital grant funding available under the Affordable Homes Programme (AHP) 2016-2021. In 2018, Local Authorities were invited to bid to the Greater London Authority (GLA) for an allocation of Capital Grant from the AHP and, at the same time, the borrowing cap on the Housing Revenue Account (HRA) was lifted. This enabled the Council to consider a much larger building programme than previously.
3.2Following the first bid round, £66.5m was secured to deliver c850 new homes. This grew over the subsequent 3 years through negotiation to £103m and enabled the acquisition of additional sites such as Gloucester and Durham from Telford Homes and Notting Hill Genesis with further grant allocation of £30.55m.
3.3As a consequence of an ambitious approach to the programme, the Council has become one of the biggest Council House builders in London and as such a key partner to the GLA. It is anticipated that by 31st March 2022, 660 new affordable rented homes will have been completed since 2019 and 398 affordable rented homes handed over in 2021- 22 alone.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
8a. Appendix 1: Church End Detailed Market Design Drawing: Phase 1Appendix | 1.2 MB | Download |
PDF |
8b. Appendix 2: Church End Detailed Market Design Drawing: Phase 2Appendix | 1.2 MB | Download |
PDF |
Six Month Update on Supply of New Affordable HomesReport | 611 KB | DownloadRead as text |
Follow Cabinet at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... | Decided | Open |
| 9 Nov 2026 | Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... | Decided | Open |
| 9 Nov 2026 | Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... | Approved | Open |
| 9 Nov 2026 | Matters Arising (if any)None identified. | Decided | Open |
| 9 Nov 2026 | Petitions (if any)There were no petitions presented at the meeting. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.