Resolved
Granted planning permission subject to the conditions and informatives set out in the report and supplementary agenda.
Planning Committee decided this item on Wednesday 23 March 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
Granted planning permission subject to the conditions and informatives set out in the report and supplementary agenda.
Case Ref: 21/4690 Page 1 of 3 Supplementary Information 23 March, 2022
Agenda Item 04 Supplementary Information Planning Committee on 23 March, 2022 Case No. 21/4690 __________________________________________________ Location Windmill Court and car park, 52 Mapesbury Road, London, NW2 Description Demolition of car park and 1-2 & 5-18 Windmill Court maisonettes and redevelopment to provide 60 flats (Use Class C3) in two separate buildings rising to 7 storeys with car parking, cycle parking, access routes, refuse and recycling storage, amenity space, landscaping, boundary treatments, a substation and other associated works. Internal reconfiguration of the ground and first floors of the existing Windmill Court block and the creation of private terraces to 2 x ground floor (3&4 Windmill Court) flats alongside associated external works including new brickwork and cladding, windows and doors. Extension of the community room and associated external works including the provision of a new entrance and windows.
Agenda Page Number: 17-56
Further representations
With regard to surface water flood risk, Thames Water have recommend the following additional condition is attached to any consent, as requested within their original comments on the application:
“The development shall not be occupied until confirmation has been provided that either:-
1. All surface water network upgrades required to accommodate the additional flows from the development have been completed; or 2. A development and infrastructure phasing plan has been agreed with the Local Authority in consultation with Thames Water to allow development to be occupied. Where a development and infrastructure phasing plan is agreed, no occupation shall take place other than in accordance with the agreed development and infrastructure phasing plan.
Reason: Network reinforcement works are likely to be required to accommodate the proposed development.”
Amendments to main report
The schedule of accommodation table under para. 11 has been corrected to read as follows:
Affordable Housing Social Rent London Total Units % by unit %by Affordable habitable Rent room 1 Bed 3 (6) 6 (12) 9 15 9 2 Bed 2 (6) 30 (90) 32 53 50 3 Bed 2 (8) 16 (64) 18 30 38 4 Bed 1 (5) 1 2 3 Subtotal 8 (25) 52 (166) 60 (191) 100% 100% Affordable 13.3% 86.7% Percentage (by habitable room) Affordable 13.1% 86.9% Percentage (by unit)
DocSuppF Document Imaged Ref: 21/4690 Page 1 of 3 With regard to external amenity space for the proposed development, the table under para. 75 of the main committee report has been amended to reflect updated figures as a result of new requirements outlined under Policy BH13 of the recently adopted London Plan. The table therefore should read as follows:
Private space BH13 requirement Provision Shortfall Proposed Block A 690 349 341 Proposed Block B 540 297 243 Existing Block 2440 354 2086 including refurbished units Total private space 3670 1000 2670 Communal space Less proposed 4677 communal space (all existing and proposed blocks ) Overall total external 3,670 sqm 5,675 sqm +2007 sqm (Surplus) space
The updated table confirms that the amenity space provided would continue to exceed levels required under BH13, and therefore officers’ views set out in paras. 71-77 of the main report remain relevant.
Additional conditions:
Following correspondence with the applicant, it is requested that the following additional condition is attached to the permission, in relation to the affordable housing units secured by the scheme:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
04. Supp 21.4690 Windmill CourtReport | 118 KB | DownloadRead as text |
PDF |
04a. 21-4690 Windmill Court: AddendumAddendum | 142 KB | Download |
PDF |
21/4690: Windmill Court and car park, 52 Mapesbury Road, London, NW2Plan | 470 KB | Download |
Follow Planning Committee at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Aug 2026 | Apologies for AbsenceApologies for absence were received from Councillor Gallagher with Councillor Ahmadi-Moghaddam substituting. Apologie... | Decided | Open |
| 5 Aug 2026 | Declarations of interestsNo declarations of interest were made during the meeting. | Decided | Open |
| 5 Aug 2026 | Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the... | Approved | Open |
| 5 Aug 2026 | 26/0225 - Brent NHS Primary Care Trust, Wembley Centre For Health & Care, 116 Chaplin Road, Wembley, HA0 4UZGranted planning permission subject to: (1) The prior completion of a satisfactory legal agreement; and (2) The condi... | Agreed | Open |
| 5 Aug 2026 | Any Other Urgent BusinessThere was no other urgent business. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.