Granted planning permission subject to: (a) the prior completion of a legal agreement to secure the planning obligations set out within the report along with updates detailed within the supplementary agenda and following additional obligation agreed at the meeting: · Inclusion of an additional financial contribution of £15,000 towards the improvements to local parks and open spaces. (b) the conditions and informatives set out in the report and updates detailed within the supplementary agenda along with the inclusion of the following additional condition agreed at the meeting: · To require that the communal spaces are for use by all residents within the development.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
COMMITTEE REPORT Planning Committee on 14 June, 2022 Item No 04 Case Number 21/3754
SITE INFORMATION
RECEIVED 5 October, 2021
WARD Brondesbury Park
PLANNING AREA Brent Connects Kilburn
LOCATION 66 Cavendish Road, London, NW6 7XP
PROPOSAL Demolition of the existing residential building and the construction of a new part five, part six storey residential building, together with associated landscaping, cycle parking and refuse and recycling facilities.
PLAN NO’S See Condition 2
LINK TO DOCUMENTS When viewing this on an Electronic Device ASSOCIATED WITH THIS PLANNING Please click on the link below to view ALL document associated to case APPLICATION <https://pa.brent.gov.uk/online-applications/applicationDetails.do?activeTab=documents&keyVal=DCAPR_157273>
When viewing this as an Hard Copy
Please use the following steps
1. Please go to pa.brent.gov.uk 2. Select Planning and conduct a search tying "21/3754" (i.e. Case Reference) into the search Box 3. Click on "View Documents" tab
DocRepF Document Imaged Ref: 21/3754 Page 1 of 30 RECOMMENDATIONS A. That the Committee resolve to GRANT planning permission subject to the prior completion of a legal agreement to secure the following planning obligations:
1. Payment of the Council’s legal and other professional costs in (a) preparing and completing the agreement and (b) monitoring and enforcing its performance
2. Notification of material start 28 days prior to commencement
3. Financial contribution of £150,000 towards affordable housing provision in Brent.
4. Late stage viability review (drafted in line with standard GLA review clause wording) to be submitted at or after 75% occupation of the private residential development. An offsite affordable housing payment to be made where an uplift in profit above a break-even position is identified. Viability review to be based on an agreed Benchmark Land Value of £3.368m and developer profit of 17.5%. Not more than 90% of the private dwellings to be occupied until viability review approved in writing by the LPA.
5. Sustainability and energy
a. Detailed design stage energy assessment. Initial carbon offset payment if zero-carbon target not achieved on site. b. Post-construction energy assessment. Final carbon offset payment if zero-carbon target not achieved on site. c. ‘Be seen’ energy monitoring requirements
That the Head of Planning is delegated authority to negotiate the legal agreement indicated above.
B. That the Head of Planning is delegated authority to issue the planning permission and impose conditions and informatives to secure the following matters:
Conditions:
Compliance
1. Three year rule 2. Approved documents 3. Withdraw permitted development rights for small HMOs 4. Non-Road Mobile Machinery 5. Provision of bin and cycle storage 6. Internal noise levels 7. Internal vibration levels 8. Car free development 9. Compliance with overheating assessment 10. Compliance with acoustic report 11. Highways works 12. Ecology and protected species
Pre-commencement
13. Construction method statement 14. Arboricultural method statement 15. Site investigation for contaminated land
During construction
16. Materials samples 17. Landscaping scheme
Pre-occupation 18. Remediation and verification of contaminated land 19. External lighting 20. Details of PV panels and heat pumps
Informatives:
1. CIL Liability 2. Thames Water 3. Network Rail 4. Bats and other protected species 5. Construction hours 6. Soil quality
C. That the Head of Planning is delegated authority to make changes to the wording of the committee’s decision (such as to delete, vary or add conditions, informatives, planning obligations or reasons for the decision) prior to the decision being actioned, provided that the Head of Planning is satisfied that any such changes could not reasonably be regarded as deviating from the overall principle of the decision reached by the committee nor that such change(s) could reasonably have led to a different decision having been reached by the committee
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.