Cabinet RESOLVED (1) To approve the inviting of a tender using a direct award process under the Network Homes Contractor Framework agreement on the basis of the pre-tender considerations set out in paragraph 3.6 of the report. (2) To delegate authority to award the contract for the Morland Gardens Redevelopment Design and Build Contract following the successful outcome of the tender exercise to the Strategic Director, Regeneration and Environment, in consultation with the Cabinet Member for Finance, Resources & Reform.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report concerns the redevelopment at 1 Morland Gardens, Stonebridge to deliver a new education centre, new council homes, affordable workspace, a public facing café, and public realm improvements. This report requests approval to invite a tender using a direct award procedure under the Network Homes Contractor Framework and approve the pre tender considerations as required by Contract Standing Orders 88 and 89.
2.0Recommendation(s)
Cabinet is requested to: 2.1 Approve the inviting of a tender using a direct award process under the Network Homes Contractor Framework agreement on the basis of the pre-tender considerations set out in paragraph 3.6 of the report.
2.2Delegate authority to award the contract for the Morland Gardens Redevelopment Design and Build Contract following the successful outcome of the tender exercise to the Strategic Director, Regeneration and Environment, in consultation with the Cabinet Member for Finance, Resources & Reform.
Background
3.1On 14 January 2020, Cabinet approved a number of recommendations relating to the Morland Gardens redevelopment. Cabinet approved to support the proposal to invest up to £43m to deliver a state of the art adult education centre, 65 new affordable homes, 675 sq. metres of affordable workspace for start-up businesses from the local community and a public facing cafe. This also includes the cost of the 2 year service decant and £6.5m of GLA affordable housing grant.
3.2Since then, the council has developed the design and received planning permission for the scheme in October 2020. A stopping up order has been submitted for the parts of the public highway required for development under s247 of the Town and Country Planning Act 1990.
3.3The council also sought to procure a contractor for the scheme in May 2021 and May 2022 but both tender opportunities were unsuccessful. The first tender opportunity did not elicit any bids. The second tender opportunity elicited three bids and the council recommended the award of the contract as detailed in the Key Officer Decision report of 20 May 2022. This decision was subject to “call in”, during which period the Framework under which the contract was awarded, expired and so the council is required to procure a contractor again under a further procurement process. Resources and Public Realm Scrutiny Committee considered the “call in” at its meeting on 9 June 2022 and determined that the Committee did not object to the decision and the decision could therefore be implemented.
3.4The estimated contract value of the procurement is £38m and having reviewed procurement options, Officers recommend the use of a direct award process under the Network Homes Contractor Framework agreement (the “Framework”). A direct award process using the Framework offers an efficient and effective route to appoint an appropriately qualified and experienced contractor to deliver the scheme. Approval was obtained from the Director of Legal, HR, Audit and Investigations on 14 June 2022 that it was legally permissible for the council to participate in the Framework.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.