(1) The prior completion of a legal agreement to secure the planning obligations set out in the report and supplementary agenda; (2) The conditions and informatives set out in the report and supplementary agenda, as amended below; Condition 18 – to include further clarification on the number of Electric Vehicle Charging points. Condition 23 – to include additional details regarding the size, species and maturity of trees in the Landscaping Scheme. (3) Referral of the application for Stage 2 review by the Mayor of London.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
COMMITTEE REPORT Planning Committee on 13 July, 2022 Item No 04 Case Number 21/1124
SITE INFORMATION
RECEIVED 26 March, 2021
WARD Kingsbury
PLANNING AREA Brent Connects Kingsbury & Kenton
LOCATION 363 Edgware Road, London, NW9 6AF
PROPOSAL Demolition of showroom and multi-storey carpark building and erection of a ground plus up to 19 storey building to provide residential units (Use Class C3) with commercial use (Use Class E) at ground floors, together with associated parking at basement and landscaping
PLAN NO’S Please see Condition 2.
LINK TO DOCUMENTS When viewing this on an Electronic Device ASSOCIATED WITH THIS PLANNING Please click on the link below to view ALL document associated to case APPLICATION <https://pa.brent.gov.uk/online-applications/applicationDetails.do?activeTab=documents&keyVal=DCAPR_154392>
When viewing this as an Hard Copy
Please use the following steps
1. Please go to pa.brent.gov.uk 2. Select Planning and conduct a search tying "21/1124" (i.e. Case Reference) into the search Box 3. Click on "View Documents" tab
DocRepF Document Imaged Ref: 21/1124 Page 1 of 47 RECOMMENDATIONS That the Committee resolve to GRANT planning permission subject to:
Referral to the Mayor of London (stage II referral)
The prior completion of a legal agreement to secure the following planning obligations:
1. Payment of the Council’s legal and other professional costs in (a) preparing and completing the agreement and (b) monitoring and enforcing its performance
2. Notification of material start 28 days prior to commencement
3. Provision of 20 units [10 x 2bed and 10 x 3bed] as London Affordable Rent, disposed on a freehold / minimum 125 year leasehold to a Registered Provider and subject to an appropriate Affordable Rent nominations agreement with the Council, securing 100% nomination rights for the Council on initial lets and 75% nomination rights for the Council on subsequent lets.
4. Provision of 6 Shared Ownership units [3 x 1bed and 3 x 2bed] as defined under section 70(6) of the Housing & Regeneration Act 2008, subject to London Plan policy affordability stipulations that total housing costs should not exceed 40% of net annual household income, disposed on a freehold / minimum 125 year leasehold to a Registered Provider.
5. Early stage viability review (drafted in line with standard GLA review clause wording) to be submitted where material start does not commence within 2 years of planning permission being granted. Viability review to set out details of additional on-site affordable housing where uplift in profit is identified. Viability review to be based on an agreed Benchmark Land Value of £5.08m.
6. Late stage viability review (drafted in line with standard GLA review clause wording) to be submitted at or after 75% occupation of the private residential development. An offsite affordable housing payment to be made where an uplift in profit is identified. Viability review to be based on an agreed Benchmark Land Value of £5.08m. Not more than 90% of the private dwellings to be occupied until viability review approved in writing by the LPA.
7. Sustainability and energy
a. Detailed design stage energy assessment. Initial carbon offset payment if zero-carbon target not achieved on site. b. Post-construction energy assessment. Final carbon offset payment if zero-carbon target not achieved on site. c. ‘Be seen’ energy monitoring requirements
8. Financial contributions (indexed from the date of committee resolution)
a. To Brent Highways for implementation of a Controlled Parking Zone in the area (£80,000) b. To TfL for public transport improvements (£30,000) c. To Brent Council for enhancement of off-site play provision in Grove Park (£50,000).
9 Submission and approval of Residential and Commercial Travel Plans prior to occupation of the development and the provision of three years' free membership of a Car Club for the first resident of each residential unit and one year's free membership for commercial users.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.