Resolved
Cabinet
Cabinet decided this item on Monday 6 February 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Cabinet
1.1This report concerns the award of a contract for the purchase and management of future bike hangars and the transfer of the management and maintenance of current bike hangars.
1.2Cabinet approved a report titled “Brent Bike Hangars” on 20th June 2022, which detailed the current arrangements, aims and objectives to reduce and standardise the annual costs for future and existing bike hangar users, and the tendering of a contract.
1.3This report requests approval to award contracts as required by Contract Standing Order 88. It summarises the process undertaken in tendering this
Cabinet Date 06 February 2023 contract and, following the completion of the evaluation of the tenders, recommends to whom the contracts should be awarded, setting out the financial savings and benefits associated with the contract.
That Cabinet:
2.1Approves the award of a contract for the purchase and management of future bike hangars and the transfer of the management and maintenance of current bike hangars to Lock It Safe Ltd for an initial contract period of three (3) years, with an option to extend for up to a further two (2) years on an annual basis.
2.2Notes that the value of the contract referred to in 2.1 above is estimated to be £90,000 for year 1 but that this value may increase if further funding is made available through S106 developer funding and Transport for London Local Implementation Plan funding in future years.
3.1Following a successful trial in 2016, the Council has continued to install bike hangars when funding has been available, and there are currently 104 bike hangars in Brent which includes 5 on Brent owned housing estates.
3.2Originally Cyclehoop Ltd (“Cyclehoop”) were the main providers for bike hangars in the borough, but due to their limited supply and in order to meet growing demand for bike hangars in the borough, Cabinet approved the use of the Waltham Forest Framework on 9th March 2020, which enabled the use of both Cyclehoop and Falco UK Ltd (“Falco”) as suppliers to provide, install and manage these assets.
3.3Once a bike hangar has been installed the supplier is responsible for the management, maintenance, and any associated repairs. If a bike hangar is damaged and the bikes need to be removed, the supplier will contact the residents to inform them of this and will arrange for the repairs to be completed as soon as practicable.
3.4To date, the Council has received approximately 520 individual requests for bike hangar spaces and this number is increasing on a weekly basis. Information on cycle parking and requesting a bike hangar can be found on the Council’s website at: Cycle parking, repair stations and maintenance | Brent Council
3.5In 2020, Scrutiny Committee raised concerns about the cost of bike hangars to residents and made comparisons to the cost of a parking permit. Whilst officers are of the view that these are not clearly comparable as the cost of providing, managing, and maintaining a bike hangar would exceed that of a parking space,
Cabinet Date 06 February 2023 it was agreed that officers would explore opportunities to reduce costs to residents, as the numbers increase.
3.6There are currently 104 bike hangar units installed around the borough. Under the current arrangements, there are three tiers of rental fees for hangars.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
17a. Appendix A: Tender Evaluation GridAppendix | 71 KB | Download |
PDF |
17b. Appendix B: Product ImageAppendix | 83 KB | Download |
PDF |
Authority to award contract for the provision and management of bike hangars in BrentReport | 279 KB | DownloadRead as text |
Follow Cabinet at Brent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Nov 2026 | Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... | Decided | Open |
| 9 Nov 2026 | Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... | Decided | Open |
| 9 Nov 2026 | Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... | Approved | Open |
| 9 Nov 2026 | Matters Arising (if any)None identified. | Decided | Open |
| 9 Nov 2026 | Petitions (if any)There were no petitions presented at the meeting. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.