London Borough of Brent
Cabinet, Monday 22 May 2023 at 10.00am

Authority to tender contract to design, build, operate and maintain the South Kilburn District Heat Network

Approved Executive 1 paper

Cabinet approved this item on Monday 22 May 2023. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Cabinet RESOLVED to: (1) Approve inviting tenders to Design, Build, Operate and Maintain the South Kilburn Heat Network on the basis of the pr -tender considerations set out in paragraph 3.11 of the report. (2) Approve officers evaluating the tenders referred to in (1) above on the basis of the evaluation criteria set out in paragraph 3.11 of the report. (3) Note the award of a grant of £4.7m from the Green Heat Network Fund is to be applied towards the costs of constructing the district heat network and £0.45m towards the council’s costs to procure the network. (4) Note that the project utilises S106 funds specifically allocated as set out in paragraph 5.4 of the report. (5) Approve the allocation of an estimated £5.3m from prudential borrowing to fund the remainder of the scheme.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1This report concerns the district heat network in South Kilburn which will provide low carbon heat to the South Kilburn regeneration programme. This report requests approval to invite tenders in respect of a contract for a Design, Build, Operate and Maintain contractor, through a competitive dialogue procedure, as required by Contract Standing Orders 88 and 89.

1.2This report highlights the offer of £4.7m of grant from the Green Heat Network Fund (GHNF) towards the costs of constructing the district heat network and

Contract Procurement and Management Guidelines Precedent 1(a) Cabinet Authority to Tender Report June 2019 Page 1 £0.45m towards the council’s costs to procure the network including internal and external costs.

2.0Recommendation(s)

That Cabinet:

2.1Approves inviting tenders to Design, Build, Operate and Maintain the South Kilburn Heat Network on the basis of the pre - tender considerations set out in paragraph 3.11 of the report.

2.2Approves Officers evaluating the tenders referred to in 2.1 above on the basis of the evaluation criteria set out in paragraph 3.11 of the report.

2.3Notes the award of a grant of £4.7m from the Green Heat Network Fund is to be applied towards the costs of constructing the district heat network and £0.45m towards the council’s costs to procure the network.

2.4Notes that the project utilises S106 funds specifically allocated as set out in paragraph 5.4.

2.5Approves the allocation of an estimated £5.3m from prudential borrowing, to fund the remainder of the scheme.

3.0Detail

3.1The South Kilburn District Heat Network will be a network of pipes feeding heat to the buildings in South Kilburn.

3.2The use of a district heat network is in-line with GLA policy and Brent’s Local Plan. For South Kilburn, the heat network aims to initially provide low carbon heat but ultimately to provide zero carbon heat to developments in South Kilburn which form part of the South Kilburn Regeneration Programme along with additional connections where appropriate and practicable.

3.3The Critical Success Factors for this project are:  Ensures affordable low carbon heat to all residents in South Kilburn buildings which are connected to the network;  Provides low carbon heat to developments in South Kilburn in order to help enable them to comply with the energy requirements of the London Plan;  Provides a service which residents believe is satisfactory and value for money;  Provides CO2 savings contributing to the Council’s aspiration to be net zero carbon by 2030;  Delivers an employment and training programme to enable local residents to work on the installation and management of the project.

Contract Procurement and Management Guidelines Precedent 1(a) Cabinet Authority to Tender Report June 2018

 London Borough Of Brent 3.4 Having sought and reviewed external consultancy advice on a range of delivery options, Officers’ preferred way to deliver the area wide network of pipes supplying the buildings within the South Kilburn Regeneration Programme (the “Estate”) with heat and hot water is that Brent Council will directly contract and client a single contractor who will design, build, operate and maintain the generating system and its distribution pipes to connected buildings on the Estate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Authority to tender contract to design, build, operate and maintain the South Kilburn District Heat NetworkReport 433 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 22 attended
MB
Councillor Muhammed Butt Leader of the CouncilChair, present
MP
Councillor Mili Patel Deputy Leader and Cabinet Member for Finance, Resources & ReformVice-Chair, present
FD
Councillor Fleur Donnelly-Jackson Cabinet Member for Customers, Communities and CultureCommittee Member, present
HF
Councillor Harbi Farah Cabinet Member for Safer Communities & Public ProtectionCommittee Member, present
GG
Councillor Gwen Grahl Cabinet Member for Children, Young People & SchoolsCommittee Member, present
PK
Councillor Promise Knight Cabinet Member for Housing, Homelessness & Renters SecurityCommittee Member, present
NN
Councillor Neil Nerva Cabinet Member for Public Health & Adult Social CareCommittee Member, present
KS
Councillor Krupa Sheth Cabinet Member for Environment, Infrastructure & Climate ActionCommittee Member, present
ST
Councillor Shama Tatler Cabinet Member for Regeneration, Planning & GrowthCommittee Member, present
BC
Councillor Bhagwanji ChohanCouncillor, in attendance
KS
Councillor Ketan ShethCouncillor, in attendance
A
AdministratorOfficer, expected

All 22 on the meeting page

On this subject at Brent

Search all
  1. Authority to tender contract to design, build, operate and maintain the South Kilburn District Heat NetworkThis decision
  2. Authority to invite tenders for Homecare Services for Adult Social Care and Children and Young People with DisabilitiesApproved
  3. Authority to Tender for the Appointment of a Social Investment Backed Design & Delivery Partner to support the sourcing of suitable Providers for Housing Related Support ServicesApproved
  4. Authority to invite tenders for care and support at six supported living sites for adults with Mental Health DifficultiesApproved
  5. Authority to invite tenders in respect of appointing Charging Point Operator(s) to supply, install, operate and maintain electric vehicle charge pointsApproved
  6. Authority to Tender for a Day Opportunities Framework for the Provision of Community Based Activities for AdultsDecided

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies