Granted planning permission subject to the referral of the application to the Mayor of London (stage 2 referral) and the prior completion of a legal agreement to secure the planning obligations as detailed in the Committee report; and the conditions and informatives as set out in the Committee report and supplementary report.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
COMMITTEE REPORT Planning Committee on 9 August, 2023 Item No 05 Case Number 22/3965
SITE INFORMATION
RECEIVED 18 November, 2022
WARD Wembley Park
PLANNING AREA Brent Connects Wembley
LOCATION 1-4 and 9 Watkin Road, Wembley, HA9 0NL
PROPOSAL Demolition of existing buildings and construction of two new buildings to provide commercial floorspace (Use Class: E) and student accommodation bedspaces (Use Class: Sui Generis), associated access and highways works, amenity space, cycle parking spaces, disabled car parking spaces and refuse/recycling stores.
PLAN NO’S See condition 2.
LINK TO DOCUMENTS When viewing this on an Electronic Device ASSOCIATED WITH THIS PLANNING Please click on the link below to view ALL document associated to case APPLICATION <https://pa.brent.gov.uk/online-applications/applicationDetails.do?activeTab=documents&keyVal=DCAPR_162738>
When viewing this as an Hard Copy
Please use the following steps
1. Please go to pa.brent.gov.uk 2. Select Planning and conduct a search tying "22/3965" (i.e. Case Reference) into the search Box 3. Click on "View Documents" tab
DocRepF Document Imaged Ref: 22/3965 Page 1 of 52 RECOMMENDATIONS That the Committee resolve to GRANT planning permission subject to the referral of the application to the Mayor of London (stage 2 referral) and the prior completion of a legal agreement to secure the following planning obligations:
1. Payment of the Council’s legal and other professional costs in (a) preparing and completing the agreement and (b) monitoring and enforcing its performance.
2. Notification of material start 28 days prior to commencement
3. Nominations agreement for student accommodation including affordable student accommodation – Agreement with one or more Higher Education Providers to secure nomination rights for at least 51% of the student bedrooms (315 bedrooms), including 35% (216 bedrooms) to be provided as affordable student accommodation (as defined within the London Plan), comprising a mix of units of different types and proportion of wheelchair accessible units to reflect the overall mix. Communal facilities including refuse storage, cycle storage, internal and external communal areas to be available equally to all students without additional charges. Early stage viability review if substantial implementation does not occur within two years.
4. Training and employment of Brent residents - Prior to a material start: a. to inform Brent Works in writing of the projected number of construction jobs and training opportunities and provide a copy of the Schedule of Works; b. to prepare and submit for the Council’s approval an Employment Training Plan for the provision of training, skills and employment initiatives for residents of the Borough relating to the construction phase and operational phase of the Development c. financial contribution to Brent Works for job brokerage services.
5. Sustainability and energy a) Detailed design stage energy assessment. Initial carbon offset payment if zero-carbon target not achieved on site. b) Post-construction energy assessment. Final carbon offset payment if zero-carbon target not achieved on site. c) ‘Be seen’ energy monitoring requirements
6. Student Travel Plan – Submission and implementation of Travel Plan for student accommodation and commercial uses, with a target of 100% of trips to be made by foot, cycle or public transport , including monitoring and review arrangements under the i-TRACE or TRICS survey methodology,
7. Submission, approval and implementation of a waste management plan including commitment to fund and arrange independent collections from the site. Collections must be entirely privately funded and arranged unless an alternative plan showing a revised layout is submitted and agreed with the LPA which meets Veolia's requirements in respect of carrying distances.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.