Granted planning permission subject to: · referral of the application to the Mayor of London (Stage 2 referral) and prior completion of a legal agreement to secure the planning obligations set out in the Committee report; · the conditions and informatives as set out in the Committee and Supplementary report including an amendment to the Section 106 Agreement Heads of Terms to ensure that use of the £10,000 contribution secured towards the enhancement and improvement to public open spaces in the borough was focussed within the vicinity of the development.
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
COMMITTEE REPORT Planning Committee on 7 August, 2024 Item No 05 Case Number 22/2477
SITE INFORMATION
RECEIVED 12 July, 2022
WARD Alperton
PLANNING AREA Brent Connects Wembley
LOCATION 245-249 and 253 Ealing Road, Wembley, HA0 1EX
PROPOSAL Redevelopment of site to provide two buildings accommodating residential units, the use of ground floor as a Community Use (Use Class: F2) with additional affordable workspace (Use Class: E) at ground floor level, associated vehicular crossover, car and cycle parking spaces, refuse storage, amenity spaces, landscaping and associated works
PLAN NO’S See condition 2.
LINK TO DOCUMENTS When viewing this on an Electronic Device ASSOCIATED WITH THIS PLANNING Please click on the link below to view ALL document associated to case APPLICATION <https://pa.brent.gov.uk/online-applications/applicationDetails.do?activeTab=documents&keyVal=DCAPR_161085>
When viewing this as an Hard Copy
Please use the following steps
1. Please go to pa.brent.gov.uk 2. Select Planning and conduct a search tying "22/2477" (i.e. Case Reference) into the search Box 3. Click on "View Documents" tab
DocRepF Document Imaged Ref: 22/2477 Page 1 of 50 RECOMMENDATIONS That the Committee resolve to GRANT planning permission subject to the application’s referral to the Mayor of London (Stage 2 referral).
That the Head of Planning is delegated authority to issue the planning permission and impose conditions and informatives to secure the following matters:
1. Payment of the Council’s legal and other professional costs in (a) preparing and completing the agreement and (b) monitoring and enforcing its performance. 2. Notification of material start 28 days prior to commencement.
3. Provision of 32 homes (10 Shared Ownership and 22 London Affordable Rent) at 35.5% per habitable room and an early and late-stage review mechanism, and subject to an appropriate Affordable Rent nominations agreement with the Council, securing 100% nomination rights on first lets and 75% nomination rights on subsequent lets for the Council)
4. Training and employment of Brent residents - Prior to a material start: a) to inform Brent Works in writing of the projected number of construction jobs and training opportunities and provide a copy of the Schedule of Works; b) to prepare and submit for the Council’s approval an Employment Training Plan for the provision of training, skills and employment initiatives for residents of the Borough relating to the construction phase and operational phase of the Development; c) financial contribution (estimated to be £27,500 for construction fee and £7,150 for operational fee) to Brent Works for job brokerage services., any additional charge against the shortfall in provision of jobs as identified within the employment and training plan.
5. The Class E Workspace floorspace to be provided as affordable workspace to be delivered as follows: a) In perpetuity b) At no more than 50% of comparable local market rates c) Floorspace is to be provided as affordable research and development, light industrial, flexible office and studio workspace (Use Class E(g)) d) Managed by one of the Councils approved affordable workspace operators e) With a minimum lease term of 15 years or a minimum long-lease of 125 years f) To a minimum fit-out standard as set out in the Affordable Workspace SPD
6. Sustainability and Energy;
· Detailed design stage energy assessment based on Part L 2021 of Building Regulations with a minimum 35% reduction on site. Initial carbon offset payment to be paid prior to material start if zero-carbon target not achieved on site. · Post-construction energy assessment. Final carbon offset payment upon completion of development if zero-carbon target not achieved on site. · Be seen’ energy performance monitoring and reporting
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.