Approval to Proceed with Alternative Heat Supply for Willesden Green Library- Public Sector Decarbonisation Scheme (PSDS) Phase 4
ApprovedExecutive2 papers
AI summaryBrent Cabinet approves £917,628 budget to install an air source heat pump at Willesden Green Library under the PSDS Phase 4 grant, with all grant funds to be committed by 31 March 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedAlternative heat supply for Willesden Green Library
Money£917,628Total capital budget, Salix grant plus Carbon Offset Fund
What happens nextProceed with installationVariation to existing contract; target completion 19 June 2026
Who it affectsLibrary users, staff, Newman Close residentsTwo Brent corporate sites: library and cemetery
What was decided
Cabinet approved a total capital budget of £917,628 to install an air source heat pump and other energy efficiency measures at Willesden Green Library and Willesden New Cemetery, funded by a £667,628 Salix grant and £250,000 from the Carbon Offset Fund. Report 2.1, 2.2, 5.1, 5.2
Cabinet acknowledged the Equality Impact Assessment and noted that 80% of consultation respondents (4 out of 5) supported the Council leaving the existing energy centre to set up its own heating source. Report 2.3, 7.1
Cabinet noted the Salix grant spending deadline of 31 March 2026 and the risk that completion is not expected until 19 June 2026, requiring the remaining costs to be covered by the Carbon Offset Fund. Report 2.4, 5.3, P32
Why
The existing heating arrangement at Willesden Green Library is not fit for purpose and negotiations with the Right to Manage company did not result in a heat agreement, so the Council sought a separate route through PSDS Phase 4 funding. Report 3.1, 3.3, 3.5
An air source heat pump would allow the Council to internalise heat production, reduce energy use and maintenance costs, and contribute to the Council's 2030 Net Zero target with an estimated 2,708 tonnes of CO2 saved over the project's lifetime. Report 3.7, P18, P19, P20, 8.1
Following public consultation in August and September 2025 and a member briefing on 7 July 2025, officers recommended proceeding with the project. Report 3.12, 4.1, 4.2
What happens next
Officers will work with consultants to progress the project quickly, including obtaining planning permission and executing a contract variation under Regulation 72 of the Public Contracts Regulations 2015. Report 6.4, 9.1
An investment grade proposal is targeted for 5 December 2025, construction contract agreement for 19 January 2026, procurement of all parts by 23 March 2026, and on-site completion by 19 June 2026. Report P32
A communication strategy will be developed to manage the works, the transfer of heat supply, and continued engagement with residents connected to the Energy Centre, library users and staff. Report 10.1, P47, P48
The money
£917,628 Total capital budget for the two projects Report 2.1, 5.1
£807,000 Installation costs within the capital budget Report 2.1
£111,000 Contingency and staff capitalisation costs Report 2.1, 5.1
£667,628 Salix grant funding portion of the capital budget Report 2.2, 5.2
£250,000 Contribution from Brent's Carbon Offset Fund Report 2.2, 5.2
£742,016 Cost of the heat pump at Willesden Green Library including fitting Report 5.1
£64,523 Insulation measures at Willesden New Cemetery Report 5.1
£668K Government grant-funding secured under PSDS P4 across the two sites Report 3.6
Options considered
Chosen: Proceed with the alternative heat supply project at Willesden Green Library and Willesden New Cemetery. Existing heating unfit for purpose, PSDS P4 grant secured, 80% of consultation respondents supportive, delivers carbon and cost savings Report 3.1, 3.12, 7.1
Rejected: Continue negotiations with the Right to Manage company for the existing energy centre heat supply. Two previous attempts did not result in a resolution; the RTM has indicated alternative arrangements should be considered Report 3.3, 6.2
Implications
Financial: Failure to spend the Salix grant by 31 March 2026 would result in forfeiture of unspent grant; the £250,000 Carbon Offset Fund contribution will cover any unspent grant and costs after the deadline. Report 5.3
Legal: The contract variation will be carried out under Regulation 72 of the Public Contracts Regulations 2015 and must comply with the Council's Contract Standing Orders and Financial Regulations. Report 6.1, 6.4
Equalities: The Equality Impact Assessment found no disproportionate impacts on protected groups and no specific equality concerns; free energy advice and external funding avenues have been signposted to residents. Report 7.1, 7.2, 3.11
Climate: The works are expected to reduce carbon emissions by approximately 2,708 tonnes CO2 equivalent over the project lifetime, contributing to the Council's 2030 Net Zero target and a 5% annual reduction across the corporate estate. Report 3.7, P20, 8.1
Risk: There is a risk the project will not complete by 31 March 2026, requiring the Carbon Offset Fund to cover remaining costs; temporary physical disruption is anticipated during installation. Report 5.3, 9.1
Other: The works are expected to deliver reductions in maintenance and service charge costs, and bring the heating system under the Council's direct control. Report 3.7, P18, P19
Who and where
Users and staff of Willesden Green Library Report 3.1, 7.1, 9.1
Residents of the 95 flats at Newman Close connected to the existing Energy Centre Report 3.3, 3.9, 4.2
Willesden New Cemetery (energy efficiency and insulation works) Report P16, 5.1
Brent Council as the operator and asset owner of both sites Report 3.1, 3.5, 6.2
Timeline
June 2015: Linden Homes and Galliford Try achieved Practical Completion for the new Willesden Cultural Centre including 95 residential units Report 3.3
November 2024: Brent Council's Energy Team applied for PSDS P4 funding for energy efficiency works at two corporate sites Report 3.5
21st March 2025: Brent Council confirmed successful PSDS P4 bid securing £668K of government grant funding Report 3.6
7th July 2025: Officers held a member briefing session on the project proposals Report 4.1
Saturday 9th August and Thursday 21st August: Two in-person public consultation meetings were held with residents of Newman Close Report 3.9, 4.2
20th September 2025: Public consultation closed and the EIA was updated to reflect resident feedback
17th November 2025: Cabinet considered and approved the report
6pm on Monday 24 November 25: Deadline for submission of call-in
5th December 2025: Target date for Investment Grade Proposal (Construction) Report P32
19th January 2026: Target date for Construction Contract Agreement Report P32
23rd March 2026: Target date for procurement of all parts complete Report P32
31st March 2026: Grant invoicing deadline stipulated by Salix Report 2.4, 5.3, P32
19th June 2026: Target date for completion on-site and commissioning Report P32
Plain English for the jargon
PSDS Phase 4: Public Sector Decarbonisation Scheme Phase 4, a government grant programme funding energy efficiency and low carbon heating works in public sector buildings
Salix: Salix Finance, the public sector funding body administering the PSDS grant
ASHP: Air Source Heat Pump, a low carbon heating system extracting heat from outside air
BMS: Building Management System, used to control and monitor building services
EIA: Equality Impact Assessment, an analysis of how a proposal may affect people with protected characteristics
RTM: Right to Manage company (Newman Close), which manages the existing Energy Centre serving the flats and library
Carbon Offset Fund: Brent Council fund used as match funding for the project
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
Cabinet RESOLVED to: (1) Approve a total capital budget of £917,628, which included £807,000 for installation, £111,000 contingency, and staff capitalisation costs. (2) Note that the total capital budget of £917,628 would be sourced from £667,628 Salix grant and £250,000 from the Carbon Offset Fund. The budget would be split across delivery of the following two projects: Willesden Green Library and Willesden New Cemetery. (3) Acknowledge the findings of THE Equality Impact Assessment (detailed within Appendix 1 of the report) regarding the installation of an alternative heat supply at Willesden Green Library that included the results of a public consultation undertaken. (4) Note the grant spend timeline stipulated by Salix and its implication on the delivery of the project, particularly when it comes to the requirement to spend all grant funding by March 31 st , 2026, as set out in section 5.3 – 5.4 of the report. (5) Note the significant financial, energy and carbon savings that the delivery of an alternative heat supply at Willesden Green Library would provide as set out section 3.7 of the report. Eligible for call-in: Yes Deadline for submission of call-in: 6pm on Monday 24 November 25
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1This report considers the recommendation for the installation of an alternative, low carbon heating solution at Willesden Green Library and other energy conservation measures following Brent Council’s successful bid for the Public Sector Decarbonisation Scheme Phase 4 (PSDS P4). The project aims to deliver significant carbon savings, improve energy efficiency, and reduce operational costs. 2.0 Recommendation(s)
2.1That Cabinet approves a total capital budget of £917,628, which includes £807,000 for installation, £111,000 contingency, and staff capitalisation costs.
2.2Cabinet notes that the total capital budget of £917,628 will be sourced from £667,628 Salix grant and £250,000 from the Carbon Offset Fund. The budget will be split across delivery of the following two projects: Willesden Green Library and Willesden New Cemetery.
2.3Cabinet acknowledges the findings of an Equality Impact Assessment (at Appendix 1) regarding the installation of an alternative heat supply at Willesden Green Library that includes the results of a public consultation undertaken.
2.4Cabinet notes the grant spend timeline stipulated by Salix and its implication on the delivery of the project, particularly when it comes to the requirement to spend all grant funding by March 31st, 2026, as set out in points 5.3 – 5.4.
2.5Cabinet notes the significant financial, energy and carbon savings that the delivery of an alternative heat supply at Willesden Green Library will provide as set out in point 3.7.
3.0Detail
Cabinet Member Foreword
3.1This report sets out proposals to proceed with the installation of a new low carbon heating system at Willesden Green Library. The existing heating arrangement is not fit for purpose and has presented ongoing operational challenges. The proposed works will deliver a reliable and energy-efficient solution through the installation of an Air Source Heat Pump, supported by other energy-saving measures.
3.2These proposals align with the Council’s strategic priorities as set out in the Borough Plan 2023 - 2027, notably:
A Cleaner, Greener Future: delivering a low-carbon, energy-efficient building with active travel facilities.
Background
3.3Linden Homes and Galliford Try (contractor) achieved Practical Completion in June 2015 for the design and construction of the new Willesden Cultural Centre, which includes a new library and 95 residential units. Under the development agreement between the Council and Linden Homes, heating and hot water were to be provided via the Energy Centre. The Council attempted to formalise a heat agreement on two occasions, but negotiations with the Right to Manage (RTM) company, Newman Close, did not result in a resolution. 3.4 The RTM has since indicated that Brent Council should explore alternative heating solutions for Willesden Green Library and has expressed a willingness to support the Council during any transition period for a new system.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.