Statement of Accounts 2024-25

Approved Finance 4 papers

AI summaryBrent's Audit and Standards Committee delegates sign-off of 2024-25 accounts to its chair and approves £19,000 in additional audit fees, with signing expected before the 27 February 2026 backstop date.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedLetters of representation and final accounts approval delegated
Money£19,000 additional fee approvedOn top of £545,235 original audit fee
What happens nextAccounts to be signed by 27 February 2026Government backstop date for 2024/25
Who it affectsBrent Council and Pension FundFormal audited accounts for 2024/25

What was decided

Approval of the draft letters of representation to Grant Thornton for the Council and Pension Fund was delegated to the Corporate Director of Finance & Resources. Report 2.1, P15

Approval to sign off the final statement of accounts for 2024-25 was delegated to the Chair of the Audit & Standards Committee, subject to written assurance that all outstanding matters in the Audit Findings report have been made. Report 2.2

The audit fees for 2024-25 were approved, as set out in section 3.2.9 of the report. Report 2.3, P16

Why

External auditors Grant Thornton are still finalising the audit of the 2024/25 accounts and their Audit Findings Report, with most key areas reviewed but some awaiting senior management review. Report P10, P11

A government backstop date of 27 February 2026 applies to 2024/25 accounts; if the audit cannot be completed by then the auditor can issue a modified or disclaimed opinion. Report P13, P14

Additional work was required on Plant, Property & Equipment and Leases due to poor record keeping by service areas in recent years. Report P11, P16

What happens next

The Corporate Director of Finance & Resources will approve the letters of representation to Grant Thornton, with any significant changes reported back to the Audit and Standards Advisory Committee. Report 2.1

The Chair of the Audit & Standards Committee will sign off the final statement of accounts once written assurance is provided that all outstanding matters and adjustments have been made. Report 2.2

The final accounts and final Audit Findings Report will be sent to the committee as soon as practically possible, and members of the Advisory Committee will be notified of any material adjustments. Report P14

The money

  • £545,235 Original audit fees as per the original audit plan Report P16
  • £19,000 Additional fees primarily due to extra work on Plant, Property and Equipment Report P16

Implications

  • Financial: Further fees may be incurred as part of the audit of leases if additional work is required. Report P16
  • Risk: If the audit is not completed before the 27 February 2026 backstop date, the auditor can issue a modified or disclaimed audit opinion. Report P13, P14
  • Other: An improvement plan to address shortcomings in the council's records of assets has been ongoing since the 2023/24 audit, with a second phase underway covering Universal Property Reference Numbers, Land Registry reconciliation, and service area inventories. Report P11

Who and where

  • Brent Council taxpayers Report P7
  • Pension Fund members Report 2.1, P15
  • Members of the Audit & Standards Committee and Advisory Committee

Timeline

  • 2024: Government introduced 'backstop' dates as part of plans to clear local authority audit backlogs Report P13
  • 2025-12-03: Audit and Standards Committee meeting at which this report was considered
  • 27 February 2026: Backstop date for 2024/25 accounts Report P13, P14

Plain English for the jargon

  • ISA260 (Audit Findings Report): The external auditor's 'report to those charged with governance' identifying changes to the accounts, unadjusted misstatements or material weaknesses in controls.
  • Backstop date: A government-set deadline by which local authority accounts must be audited; otherwise the auditor can issue a modified or disclaimed opinion.
  • Letter of representation: A letter from the Council to the auditors setting out the responsibilities and representations made by Brent to confirm certain matters.
  • Plant, Property & Equipment: A category of fixed assets covering items such as land, buildings, and equipment, which the council has had record keeping issues with.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

RESOLVED that the Audit and Standards Committee, having once again thanked Sophia Brown and the audit team at Grant Thornton along with the Council’s Finance Team for their efforts to progress completion of the audit: (1) That approval of the draft letters of representation to Grant Thornton for the Council and Pension Fund be delegated to the Corporate Director of Finance & Resources, as set out in Appendices A & B of the report, which members noted followed the standard template, subject to any significant changes or adjustments required as a result of the final audit findings report being issued to be reported back to members of the Audit and Standards Advisory Committee . (2) That approval to sign off the final statement of accounts for 2024-25 be delegated to the Chair of the Audit & Standards Committee, subject to written assurance being provided that all outstanding matters and adjustments contained in the Audit Findings report had been made, with any material adjustments required as a result of the final Audit Findings report being issued to be reported back to the Audit and Standards Committee and also notified to all members of the Audit & Standards Advisory Committee. (3) That the audit fees for 2024-25 be approved , as detailed in section 3.2.9 of the report subject to members of the Audit & Standards and Advisory Committee being notified of any material adjustment or change.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Audit and Standards Committee

Purpose of the report

1.1This report provides an update on the statement of accounts for the Council and Pension Fund for 2024/25

2.0Recommendation(s) Audit & Standards Committee, having considered any comments referred by the preceding Audit & Standards Advisory Committee, is asked to:

2.1Delegate approval of the draft letters of representation to Grant Thornton for the Council and Pension Fund to the Corporate Director of Finance & Resources, as set out in Appendices A and B.

2.2Approve the final statement of accounts for 2024/25, subject to a written assurance being provided that all outstanding matters and adjustments contained in the Audit Findings report had been made. If there were any material adjustments required as a result of the final Audit Findings report being issued, these would be reported back to the committee

2.3Agree the audit fees for 2024/25, as set out in section 3.2.9 of this report.

Background

3.1Contribution to Borough Plan Priorities and Strategic Context

3.1.1 The statement of accounts is the formal audited accounts of the Council. The purpose of the statement of accounts is to give clear information on the Council’s overall finances and demonstrate stewardship of public money for the year. Being able to independently demonstrate that the Council’s financial affairs are sound, will ensure the Council can achieve its Borough Plan priorities and objectives.

3.2Detail

3.2.1 The Audit Committee has responsibility for considering issues raised by the external auditors as part of the process of approving the annual statement of accounts. The basis for this consideration is the “report to those charged with governance” also referred to as the ISA260 (Audit Findings Report). The Council’s external auditors, Grant Thornton, produce the report following completion of the audit of accounts. The report is intended to identify any changes to the accounts, unadjusted mis-statements or material weaknesses in controls identified during the audit work.

3.2.2 At the time of despatch of this report, Grant Thornton are in the process of finalising the audit of the 2024/25 accounts and their ISA260 (Audit Findings Report). A draft Audit Findings Report will be presented to the committee at this meeting.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
05a. Appendix A: Draft LB Brent Letter of representationAppendix 308 KB Withheld: personal details
PDF
05b. Appendix B: Draft Brent Pension Fund letter of representationAppendix 369 KB Withheld: personal details
PDF
05c. Appendix C: Brent Pension Fund Draft Audit OpinionAppendix 420 KB Download
PDF
Statement of Accounts 2024-25Report 233 KB DownloadRead as text

At this meeting

Whole meeting
4Minutes from the previous meetingApproved
5Statement of Accounts 2024-25This decision

Who was there

6 of 12 attended
JC
Councillor Jumbo ChanChair, present
SC
Councillor Saqlain ChoudryCommittee Member, present
SK
Councillor Sandra KabirCommittee Member, apologies
JL
Councillor Janice LongCommittee Member, present
AM
Councillor Anthony MolloyCommittee Member, present
JP
Councillor Jayanti PatelCommittee Member, present
LS
Councillor Lesley SmithCommittee Member, present
DA
Darren ArmstrongOfficer, expected
HE
Harry EllisOfficer, expected
JK
James KinsellaOfficer, expected
MP
Minesh PatelOfficer, expected
BR
Biancia RobinsonOfficer, expected

On this subject at Brent

Search all
  1. Statement of Accounts 2024-25This decision
  2. External Audit Annual Report & Council's Statement of Accounts 2023-24Noted
  3. Statement of Accounts - Interim External Audit Findings ReportNoted
  4. Brent Council Statement of Accounts/Audit Findings Report 2022/23Noted
  5. Brent Council Statement of Accounts 2022/23Agreed
  6. Statement of Accounts 2022-23 UpdateNoted

More from Brent Audit and Standards Committee

All decisions
MeetingDecisionOutcome
3 Dec 2025 Minutes from the previous meetingRESOLVED to approve the minutes of the previous Committee held on Monday 16 June 2025 as a correct record. Approved Open
16 Jun 2025 Minutes of the previous meetingRESOLVED to approve the minutes of the last meeting of the Committee held on Tuesday 25 March 2025. Approved Open
16 Jun 2025 Annual Governance Statement 2024-25RESOLVED to approve the 2024-25 Annual Governance Statement for formal sign off. Approved Open
25 Mar 2025 Minutes of previous meetingRESOLVED to approve the minutes of the previous Committee held on Monday 24 February 2025 as a correct record. The Ch... Approved Open
25 Mar 2025 Annual Review of the Member Learning and Development (MLD) Programme and Members' Expenses (including the financial and procedural rules governing the Mayor's Charity Appeal)RESOLVED : (1) To note the outcome of the annual review of the financial and procedural rules governing the Mayor’s C... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies