Phase II Capital Investment Programme for School Place Sufficiency for Children and Young People with SEND
ApprovedExecutive1 paper
AI summaryBrent Cabinet approves a £10.6m SEND Phase II Capital Programme to create 212 new specialist school places across five projects, funded from the DfE High Needs Capital Grant.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedSEND Phase II Capital Programme using £10.6m from High Needs Capital Grant
Money£10.6mFunded from High Needs Capital Grant provided by the Department for Education
What happens nextCall-in deadline6pm on Monday 26 January 2026
Who it affectsNot stated
What was decided
Cabinet approved the SEND Phase II Capital Programme using £10.6m from the High Needs Capital Grant to deliver 212 new SEND places at five projects. Report 2.1, P5
The programme covers The Avenue (34 places), Strathcona site (50), The Manor School 1 (72), The Manor School 2 (16) and The Village School (40), totalling 138 primary and 74 secondary places. Report P28, P29, P30, P31
Cabinet is recommended to delegate authority for procurement and contract award above stated thresholds to the Corporate Director of Neighbourhoods and Regeneration. Report 6.6
Why
Brent faces a current shortfall of 212 primary and 150 secondary special school places, and the Phase I programme is still delivering places up to January 2030. Report P17, P13
The council has a statutory duty to provide sufficient school places for pupils with EHCPs, and not expanding places would expose Brent to financial and reputational risk, including rising independent school and tribunal costs. Report P26, 6.7
Modelled as Option 2, the programme is a proactive but measured response because of uncertainty about the Government Schools White Paper expected in January 2026. Report P32, P34
What happens next
Call-in expires at 6pm on Monday 26 January 2026, after which procurement of consultants begins between January and March 2026. Report P42
Design and surveys run from April 2026 to March 2027, with planning applications from April to August 2027 and works from July 2026 to August 2029. Report P42
The Strathcona site proposal will be subject to further consultation with key stakeholders and the local community, and academies will need Regional Schools Commissioner approval. Report 6.3
The money
£10.6m Total cost of the SEND Phase II Capital Programme Report P72, 2.1
£1.0m Cost of Strathcona site project Report P72
£22.6m Total High Needs Capital Grant received from the DfE Report 5.2
£11.6m Unallocated High Needs Capital Grant before this programme Report 5.2
£1.0m High Needs Capital Grant remaining after this programme Report 5.3
£2.2m Unallocated or uncommitted Basic Need Grant funding Report 5.3
£9.7m Basic Need grant to be received during 25/26 to 27/28 Report 5.3
£11.9m Unapplied Basic Need funding after future grant receipts Report 5.3
£4.3m Estimated annual High Needs Block cost avoidance by September 2029 Report P38, 1.2
£1.3m Estimated annual transport cost avoidance by September 2029 Report P38
£5.6m/annum Current cost of 199 Brent pupils placed in out of borough maintained special schools Report 5.5
£11.9m/annum Current cost of 197 Brent pupils placed in independent day schools Report 5.5
£38k/place/annum Average cost of out of borough special school places Report 5.6
£37k/place/annum Average cost of Brent in-borough special school places Report 5.6
£58k/place/annum Average cost of independent placements and the cost cited for an independent day placement in Option 1 Report 5.6, P26
£2,562,000 Modelled cost avoidance in 2026/27 Report P86
£1,050,000 Modelled cost avoidance in 2027/28 Report P86
£840,000 Modelled cost avoidance in 2029/30 Report P86
Options considered
Rejected: Option 1, do nothing and not expand special places once Phase I is complete. Statutory duty to meet EHCP needs would be at risk, with reputational and financial exposure and rising independent and transport costs Report P26
Chosen: Option 2, implement the proposed Phase II expansions (212 places across five projects). Addresses much of the shortfall, gives the council greater control of SEND placements, and avoids further spend on out of borough and independent day placements and transport Report P32, 2.1
Rejected: Option 3, deliver Phase II plus an additional 320 places through new SEND schools. Uncertainty about the Government direction of travel on SEND means such decisions should be deferred until autumn 2026 Report P33, P34
Implications
Financial: The £10.6m cost will be funded from the High Needs Capital Grant, leaving £1.0m of that grant and £11.9m of Basic Need funding available for future use. Report 5.2, 5.3
Financial: Estimated annual cost avoidance of £4.3m in High Needs Block spend and £1.3m in transport from September 2029, based on 212 new places. Report P38
Legal: The council must meet its statutory duty to secure sufficient school places for pupils with EHCPs and will need planning, Section 77, building control and where relevant Regional Schools Commissioner approvals. Report 6.1, 6.5, 6.3
Legal: Failure to expand places increases the risk of further first tier tribunal appeals, which rose 40% in the last academic year mostly for Section I placement. Report 6.7
Risk: Key risks are contractor quotes exceeding budgets, contaminated sites, other council priorities displacing SEND sites, and pressure on council capital contributions. Report P49, P50, P51, P52, P53
Equalities: Proposals are aimed at improving sufficiency of specialist provision for children and young people with EHCPs in Brent, with particular reference to communication and interaction and cognition and learning needs. Report 7.1, P16
Climate: Schemes will incorporate standards that support the council's Zero Carbon ambitions, such as solar PV and improved building fabric insulation, with BREEAM Excellent required for new buildings. Report 8.1, P56
Staffing: Services will be provided by external providers with no direct impact on council staff, but schools will need to recruit additional staff as pupil numbers grow. Report 9.1, P38
Who and where
Brent children and young people with EHCPs who need special school places Report 1.2, P17
Families of children with SEND, including the Brent Parent Carer Forum Report 4.2, 4.5
The Avenue school, Newman Catholic College, The Manor School sites, The Village School and a proposed satellite of an existing SEND school on the Strathcona site Report P28, P29, P30
Other local authorities who currently place children in Brent special schools and ARPs Report P14
Members representing wards where the projects are located Report 4.1
Timeline
January 2026: Cabinet approval of the SEND Phase II Capital Programme Report P42
January 2026: Opening of The Avenue (34 places) using temporary building at Newman CC Report P28
6pm on Monday 26 January 2026: Deadline for submission of call-in
Jan to Mar 2026: Procurement of consultants Report P42
April 2026: Delivery of The Manor School 1 (72 places) and The Manor School 2 (16 places) Report P29, P30
April 2026 to Mar 2027: Design and surveys across the programme Report P42
July 2026 to Aug 2029: Construction works period across the programme Report P42
Sept 2026 to Sept 2029: Schools take occupation of completed projects Report P42
Jan 2027 to Dec 2027: Contractor procurement Report P42
April 2027 to Aug 2027: Planning applications stage Report P42
Sept 2027: Opening of the Strathcona site satellite (50 primary places) Report P29
Sept 2029: Opening of The Village School rebuild (40 places) and realisation of £4.3m High Needs and £1.3m transport savings Report P30, P38
Plain English for the jargon
SEND: Special Educational Needs and Disabilities
EHCP: Education, Health and Care Plan, the legal document setting out a child or young person's needs and the provision to meet them
ARP: Additionally Resourced Provision, special provision within a mainstream school
DfE: Department for Education
High Needs Capital Grant: Capital funding from the DfE used to create specialist school places
FTT: First-tier Tribunal, the legal forum that hears SEND appeals including placement disputes
BB104: Department for Education building guidelines for school design
BREEAM Excellent: A high rating under the Building Research Establishment Environmental Assessment Method for sustainable buildings
CIL: Community Infrastructure Levy, a planning charge on certain developments
S106: Section 106 planning obligations requiring developers to contribute to local infrastructure
MoU: Memorandum of Understanding
VAT: Value Added Tax
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
Cabinet RESOLVED to approve the proposed SEND Phase II Capital Programme using £10.6m from the High Needs Capital Grant Allocation provided by the Department for Education as detailed in paragraph 3.2.2 (Option 2) of the report in order to complete the identified works within the programme. Eligible for call-in: Yes Deadline for submission of call-in: 6pm on Monday 26 January 202 6
Word for word from the decision Brent published for this meeting.Source: democracy.brent.gov.uk
1.1Despite being on target to deliver 382 new SEND places since 2022, the Council continues to experience significant pressures in SEND provision linked to continued demand for local specialist places.
1.2This report sets out the proposal to deliver a further 212 SEND places within the borough for a cost of £10.6m. This will reduce the financial cost of SEND provision by £4.3m per annum as well as provide more local specialist provision for Brent based young people with SEND. The actions outlined in this paper will also support a reduction in expenditure on the Council’s Special Needs Transport budget, which is also under financial pressure.
1.3The programme will help achieve a number of strategic priorities including investing further in SEND provision in the borough as set out in the November 2025 Cabinet report – School Place Planning Strategy 2024-28 (second refresh).
2.0Recommendation(s)
That Cabinet:
2.1Approve the proposed SEND Phase II Capital Programme using £10.6m from the High Needs Capital Grant Allocation provided by the Department for Education as detailed in paragraph 3.2.2 (Option 2) in order to complete the identified works within the programme.
3.0Detail
3.1Cabinet Member Foreword
3.1.1 The SEND Phase II Capital Investment Programme supports the Borough Plan Strategic Priority 4: The Best Start in Life. By ensuring there are sufficient, suitable SEND school places for children and young people in Brent, the local authority is meeting its statutory obligations and supporting every child and young person to access high quality education locally to them in the borough.
3.1.2 This programme also supports the Brent School Place Planning Strategy 2024- 2028 and its November 2025 refresh, which presents the objectives and operating principles to underpin the Council’s approach to school organisation over four years.
3.1.3 Continuing the good work completed in the past three years to be on target to deliver 382 new SEND places from the 2022 approved capital programme, this second phase builds on this foundation as SEND demand continues to increase. We have worked with schools to identify spare mainstream capacity to convert to SEND to reduce costs and ensure maximum value from the SEND capital grant funding.
Background
3.2.1 In January 2022 Cabinet approved £44m of capital investment for up to an additional 427 specialist places in a new secondary special school, expansions of existing special schools and new Additionally Resourced Provision (ARPs) in mainstream schools. For the purposes of this business case, this will be referred to as “SEND Phase I Capital Programme”.
3.2.2 The SEND Phase I Capital Programme is expected to deliver 382 places. At the time of drafting this report, 298 places have already been delivered with a further 84 places expected to be delivered by January 2030. The SEND Phase I Capital Programme includes the new secondary special school, Wembley Manor that was completed in autumn 2025, and Additionally Resourced Provisions (ARPs) at Elsley Primary School, Newfield Primary School, Preston Park Primary School, St Margaret Clitherow Primary School and Newman Catholic College.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.