Phase II Capital Investment Programme for School Place Sufficiency for Children and Young People with SEND

Approved Executive 1 paper

AI summaryBrent Cabinet approves a £10.6m SEND Phase II Capital Programme to create 212 new specialist school places across five projects, funded from the DfE High Needs Capital Grant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSEND Phase II Capital Programme using £10.6m from High Needs Capital Grant
Money£10.6mFunded from High Needs Capital Grant provided by the Department for Education
What happens nextCall-in deadline6pm on Monday 26 January 2026
Who it affectsNot stated

What was decided

Cabinet approved the SEND Phase II Capital Programme using £10.6m from the High Needs Capital Grant to deliver 212 new SEND places at five projects. Report 2.1, P5

The programme covers The Avenue (34 places), Strathcona site (50), The Manor School 1 (72), The Manor School 2 (16) and The Village School (40), totalling 138 primary and 74 secondary places. Report P28, P29, P30, P31

Cabinet is recommended to delegate authority for procurement and contract award above stated thresholds to the Corporate Director of Neighbourhoods and Regeneration. Report 6.6

Why

Brent faces a current shortfall of 212 primary and 150 secondary special school places, and the Phase I programme is still delivering places up to January 2030. Report P17, P13

The council has a statutory duty to provide sufficient school places for pupils with EHCPs, and not expanding places would expose Brent to financial and reputational risk, including rising independent school and tribunal costs. Report P26, 6.7

Modelled as Option 2, the programme is a proactive but measured response because of uncertainty about the Government Schools White Paper expected in January 2026. Report P32, P34

What happens next

Call-in expires at 6pm on Monday 26 January 2026, after which procurement of consultants begins between January and March 2026. Report P42

Design and surveys run from April 2026 to March 2027, with planning applications from April to August 2027 and works from July 2026 to August 2029. Report P42

The Strathcona site proposal will be subject to further consultation with key stakeholders and the local community, and academies will need Regional Schools Commissioner approval. Report 6.3

The money

  • £10.6m Total cost of the SEND Phase II Capital Programme Report P72, 2.1
  • £1.0m Cost of Strathcona site project Report P72
  • £22.6m Total High Needs Capital Grant received from the DfE Report 5.2
  • £11.6m Unallocated High Needs Capital Grant before this programme Report 5.2
  • £1.0m High Needs Capital Grant remaining after this programme Report 5.3
  • £2.2m Unallocated or uncommitted Basic Need Grant funding Report 5.3
  • £9.7m Basic Need grant to be received during 25/26 to 27/28 Report 5.3
  • £11.9m Unapplied Basic Need funding after future grant receipts Report 5.3
  • £4.3m Estimated annual High Needs Block cost avoidance by September 2029 Report P38, 1.2
  • £1.3m Estimated annual transport cost avoidance by September 2029 Report P38
  • £5.6m/annum Current cost of 199 Brent pupils placed in out of borough maintained special schools Report 5.5
  • £11.9m/annum Current cost of 197 Brent pupils placed in independent day schools Report 5.5
  • £38k/place/annum Average cost of out of borough special school places Report 5.6
  • £37k/place/annum Average cost of Brent in-borough special school places Report 5.6
  • £58k/place/annum Average cost of independent placements and the cost cited for an independent day placement in Option 1 Report 5.6, P26
  • £2,562,000 Modelled cost avoidance in 2026/27 Report P86
  • £1,050,000 Modelled cost avoidance in 2027/28 Report P86
  • £840,000 Modelled cost avoidance in 2029/30 Report P86

Options considered

  • Rejected: Option 1, do nothing and not expand special places once Phase I is complete. Statutory duty to meet EHCP needs would be at risk, with reputational and financial exposure and rising independent and transport costs Report P26
  • Chosen: Option 2, implement the proposed Phase II expansions (212 places across five projects). Addresses much of the shortfall, gives the council greater control of SEND placements, and avoids further spend on out of borough and independent day placements and transport Report P32, 2.1
  • Rejected: Option 3, deliver Phase II plus an additional 320 places through new SEND schools. Uncertainty about the Government direction of travel on SEND means such decisions should be deferred until autumn 2026 Report P33, P34

Implications

  • Financial: The £10.6m cost will be funded from the High Needs Capital Grant, leaving £1.0m of that grant and £11.9m of Basic Need funding available for future use. Report 5.2, 5.3
  • Financial: Estimated annual cost avoidance of £4.3m in High Needs Block spend and £1.3m in transport from September 2029, based on 212 new places. Report P38
  • Legal: The council must meet its statutory duty to secure sufficient school places for pupils with EHCPs and will need planning, Section 77, building control and where relevant Regional Schools Commissioner approvals. Report 6.1, 6.5, 6.3
  • Legal: Failure to expand places increases the risk of further first tier tribunal appeals, which rose 40% in the last academic year mostly for Section I placement. Report 6.7
  • Risk: Key risks are contractor quotes exceeding budgets, contaminated sites, other council priorities displacing SEND sites, and pressure on council capital contributions. Report P49, P50, P51, P52, P53
  • Equalities: Proposals are aimed at improving sufficiency of specialist provision for children and young people with EHCPs in Brent, with particular reference to communication and interaction and cognition and learning needs. Report 7.1, P16
  • Climate: Schemes will incorporate standards that support the council's Zero Carbon ambitions, such as solar PV and improved building fabric insulation, with BREEAM Excellent required for new buildings. Report 8.1, P56
  • Staffing: Services will be provided by external providers with no direct impact on council staff, but schools will need to recruit additional staff as pupil numbers grow. Report 9.1, P38

Who and where

  • Brent children and young people with EHCPs who need special school places Report 1.2, P17
  • Families of children with SEND, including the Brent Parent Carer Forum Report 4.2, 4.5
  • The Avenue school, Newman Catholic College, The Manor School sites, The Village School and a proposed satellite of an existing SEND school on the Strathcona site Report P28, P29, P30
  • Other local authorities who currently place children in Brent special schools and ARPs Report P14
  • Members representing wards where the projects are located Report 4.1

Timeline

  • January 2026: Cabinet approval of the SEND Phase II Capital Programme Report P42
  • January 2026: Opening of The Avenue (34 places) using temporary building at Newman CC Report P28
  • 6pm on Monday 26 January 2026: Deadline for submission of call-in
  • Jan to Mar 2026: Procurement of consultants Report P42
  • April 2026: Delivery of The Manor School 1 (72 places) and The Manor School 2 (16 places) Report P29, P30
  • April 2026 to Mar 2027: Design and surveys across the programme Report P42
  • July 2026 to Aug 2029: Construction works period across the programme Report P42
  • Sept 2026 to Sept 2029: Schools take occupation of completed projects Report P42
  • Jan 2027 to Dec 2027: Contractor procurement Report P42
  • April 2027 to Aug 2027: Planning applications stage Report P42
  • Sept 2027: Opening of the Strathcona site satellite (50 primary places) Report P29
  • Sept 2029: Opening of The Village School rebuild (40 places) and realisation of £4.3m High Needs and £1.3m transport savings Report P30, P38

Plain English for the jargon

  • SEND: Special Educational Needs and Disabilities
  • EHCP: Education, Health and Care Plan, the legal document setting out a child or young person's needs and the provision to meet them
  • ARP: Additionally Resourced Provision, special provision within a mainstream school
  • DfE: Department for Education
  • High Needs Capital Grant: Capital funding from the DfE used to create specialist school places
  • FTT: First-tier Tribunal, the legal forum that hears SEND appeals including placement disputes
  • BB104: Department for Education building guidelines for school design
  • BREEAM Excellent: A high rating under the Building Research Establishment Environmental Assessment Method for sustainable buildings
  • CIL: Community Infrastructure Levy, a planning charge on certain developments
  • S106: Section 106 planning obligations requiring developers to contribute to local infrastructure
  • MoU: Memorandum of Understanding
  • VAT: Value Added Tax
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Cabinet RESOLVED to approve the proposed SEND Phase II Capital Programme using £10.6m from the High Needs Capital Grant Allocation provided by the Department for Education as detailed in paragraph 3.2.2 (Option 2) of the report in order to complete the identified works within the programme. Eligible for call-in: Yes Deadline for submission of call-in: 6pm on Monday 26 January 202 6
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Cabinet

Executive summary

1.1Despite being on target to deliver 382 new SEND places since 2022, the Council continues to experience significant pressures in SEND provision linked to continued demand for local specialist places.

1.2This report sets out the proposal to deliver a further 212 SEND places within the borough for a cost of £10.6m. This will reduce the financial cost of SEND provision by £4.3m per annum as well as provide more local specialist provision for Brent based young people with SEND. The actions outlined in this paper will also support a reduction in expenditure on the Council’s Special Needs Transport budget, which is also under financial pressure.

1.3The programme will help achieve a number of strategic priorities including investing further in SEND provision in the borough as set out in the November 2025 Cabinet report – School Place Planning Strategy 2024-28 (second refresh).

2.0Recommendation(s)

That Cabinet:

2.1Approve the proposed SEND Phase II Capital Programme using £10.6m from the High Needs Capital Grant Allocation provided by the Department for Education as detailed in paragraph 3.2.2 (Option 2) in order to complete the identified works within the programme.

3.0Detail

3.1Cabinet Member Foreword

3.1.1 The SEND Phase II Capital Investment Programme supports the Borough Plan Strategic Priority 4: The Best Start in Life. By ensuring there are sufficient, suitable SEND school places for children and young people in Brent, the local authority is meeting its statutory obligations and supporting every child and young person to access high quality education locally to them in the borough.

3.1.2 This programme also supports the Brent School Place Planning Strategy 2024- 2028 and its November 2025 refresh, which presents the objectives and operating principles to underpin the Council’s approach to school organisation over four years.

3.1.3 Continuing the good work completed in the past three years to be on target to deliver 382 new SEND places from the 2022 approved capital programme, this second phase builds on this foundation as SEND demand continues to increase. We have worked with schools to identify spare mainstream capacity to convert to SEND to reduce costs and ensure maximum value from the SEND capital grant funding.

Background

3.2.1 In January 2022 Cabinet approved £44m of capital investment for up to an additional 427 specialist places in a new secondary special school, expansions of existing special schools and new Additionally Resourced Provision (ARPs) in mainstream schools. For the purposes of this business case, this will be referred to as “SEND Phase I Capital Programme”.

3.2.2 The SEND Phase I Capital Programme is expected to deliver 382 places. At the time of drafting this report, 298 places have already been delivered with a further 84 places expected to be delivered by January 2030. The SEND Phase I Capital Programme includes the new secondary special school, Wembley Manor that was completed in autumn 2025, and Additionally Resourced Provisions (ARPs) at Elsley Primary School, Newfield Primary School, Preston Park Primary School, St Margaret Clitherow Primary School and Newman Catholic College.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Phase II Capital Investment Programme for School Place Sufficiency for Children and Young People with SENDReport 411 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 23 attended
MB
Councillor Muhammed Butt Leader of the Council & Cabinet Member for Safer Communities. Jobs & SkillsChair, present
MP
Councillor Mili Patel Deputy Leader and Cabinet Member for Finance & ResourcesVice-Chair, present
TB
Councillor Teo Benea Cabinet Member for Regeneration, Planning & PropertyCommittee Member, present
FD
Councillor Fleur Donnelly-Jackson Cabinet Member for HousingCommittee Member, present
GG
Councillor Gwen Grahl Cabinet Member for Children, Young People & SchoolsCommittee Member, present
PK
Councillor Promise Knight Cabinet Member for Customer Experience, Resident Support & CultureCommittee Member, apologies
NN
Councillor Neil Nerva Cabinet Member for Adult Social Care, Public Health and LeisureCommittee Member, present
JR
Councillor Jake Rubin Cabinet Member for Climate Action and Community PowerCommittee Member, present
KS
Councillor Krupa Sheth Cabinet Member for Public Realm and EnforcementCommittee Member, apologies
A
AdministratorOfficer, expected
KW
Kim WrightOfficer, expected
NC
Nigel ChapmanOfficer, expected

All 23 on the meeting page

More from Brent Cabinet

All decisions
MeetingDecisionOutcome
9 Nov 2026 Apologies for AbsenceApologies for absence were received from Thomas Cattermole (Corporate Director Resident & Housing Services) with Spen... Decided Open
9 Nov 2026 Declarations of InterestCouncillor Grahl declared a personal interest in relation to Agenda Item 10 (Rent Setting Policy Statement) and Agend... Decided Open
9 Nov 2026 Minutes of the Previous MeetingCabinet RESOLVED that the minutes of the previous meeting held on Monday 12 October 2026 be approved as a correct rec... Approved Open
9 Nov 2026 Matters Arising (if any)None identified. Decided Open
9 Nov 2026 Petitions (if any)There were no petitions presented at the meeting. Decided Open