London Borough of Brent
Planning Committee, Wednesday 11 February 2026 at 6.00pm

25/0041 - Little Trainers Playground and Hazel Road Community Centre, 26 Hazel Road and Harriet Tubman House, 28 Hazel Road, London, NW10 5PP

Agreed Planning 2 papers

AI summaryBrent Planning Committee grants permission for a 4-storey community building on Hazel Road, NW10, with a condition delaying demolition of Harriet Tubman House until a replacement contract is signed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedSubject to legal agreement and conditions
MoneyNot stated
What happens nextLegal agreement to be completedPlus conditions set out in the report
Who it affectsHazel Road, NW10 areaIncluding Harriet Tubman House

What was decided

Planning permission granted, subject to completion of a legal agreement securing planning obligations and the conditions and informatives in the report.

An additional condition was added: no demolition of Harriet Tubman House may take place until a binding contract is in place for the demolition and construction of the new development.

The committee accepted the officer recommendation that the redevelopment is supported in principle in land use terms and complies with Local Plan policy BSI1. Report P1

Why

Officers considered Harriet Tubman House a non-designated heritage asset of modest significance, assessed by Brent's heritage officer at 5 out of 12, below the 6-point local listing threshold. Report P17, P18, P33, P34, P35, P36, P37, P38

Officers weighed the harm from demolishing the existing building against the public benefits of an expanded training centre and community hall, concluding the benefits clearly outweigh the loss. Report P40, P46

A Level 2 building recording survey is required before any demolition, to align with paragraph 218 of the NPPF. Report P47

What happens next

Complete a legal agreement to secure the planning obligations detailed in the committee report.

Comply with the additional condition that no demolition of Harriet Tubman House occurs until a binding contract for the new development is in place.

Undertake a Level 2 building recording survey by an experienced heritage professional before demolition, and add it to the Greater London Historic Environment Record. Report P47

Options considered

  • Chosen: Grant planning permission with conditions and legal agreement. Enhanced community offer and public benefits outweighed harm to the non-designated heritage asset. Report P1, P46
  • Rejected: Refuse on heritage grounds. Officers concluded the building does not meet the threshold for local listing and harm was outweighed by public benefits. Report P33, P46

Implications

  • Legal: A legal agreement must be completed to secure the planning obligations before permission is finalised.
  • Equalities: Objections were received from the Kensal Green Residents Association and the Willesden Local History Society over the loss of the non-designated heritage asset. Report P27
  • Other: The proposal would enhance the visual amenity of the site and the Hazel Road open space, and is designed with the Metropolitan Police's Secured by Design team. Report P46, P61
  • Other: Daylight and sunlight impacts at 23-25, 27 and 29 Hazel Road were considered acceptable in the urban context, with retained daylight distribution above 50%. Report P75, P79, P80, P81
  • Risk: Officers noted the proposal would not have a notable effect on the Kensal Green (All Souls) Cemetery Registered Park and Garden (Grade I) or the nearby Grade II listed horses' trough. Report P45
  • Climate: The proposed building uses a lightweight timber frame with low embodied carbon to reduce load bearing on the network rail lines beneath. Report P60

Who and where

  • Users of the existing Little Trainers Playground, Hazel Road Community Centre and Harriet Tubman House Report P40
  • Residents of 23-31 Hazel Road, including the religious property at 29 Hazel Road Report P73, P75, P76, P77, P82
  • Kensal Green Residents Association and Willesden Local History Society, who objected on heritage grounds Report P27
  • Visitors to Kensal Green Cemetery Conservation Area and the Grade II listed horses' trough south of the site Report P26, P45
  • Future users of the proposed training centre and community hall Report P40, P46

Timeline

  • 1899: Harriet Tubman House was built as an Anglican mission hall. Report P16
  • 1900: Building opened as the St Martin's Institute and Mission Hall. Report P16
  • 2016: Harriet Tubman House was considered for local listing but not added to the list. Report P17
  • 2026-02-11: Planning Committee resolved to grant planning permission subject to a legal agreement, conditions, and an additional demolition-timing condition.

Plain English for the jargon

  • NDHA: Non-designated heritage asset, identified locally as having heritage significance but not statutorily listed.
  • VSC: Vertical Sky Component, a daylight measure of visible sky from a window.
  • NSL: No Sky Contour, the area of a room at desk height from which sky can be seen.
  • APSH: Annual Probable Sunlight Hours, a sunlight measure for south-facing windows and amenity spaces.
  • BRE 209: Building Research Establishment guidance on site layout for daylight and sunlight (2022 edition).
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Granted planning permission subject to: (1) The completion of a legal agreement to secure the planning obligations as detailed within the committee report. (2) The conditions and informatives , as set out in the committee report, together with an additional condition: That no demolition of Harriett Tubman House should take place until a binding contract has been entered into for the demolition and construction of the new development.
Word for word from the decision Brent published for this meeting. Source: democracy.brent.gov.uk

Follow this further

Built from Brent's papers

What the report saysPro

Report to Planning Committee

COMMITTEE REPORT Planning Committee on 11 February, 2026 Item No 04 Case Number 25/0041

SITE INFORMATION

RECEIVED 7 January, 2025

WARD Queens Park

PLANNING AREA Brent Connects Harlesden

LOCATION Little Trainers Playgroup and Hazel Road Community Centre, 26 Hazel Road and Harriet Tubman House, 28 Hazel Road, London, NW10 5PP

PROPOSAL Demolition of all existing buildings and structures and erection of 4 storey mixed-use building comprising of training centre and community hall uses (Use Classes F1/F2), with roof and rear first floor terraces, associated cycle parking, refuse storage, landscaping and all other associated and ancillary works.

PLAN NO’S See condition 2

LINK TO DOCUMENTS When viewing this on an Electronic Device ASSOCIATED WITH THIS PLANNING Please click on the link below to view ALL document associated to case APPLICATION <https://pa.brent.gov.uk/online-applications/applicationDetails.do?activeTab=documents&keyVal=DCAPR_171575>

When viewing this as an Hard Copy

Please use the following steps

1. Please go to pa.brent.gov.uk 2. Select Planning and conduct a search tying "25/0041" (i.e. Case Reference) into the search Box 3. Click on "View Documents" tab

DocRepF Document Imaged Ref: 25/0041 Page 1 of 37 RECOMMENDATIONS That the Committee resolve to GRANT planning permission subject to completion of a legal agreement to secure the following planning obligations:

1. Payment of the Council’s legal and other professional costs in (a) preparing and completing the agreement and (b) monitoring and enforcing its performance.

2. Notification of material start 28 days prior to commencement.

3. Detailed design stage energy assessment: (a) Initial carbon offset payment (approx. £3,924.50) to be paid prior to material start if zero-carbon target not achieved on site. (b) Post-construction energy assessment. Final carbon offset payment (approx. £3,924.50) upon completion of development if zero-carbon target not achieved on site. (c) ‘Be seen’ energy performance monitoring and reporting

4. Biodiversity Net Gain including Habitat Management and Monitoring Plan (HMMP) for on site BNG, provision of off site habitat units

5. Contribution of £3000 for off street tree planting within the vicinity of the site

6. Indexation of contributions in line with inflation (to be indexed from date of Planning Committee resolution)

7. Any other planning obligation(s) considered necessary by the Head of Planning.

That the Head of Planning or other duly authorised person is delegated authority to negotiate the legal agreement indicated above.

That the Head of Planning or other duly authorised person is delegated authority to issue the planning permission and impose conditions and informatives to secure the following matters:

1. 3 year time period for commencement 2. Approved drawings 3. Use Class Restriction 4. Compliance with Travel Plan measures 5. Compliance with tree protection plan and Arboricultural Method Statement 6. Written Scheme of Investigation for heritage 7. Heritage Mitigation measures 8. Construction Logistics Plan 9. Construction Management Plan 10. Construction Environmental Management Plan 11. Further bat surveys 12. TFL infrastructure 13. Sustainable drainage measures 14. Contaminated land – site investigation 15. Contaminated land – remediation and verification 16. Piling Method Statement 17. External Materials 18. Cycle parking 19. Hard and soft landscaping 20. Wildlife nesting features 21. Delivery and servicing plan 22. Community access plan 23. External lighting 24. Plant Noise 25. BREEAM 26. SIte management plan 27. Vibration condition 28. Internal noise insulation Informatives

As set out within decision notice.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
25/0041: Little Trainers Playground and Hazel Road Community Centre, 26 Hazel Road and Harriet Tubman House, 28 Hazel Road, London, NW10 5PPReport 533 KB DownloadRead as text
PDF
25/0041: Supplementary InformationSupplementary 114 KB Download

At this meeting

Whole meeting

Who was there

8 of 15 attended
MK
Councillor Matt KelcherChair, present
SB
Councillor Saqib ButtVice-Chair, present
IA
Councillor Iman Ahmadi MoghaddamCommittee Member, present
AA
Councillor Ajmal AkramCommittee Member, present
RB
Councillor Rita BegumCommittee Member, present
EC
Councillor Elliot ChappellCommittee Member, present
RJ
Councillor Robert JohnsonCommittee Member, present
JP
Councillor Jayanti PatelCommittee Member, present
JW
Jehan WeerasingheOfficer, expected
RR
Rebecca ReidOfficer, expected
JK
James KinsellaOfficer, expected
HO
Hannah O'BrienOfficer, expected

All 15 on the meeting page

More from Brent Planning Committee

All decisions
MeetingDecisionOutcome
5 Aug 2026 Apologies for AbsenceApologies for absence were received from Councillor Gallagher with Councillor Ahmadi-Moghaddam substituting. Apologie... Decided Open
5 Aug 2026 Declarations of interestsNo declarations of interest were made during the meeting. Decided Open
5 Aug 2026 Minutes of the previous meetingRESOLVED that the minutes of the previous meeting held on Thursday 2 July 2026 be approved as a correct record of the... Approved Open
5 Aug 2026 26/0225 - Brent NHS Primary Care Trust, Wembley Centre For Health & Care, 116 Chaplin Road, Wembley, HA0 4UZGranted planning permission subject to: (1) The prior completion of a satisfactory legal agreement; and (2) The condi... Agreed Open
5 Aug 2026 Any Other Urgent BusinessThere was no other urgent business. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies