GREAT EASTERN MAIN LINE THROUGH BRENTWOOD BOROUGH HUTTON ROAD SHENFIELD ESSEX CROSSRAIL INFRASTRUCTURE AND STATION WORKS IN BRENTWOOD BOROUGH COUNCIL, INCLUDING WORKS AT BRENTWOOD STATION, SHENFIELD STATION AND SIDINGS. APPLICATION NO: 14/01016/CROSS
DeferredPlanning3 papers
Planning and Development Control Committee deferred this item on Wednesday 19 November 2014. Below is the council's own wording, with the papers it was decided on.
RESOLVED UNANIMOUSLY that planning application is deferred. (Cllr Clark, declared non pecuniary interest under the Councils Code of Conduct by virtue of living within a close proximity of the site . Cllr Clark is not a member of the committee and would not be voting on this item ).
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
Report to Planning and Development Control Committee
SITE PLAN ATTACHED
09. GREAT EASTERN MAIN LINE THROUGH BRENTWOOD BOROUGH HUTTON ROAD SHENFIELD ESSEX
CROSSRAIL INFRASTRUCTURE AND STATION WORKS IN BRENTWOOD BOROUGH COUNCIL, INCLUDING WORKS AT BRENTWOOD STATION, SHENFIELD STATION AND SIDINGS.
APPLICATION NO: 14/01016/CROSS
8/13 WEEK WARD Shenfield 19.11.2014 DATE
NPPF NPPG PARISH POLICIES CP1 T2 PC4
CASE OFFICER [name removed] 01277 312588
Drawing no(s) ENVIRONMENTAL MANAGEMENT PLAN; WRITTEN relevant to this STATEMENT FOR INFORMATION; decision: CRL1-NRI-T-QAP-CR001-50108;
1. Proposals
At the request of members this application is being reported to planning committee to ensure that it is debated within the public arena.
The submitted application is for the formal determination of details pursuant to the proposed construction arrangements to facilitate the crossrail infrastructure and station works in Brentwood, including those at Brentwood station, Shenfield station and sidings.
Process and matters for consideration
The Crossrail Act 2008 deems planning permission is to be granted for the works authorised by it, subject to the conditions set out in Schedule 7. In paragraph 16 schedule 7 part 3 of the Crossrail Act 2008 it sets out that development shall be carried out in accordance with arrangements approved by the district planning authority at the request of the nominated undertaker with respect to matters of (in this case) storage sites, screening, artificial lighting, suppression of dust and mud on highway. Each of the aforementioned matters will be considered under separate sections of the subsequent report. 2. Policy Context
The National Planning Policy Framework (NPPF) came into effect on 27 March 2012 and is now a material consideration in planning decisions. The weight to be given to it will be a matter for the decision makers planning judgement in each particular case. This Framework replaces all the national planning guidance documents as stated in the NPPF, including Planning Policy Guidance Notes and Planning Policy Statements. Notwithstanding this, the NPPF granted a one year period of grace for existing adopted Local Plan policies which has now ended, but, the NPPF advises that following this 12 month period, due weight should be given to relevant policies in existing plans according to their degree of consistency with the Framework, (the closer the policies in the plan to the policies in the Framework, the greater the weight that may be given). The National Planning Practice Guidance (NPPG) is a material consideration in the determination of this application.
At a local level there is the Brentwood Replacement Local Plan 2005 the most relevant Policies to this application are:
CP1 -General Development Criteria PC4 - Noise T2 - New Development and Highway Considerations
3. Relevant History
• None
4. Neighbour Responses
Notifications letters were sent to the following:
- Environment Agency - Natural England - The scheduled Ancient Monument Society - English Heritage - County Archaeologist - Essex County Council (Highways) and the - Essex Wildlife Trust
There has also been consultation with the Council's historic buildings advisor, arboriculturalist, and the Environmental Health team. 5. Consultation Responses
• Highway Authority: A copy of the representation that has been received can be found in Appendix B of this report. The point that has been raised with regards to wheel washing facilities are assessed as part of this application. All other matters raised are not for consideration under this application and are dealt with via separate legislation in terms of the Crossrail Act 2008 itself or the Control of Pollution Act 1974.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
GREAT EASTERN MAIN LINE THROUGH BRENTWOOD BOROUGH HUTTON ROAD SHENFIELD ESSEX CROSSRAIL INFRASTRUCTURE AND STATION WORKS IN BRENTWOOD BOROUGH COUNCIL, INCLUDING WORKS AT BRENTWOOD STATION, SHENFIELD STATION AND SIDINGS. APPLICATION NO: 14/01016/CROSSReport
291GREAT EASTERN MAIN LINE THROUGH BRENTWOOD BOROUGH HUTTON ROAD SHENFIELD ESSEX CROSSRAIL INFRASTRUCTURE AND STATION WORKS IN BRENTWOOD BOROUGH COUNCIL, INCLUDING WORKS AT BRENTWOOD STATION, SHENFIELD STATION AND SIDINGS. APPLICATION NO: 14/01016/CROSSThis decision
GREAT EASTERN MAIN LINE THROUGH BRENTWOOD BOROUGH HUTTON ROAD SHENFIELD ESSEX CROSSRAIL INFRASTRUCTURE AND STATION WORKS IN BRENTWOOD BOROUGH COUNCIL, INCLUDING WORKS AT BRENTWOOD STATION, SHENFIELD STATION AND SIDINGS. APPLICATION NO: 14/01016/CROSSThis decision
Follow Planning and Development Control Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Variation in the Order of the AgendaRESOLVED UNANIMOUSLY that since a member was unwell, but wished to speak on item 7, this item will be moved to after ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.