RESOLVED UNANIMOUSLY to: 1. That Members approve the introduction of the new recycling contract, which will commence in May 2015. REASON FOR DECISION This has been through a robust procurement process, and the price outlined in the report is the best price achieved.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1The current recycling contract with Basildon is due to end in May 2015, and currently provides the Council with an income of approximately £250,000 per annum.
1.2Over the past six months there has been a joint procurement undertaken with Basildon, Rochford and Uttlesford Councils, which offered the best opportunity to secure maximum value, due to the increased tonnage. The Council is now at the final stage of this procurement, which will extend over the next four years, and it is apparent that the market for the sale of the dry recyclate is very depressed.
1.3The final stage of the procurement process is for Member approval, and shows that as opposed to the income the Council currently receives, there will now be a payment to the contractor. The Council also tips their recyclate at the Basildon depot, who will charge a nominal fee of £5.00 per tonne as a gate fee.
1.4The new contract will mean a net increase of over £85.00 per tonne for the Council, and will mean a net loss of approximately £540,000. This will mean a pressure on the 2015/16 budget of £300,000.
2. Recommendation(s)
2.1That Members approve the introduction of the new recycling contract, which will commence in May 2015. 3. Introduction and Background
3.1The current contract has been in place for five years, and was the first time in a many years that there had been such a large income achieved from recyclate, which is traditionally a volatile market in terms of waste. Unfortunately this was seen as a saving by the Council, and included in the base budget as a reduction in the overall cost of waste collection, although this was never sustainable in the long-term.
3.2There are a number of reasons for the dramatic fall in the market price of the materials collected by this Council:-
i) The fall in paper prices
ii) The percentage of paper in the mix has fallen, due to less newspapers being read and increasing use of digital media. A number of paper mills have closed due to the reduction in need for paper.
iii) The reduction in the use of aluminium in cans, this is now being replaced with light steel in cans.
iv) The fall in oil prices means it is cheaper to use oil rather than recycled plastics in the production of new plastics. This has reduced the price for recycled bottles.
v) The fall in the export market to China means that prices are low; this market has underpinned the UK price.
vi) There is over capacity in MRFs and a number of UK plants have closed.
vii) New legislation has increased costs. The MRF Code of Practice has meant that MRF must operate to a high standard and produce an end product comparable to that collected and sorted at kerbside. The cost of processing has gone up.
viii) The new EU Regulations have meant that it is quality rather than quantity which is the driving factor.
3.3These factors have driven up the costs at material recovery facilities and decreased the prices that the operator can receive from the materials, such that there is now a net increase in cost to this Authority.
3.4At the beginning of the procurement process it was thought by the consultants employed by the Councils to manage this that the price would be at zero or at the worst a slight negative cost. 4. Issue, Options and Analysis of Options
4.1The Council has been through a robust procurement process in partnership with other Local Authorities, therefore it is felt there are no other options at this stage.
Reasons for recommendation
5.1This has been through a robust procurement process, and the price outlined in the report is the best price achieved.
Consultation
6.1The consultation process was through the procurement process in partnership with other Local Authorities.
7. References to Corporate Plan
7.1The Council are committed to increasing recycling.
8. Implications
Financial Implications Name & Title: Chris Leslie – Financial Services Manager (S151 Officer) Tel & Email: 01277 312542 / [email protected]
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.