LAND AT HAVERING GROVE FARM 552A RAYLEIGH ROAD HUTTON ESSEX CM13 1SG

Refused Planning 2 papers

Planning and Licensing Committee refused this item on Tuesday 23 June 2015. Below is the council's own wording, with the papers it was decided on.

Item53

Resolved

RESOLVED that the planning permission is refused for the following reasons: R1 U09973 The proposed solar farm constitutes inappropriate development within the Green Belt and would significantly and demonstrably decrease the openness of this part of the Green Belt and would conflict with the purposes of including land in the Green Belt contrary to Chapter 9 of the National Planning Policy Framework (NPPF) and Policies GB1 and GB2 of the Brentwood Replacement Local Plan 2005. R2 U09974 It has not been demonstrated that any previously developed land is available for the development within the wider area; outside the Borough of Brentwood and beyond 10km from the application site and it has not been demonstrated that there is no suitable sites of a lower agricultural quality within the Borough of Brentwood, or the surrounding area that would be more suitable for a solar farm, contrary to the National Planning Policy Framework, particularly Paragraph 112, the Written Ministerial Statement of the 25th March 2015 and Policy IR3 of the Brentwood Replacement Local Plan 2005. R3 U09976 The benefits of the proposal in terms of environmental and biodiversity benefits would not clearly outweigh the harm by reason of inappropriateness and the other harm identified, to constitute the very special circumstances required to justify this development, contrary to Chapter 9 of the National Planning Policy Framework (NPPF) and Policy GB1 of the Brentwood Replacement Local Plan 2005.
Word for word from the decision Brentwood published for this meeting. Source: brentwood.moderngov.co.uk

Follow this further

Built from Brentwood's papers

What the report saysPro

Report to Planning and Licensing Committee

SITE PLAN ATTACHED

07. LAND AT HAVERING GROVE FARM 552A RAYLEIGH ROAD HUTTON ESSEX CM13 1SG

INSTALLATION AND OPERATION OF A SOLAR FARM AND ASSOCIATED INFRASTRUCTURE, INCLUDING PV PANELS, MOUNTING FRAMES, INVERTER, TRANSFORMER, POLE MOUNTED CCTV CAMERAS, SUBSTATIONS, COMPOSTING TOILET AND FENCE.

APPLICATION NO: 15/00161/FUL

8/13 WEEK WARD Hutton East 04.05.2015 DATE

NPPF NPPG CP1 T2 GB1 PARISH POLICIES GB2 C5 C14 C16 IR3 IR6

CASE OFFICER [name removed] 01277 312536

Drawing no(s) TOPOGRAPHICAL SURVEY1; relevant to this ARCHAEOLOGICAL DESK BASED ASSESS; decision: DESIGN & ACCESS STATEMENT; ROAD_CROSS_SECTION; HISTORIC ENV. IMPACT ASSESSMENT; ALVE; AT_01 TRANSFORMER; CCTV_01 CCTV POLE DETAILS; CSR_01 SUBSTATION DETAILS; CB_01 COMMUNICATIONS BUILDING; TRAFFIC METHOD STATEMENT; DEER FENCE DETAILS; DNO_01 DNO BUILDING DETAILS; ECOLOGICAL APPRAISAL; XXX_01_A - GRP CABINET; HVG_01_REV E - LAYOUT; SITE PLAN HVG_01; SEQUENTIAL ANALYSIS STUDY; ARBORICULTURAL REPORT; FLOOD RISK ASSESSMENT; TD_01 TRANSFORMER ELEVATIONS; ID_01 INVERTER DETAILS; TOILET ELEVATION; TYP_P_E_3L PANELS ELEVATION; STATEMENT COMMUNITY INVOLVEMENT; SB_01 STORAGE BUILDING DETAILS; TOPOGRAPHICAL SURVEY2; BIODIVERSITY MANAGEMENT PLAN; SWEPT PATH ANALYSIS; ARCHAELOGICAL GEOPHYSICAL SURVEY; CONSTRUCTION TRAFFIC MANAGEMENT; PFA ROAD CONDITION SURVEY;

1. Proposals

Planning permission is sought to install a ground mounted photovoltaic (PV) solar energy farm on the site. The application site comprises 18.3ha, with the solar farm infrastructure being placed on 11ha within the site. The solar farm infrastructure will cover 19 percent of the area, for example with gaps provided between the rows of panels. The 5MW solar farm would be capable of generating enough electricity to power 1460 typical households per year. The energy generated will be fed directly into the local power grid network. The solar farm has an operational life of around 30-35 years and after this time all equipment will be removed and the land restored to its former condition. The solar panels each measure 2m x 1m x 0.05m. The mounted solar panels have a maximum height above ground level of 2.5m. The panels will be fixed to mounting frames at an angle of 25-30 degrees to optimise daylight capture and will be fixed in place rather than tracking the sun. It is proposed to have sheep grazing between the rows of solar panels.

Inverters will be required on the site, which are required to convert the Direct Current (DC) electricity generated by the panels to Alternating Current (AC) before being fed into the grid. The inverters will be located in three cabins (painted green) on the site which will be mounted on a concrete pad and measure 2.9m high, 4.4m long and 1.5m wide

Transformers are also required on the site to transform electrical energy from one circuit into another, allowing the electricity generated to be fed into the grid. The plans submitted indicate that two transformers will be installed on the site located in two cabinet (painted green) measuring 2.8m high, 6m long and 2.5m wide.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 07: 1500161 mapPlan 1.4 MB Download
PDF
LAND AT HAVERING GROVE FARM 552A RAYLEIGH ROAD HUTTON ESSEX CM13 1SG INSTALLATION AND OPERATION OF A SOLAR FARM AND ASSOCIATED INFRASTRUCTURE, INCLUDING PV PANELS, MOUNTING FRAMES, INVERTER, TRANSFORMER, POLE MOUNTED CCTV CAMERAS, SUBSTATIONS, COMPOSTING TOILET AND FENCE. APPLICATION NO: 15/00161/FUReport 202 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 33 attended
RM
Councillor Roger McCheyneChair, present
WT
Councillor William TrumpVice-Chair, present
PB
Councillor Paul BarrellCommittee Member, present
RC
Councillor Ross CarterCommittee Member, present
JC
Councillor Jon ClokeCommittee Member, present
RK
Councillor Roger KeebleCommittee Member, present
JM
Councillor Julie MorrisseyCommittee Member, present
PM
Councillor Philip MynottCommittee Member, present
JN
Councillor John NewberryCommittee Member, present
MR
Councillor Mark ReedCommittee Member, present
DT
Councillor David TeeCommittee Member, present
AW
Councillor Andrew WilesCommittee Member, present

All 33 on the meeting page

More from Brentwood Planning and Licensing Committee

All decisions
MeetingDecisionOutcome
26 Jul 2022 54 Nags Head Lane Brentwood Essex CM14 5NLRESOLVED subject to the following conditions agreed with the Chair and Vice Chair following the meeting: 1 TIM01 Stan... Agreed Open
26 Jul 2022 Licensing Act Policy ReviewRESOLVED UNANIMOUSLY to: 1. Agree for the reviewed statement of Licensing Policy to go out to consultation, and; 2. T... Agreed Open
26 Jul 2022 Gambling Act 2005 Policy ReviewRESOLVED UNANIMOUSLY to: Agree for the reviewed statement of Gambling Policy to go out to consultation, and; That aft... Agreed Open
26 Jul 2022 Development Land adjacent to Roman Road Ingatestone EssexRESOLVED subject to the conditions outlined in the report. [Cllr Bridge declared a non-pecuniary interest as he lives... Decided Open
26 Jul 2022 Urgent Business - Hackney Carriage FaresRESOLVED : 1. Consider the consultation responses as in appendix B, and 2. To either agree for the proposed table of ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies