RESOLVED UNANIMOUSLY that: 1. That the Draft Revised Local Development Scheme (July 2015) as set out at Appendix A be approved. REASON FOR RECOMMENDATION The Council, as local planning authority for the Borough, is required to prepare and maintain a Local Development Scheme. This must be made available publically and kept up-to-date so that local communities and interested parties can keep track of progress. The Council’s current Local Development Scheme (adopted December 2012) is out of date and needs to be revised. The revised Local Development Scheme (July 2015) provides updated information and a new timetable for preparation of the Local Development Plan and Community Infrastructure Levy in light of changes since 2012 and expected future timeframes.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1The Planning and Compulsory Purchase Act 2004 requires local planning authorities to prepare and maintain a Local Development Scheme.
1.2The Local Development Scheme sets out the documents which, when prepared, will comprise the Local Plan for the Borough. It provides timescales and key milestones, such as future public consultation dates.
1.3The Local Development Scheme must be made available publically and kept up-to-date so that local communities and interested parties can keep track of progress. This latest development scheme updates information and timetables for preparation of planning policies in light of changes since the current development scheme was adopted in December 2012.
Recommendation
2.1That the Draft Revised Local Development Scheme (July 2015) as set out at Appendix A be approved.
3. Introduction and Background
3.1Section 15 of the Planning and Compulsory Purchase Act 2004 (as amended by the Localism Act 2011) requires local planning authorities to prepare and maintain a Local Development Scheme.
3.2The Local Development Scheme sets out the documents which, when prepared, will comprise the Local Plan for the Borough. It sets out timescales and key milestones, such as future public consultation dates, for two key Council documents: Local Development Plan (LDP) Community Infrastructure Levy (CIL)
3.3In order to facilitate preparation of these documents the Local Development Scheme sets out:
Current planning policies and documents that have been ‘saved’ pending adoption of the new Local Plan; Details and timetables for relevant planning policy documents that the Council is preparing; Key milestones as part of the process leading to the adoption of documents (where relevant); Information on key supporting documents, such as the Authorities Monitoring Report and Statement of Community Involvement; and Resources available and any constraints.
3.4The Council’s first Local Development Scheme was adopted in 2006 and has since been subject to reviews in 2007 and 2012. This would be the fourth review and reflects revisions to the Local Plan timetable in light of the abolition of the East of England Plan, additional work required after consultation on Preferred Options in 2013, and changing legislation.
4. Issue, Options and Analysis of Options
4.1Prior to the Localism Act the Council was required to submit its Local Development Scheme to the Secretary of State for inspection. However, this is no longer a requirement and updated guidance has since been published as part of Planning Practice Guidance. Now local planning authorities must keep Local Development Schemes up-to-date and publish these on their website.
4.2In light of changes in both the national and local planning context since the Council’s current Local Development Scheme was adopted in 2012, it is necessary to update information and timetables within the document. In order to comply with Planning Practice Guidance a revised document has been prepared, as set out at Appendix A.
4.3If agreed, the revised Local Development Scheme would be finalised and published on the Council’s website in line with Planning Practice Guidance. 5. Reasons for Recommendation
5.1The Council, as local planning authority for the Borough, is required to prepare and maintain a Local Development Scheme. This must be made available publically and kept up-to-date so that local communities and interested parties can keep track of progress.
5.2The Council’s current Local Development Scheme (adopted December 2012) is out of date and needs to be revised. The revised Local Development Scheme (July 2015) provides updated information and a new timetable for preparation of the Local Development Plan and Community Infrastructure Levy in light of changes since 2012 and expected future timeframes.
Consultation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gambling Act 2005 Policy ReviewRESOLVED UNANIMOUSLY to: Agree for the reviewed statement of Gambling Policy to go out to consultation, and; That aft...
Urgent Business - Hackney Carriage FaresRESOLVED : 1. Consider the consultation responses as in appendix B, and 2. To either agree for the proposed table of ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.