Policy, Finance and Resources Committee approved this item on Tuesday 15 September 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED UNANIMOUSLY 1. To approve the areas identified for a draft “ Programme” to cover the areas identified in 4.1-4.10 of the report. 2. To agree that such activities as outlined in 4.1-4.10 of the report, be developed into full business cases with reports to come back to Policy, Finance and Resource Committee, once details are complete . 3. That opportunities be explored for the Council to maintain its own trees and possibly generate an income through other tree-works. REASON FOR RECOMMENDATION To provide Members with an update on the activities taking place regarding income generation and cost savings.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1In light of the significant budget pressures that are facing the Council in the coming years, ways of generating additional income and reducing costs are being explored.
1.2This report sets out the current activities, which are being undertaken by the Council in relation to this.
2. Recommendation(s)
2.1To approve the areas indentified for a draft “Income Generation Programme” to cover the areas indentified in 4.1-4.10 of this report.
2.2To agree that such activities as outlined below 4.1-4.10 of this report, be developed into full business cases with reports to come back to Policy, Finance and Resource Committee, once details are complete.
3. Introduction and Background
3.1The budget report presented to Council on the 10 June 2015 gave a commitment to finding additional efficiency savings and income generating actives to help reduce the budget gap.
3.2Work has been carried out to identify opportunities and the current activities being pursued are set out in this report.
4. Income Generation and Cost Reduction Activities
4.1The first process being undertaken is to ensure the Council is making the best use of its existing property assets as this is the quickest and lowest risk way to generate additional income. Following completion of these tasks the resources can be diverted into setting up a structure suitable for acquiring and managing income generating property assets.
4.2Review of existing property assets – All information on the Council’s assets is being brought together into an updated asset register so work on maximising their potential revenue streams can be realised and use reviewed. For completion by the end of 2015/16.
4.3Maximising returns from property assets – As details of assets are collated work has begun on reviewing existing leases, triggering rent review clauses or negotiating new agreements. This has identified some rent reviews that are due and these are now being enforced and income increased where possible and appropriate. A central list of all leased properties and rent review dates are being compiled in tandem with the review of existing assets to ensure leases are renewed promptly. This is anticipated to be completed by the end of 2015/16.
4.4Sale of property assets – The identification and processing of redundant assets for sale is ongoing. This will generate additional resources to fund the capital programme and reduce the revenue implications. Current sales are expected to be concluded by the end of 2015/16.
4.5Acquiring income generating property assets – To undertake a substantial investment exercise the Council must be clear about its investment objectives and criteria and have the correct resources to identify suitable properties to acquire and to manage them. This is targeted to be in place by mid 2016/17 following completion of the other work streams with the potential to commence acquiring assets by the end of 2016/17. An acquisition policy already exists which specifies a minimum yield criteria for purchases of 6% but this will be revisited. In addition, full work regarding the implications and management of such an approach need to be explored in full, ahead of any decision being made.
4.6Local Authority Trading Company (LATCo) – A LATCo enables the Council to undertake commercial activity. However, a wide range of powers are already available to Local Authorities and other Councils have successfully acquired investment property without a LATCo, saving money as a result. The need for a LATCo and associated costs will be considered as part of each business case. 4.7 Minimising borrowing costs – Strategies to secure funding for acquisitions will be reviewed to minimise costs. This includes potential sources and profiling of borrowing if required.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy, Finance and Resources Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Brentwood Economic Strategy 2017-2020RESOLVED That Members approve the and agree that a 2017/18 Economic Work Plan is implemented to support the delivery ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.