Policy, Finance and Resources Committee approved this item on Tuesday 15 December 2015. Below is the council's own wording, with the papers it was decided on.
RESOLVED UNANIMOUSLY that 1. Given the findings of the Member Working Party review, the Council continues to implement and develop its Modern Planning Service, subject to the Actions listed in Appendix 1 to the report. 2. The service continues to be monitored and that any further improvements identified will be implemented as soon as practicable. Approval of any such improvements will be delegated to the Head of Planning and Development in consultation with the Chair of the Planning and Licensing Committee. Reasons for Recommendation The Modern Planning service had been in operation for around 6 months and so there was a need to review it to ensure that it was fit for purpose. Subject to the recommendations in the Action Plan in Appendix 1, the Members Working Group agreed that the Modern Planning Service was a more efficient and effective way of delivering the planning service to the Council’s customers.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1On 2 November 2015, Policy, Finances and Resources Committee agreed to undertake a 6 monthly review of the Modern Planning Service. It was agreed to set up a Members Working Group to review the service. This report outlines the findings of that review.
1.2In addition to the Members Working Group, the Council also commissioned an internal audit of the Modern Planning Service. Its findings have also been taken into account in the recommendations of this report.
2. Recommendation(s)
2.1That given the findings of the Member Working Party review, the Council continues to implement and develop its Modern Planning Service, subject to the Actions listed in Appendix 1.
2.2That the service continues to be monitored and that any further improvements identified will be implemented as soon as practicable. Approval of any such improvements will be delegated to the Head of Planning and Development in consultation with the Chair of the Planning and Licensing Committee.
3. Introduction and Background
3.1Following the recommendations of the 2nd November 2015 Policy, Finances and Resources Committee, a cross party Members Working Group was set up to review the Modern Planning Service. The Working Group has met on 3 separate occasions to assess the on-going Modern Planning Service and the various options available to improve the Council’s Planning Service in the light of the current resources and corporate priorities.
3.2The Member Working Group concluded that the Modern Planning Service was now generally working well for all of the Council’s customers. However, it concluded that there were still improvements to be made and these are highlighted in the Action Plan highlighted in Appendix 1.
4. Issue, Options and Analysis of Options
4.1The Modern Planning Service has been operating for just over 6 months now. It is therefore prudent to review the processes and procedures to make sure that they are helping deliver the level of service that the Council and its customers expect.
4.2As well as looking at best practice elsewhere in Essex for certain elements of the service, an internal audit was commissioned to look at how well the Modern Planning Service was operating in terms of email alerts and the recently introduced online planning system .The conclusions were that, overall, the new processes were in line with best practice elsewhere throughout Essex and that the new online service was now being used successfully.
4.3However, it was acknowledged that there were still ways of making the service more effective and efficient. An Action Plan, as set out in Appendix 1, is therefore recommended. By implementing these actions, it is considered that the Modern Planning Service will operate even more efficiently for all of our customers.
4.4The Member Working Group also stressed the importance of reviewing the service regularly to continue to improve its performance. Members and Officers will therefore continue to monitor and improve processes that will continue to make the overall service better for customers and more efficient to operate. Improvements will be implemented under the delegated powers of the Head of Planning and Development in consultation with the Chair of Planning and Licensing Committee. 5. Reasons for Recommendation
5.1The Modern Planning service has been in operation for around 6 months now and so there was a need to review it to make sure that it is fit for purpose. Subject to the recommendations in the Action Plan in Appendix 1, the Members Working Group agreed that the Modern Planning Service is a more efficient and effective way of delivering our planning service to our customers.
Consultation
5.2The review of the Modern Planning Service was undertaken by a cross- party Member Working Group.
6. References to Corporate Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy, Finance and Resources Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Brentwood Economic Strategy 2017-2020RESOLVED That Members approve the and agree that a 2017/18 Economic Work Plan is implemented to support the delivery ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.