Environment and Housing Management Committee approved this item on Wednesday 9 March 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED UNANIMOUSLY. 1. That the Committee formally approver and the Council proceed to tender and delegate power to the Head of Paid Service and Section 151 Officer to award the contract. REASON FOR RECOMMENDATION To enable the contract to be delivered appropriately with a high level of time and cost certainty.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
Report to Environment and Housing Management Committee
Executive summary
1.1The previous contract for this work was terminated due to performance issues.
1.2There remains a need to finish work to 8 blocks where these are incomplete and to undertake full works to the remaining 7 blocks where work has yet to commence.
1.3Given the value and complexity of the work it is necessary to undertake a competitive tender exercise to secure the services of another contractor. This shall proceed using the Delta E-Procurement portal.
1.4The cost of both work elements described above is estimated to be c.£240K.
Recommendation
2.1The Committee is asked to formally approve that we proceed to tender and delegate power to the Head of Paid Service and Section 151 Officer to award the contract.
3. Introduction and Background
3.1As set out above the previous contract was terminated early.
3.2Outstanding work is required to the following: Part Works (Previous undertaken by MNM Property Services) 142-152 Hawthorn Avenue 162-172 Hawthorn Avenue 91-101 Hawthorn Avenue 63-69 Hawthorn Avenue/13-14 Rowan Green East 15-20 Rowan Green East 21-26 Rowan Green East 1-4 Oaktree Close/11-13 Hawthorn Ave 9-14 Oaktree Close
Complete works (Previously within the MNM Property Services contract but nothing commenced) 15-17 Hawthorn Avenue/19-22 Oaktree Close 39-49 Hawthorn Ave 51-61 Hawthorn Ave 71-77 Hawthorn Ave/11-12 Rowan Green West 90-100 Hawthorn Ave 5-10 Rowan Green West 27-32 Rowan Green East
4. Issue, Options and Analysis of Options
4.1It was necessary to fully consider and ascertain the best way forward with these works given the prolonged disruption to the residents. There were two options identified and these are outlined below.
Options considered
Explore the use of a secondary organisation from the original tender process. Undertake a new tender process including all statutory leasehold consultation (Section 20).
4.3The first option was discounted as the original tender process had been run a relatively considerable time ago, late 2014 and there could be no certainty that costs would remain as originally offered.
4.4Given that there is to be a new contract and subsequently a new contractor it is necessary to re-issue Section 20 notices to leaseholders. 5. Reasons for Recommendation
5.1To enable the contract to be delivered appropriately with a high level of time and cost certainty.
5.2Residents will benefit from the works being completed with a superior level of professionalism.
5.3The work will be completed during the summer enabling wet product curing times to be met and a reduced level of protection offered. This should enable the works to proceed apace with minimal "down time".
Consultation
6.1Statutory leasehold consultation has commenced with the initial Notice of Intention having already being issued. All affected residents have been kept aware of the process and respective timeframes.
7. References to Corporate Plan
7.1Housing, Health and Wellbeing. The recommendation will enhance the resident dwelling external environment and provide increased protection to structural elements of the blocks.
8. Implications
Financial Implications Name & Title: Ramesh Prashar, Financial Services Manager Tel & Email: 01277 312513 / [email protected]
8.1The spend associated to this project was originally budgeted for in 2015/16, within the HRA Business Plan. The slippage of this budget has been built into 2016/17 capital program and funding. The final slippage figure will go to committee in the new financial year when the final outturn is produced.
Legal Implications Name & Title: Daniel Toohey, Monitoring Officer Tel & Email: 01277 312500 / [email protected]
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Housing Management Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Street Care Updates and ActionsRESOLVED UNANIMOUSLY that: 1. The Committee agreed to the Chief Executive writing to the ECC Cabinet Member for Highw...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.