Policy, Finance and Resources Committee noted this item on Tuesday 22 March 2016. Below is the council's own wording, with the papers it was decided on.
RESOLVED that: 1. That the Head of Paid Service together with the Section 151 Officer in consultation with the sub-committee comprising of the Chair and Vice-chair of the Policy, finance and Resource Committee and a representative of the Liberal Democrat and Labour Groups be granted delegated authority to negotiate and subject to satisfactory conclusion of those negotiations grant the Hutton Community Centre Charitable Incorporated Organisation (HCC CIO) up to a 15 year lease . Negotiations will include the provision by HCC CIO of adequate terms of occupancy. 2. That Members note the lease will be at less than commercial value but recognises the social value that will be provided by HCC CIO. REASON FOR RECOMMENDATION The report provides a recommendation to allow Members to make an informed decision as to the granting of a lease of Hutton Community Centre.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1The report provides an update to the committee in relation to discussions that have taken place between bidders for the letting of Hutton Community Centre.
1.2Members will be aware that against a background of potential co- operation between the two bidders, delegated authority was granted to the Head of Paid Service and Section 151 Officer to negotiate the terms of lease on Hutton Community Centre in consultation with a sub-committee comprising of the Chair and Vice-chair of the Policy, Finance and Resources Committee and a representative of the Liberal Democrat and Labour Groups.
1.3Despite best efforts, agreement could not be reached between the two bidders with negotiations breaking down in February 2016.
1.4Since that time officers have been considering the best solution for the residents of Brentwood, recognising the need to provide a solution that balances the financial return with the social needs of the area emphasising the strong links with the local community that are essential.
1.5Members are advised that the Head of Paid Service issued advice (10 March 2016) to both bidders that the then existing bid process had been stopped, in line with the Council’s tender invitation.
1.6Members are also advised that further information has been provided relating to the finances of the Hutton Community Centre Charitable Incorporated Organisation (HCC CIO). 2. Recommendations
2.1That the Head of Paid Service together with the Section 151 Officer be granted delegated authority to negotiate and subject to satisfactory conclusion of those negotiations grant the Hutton Community Centre Charitable Incorporated Organisation (HCC CIO) up to a 15 year lease. Negotiations will include the provision by HCC CIO of adequate terms of occupancy.
2.2That Members note the lease will be at less than commercial value but recognises the social value that will be provided by HCC CIO.
3. Introduction and Background
3.1Members will recall the decision of 5 June 2013 Community Services Committee where members considered a phased approach to the reopening of Hutton Community Centre. Those phases were:
Phase 1 – Building repaired/rebuilt ( if a cheaper and better option) open and being run by the Council Phase 2 – Development of a community based organisation to run the Centre Phase 3- Lease of the Centre to an independent organisation.
3.2The criteria set out before Members consisted of the following:
That the primary usage will be a balance between community and sports use That there should also be a balance between fee paying and drop- in use (to be looked at as part of the process of developing the business case) A cafe will be provided and space will be made available to provide a limited bar facility but the views of the public will be sought on this The Centre needs to be sustainable in each phase Facilities Management arrangements will need to be put in place That the Council will look after the structure and the exterior of the building whilst it is running the Centre
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy, Finance and Resources Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Brentwood Economic Strategy 2017-2020RESOLVED That Members approve the and agree that a 2017/18 Economic Work Plan is implemented to support the delivery ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.