Brentwood Garage Sites Update

Decided Committee 2 papers

Environment and Housing Management Committee decided this item on Wednesday 15 June 2016. Below is the council's own wording, with the papers it was decided on.

Item50

Resolved

RESOLVED UNANIMOUSLY . REASONS FOR DECISION The council would progress the design to tender and the procurement of a building contractor for Fawters Road and Magdalen Gardens directly, pending the outcome of the financial assessment. It would contribute towards the council meeting its Right To Buy Capital Receipt expenditure targets for December 2016.
Word for word from the decision Brentwood published for this meeting. Source: brentwood.moderngov.co.uk

Follow this further

Built from Brentwood's papers

What the report saysPro

Report to Environment and Housing Management Committee

Executive summary

1.1The report provides an update on progress in delivering the Garage Site redevelopment proposal.

1.2In September 2015 the committee granted approval to procure a Registered Provider (RP) developer framework to acquire and redevelop Magdalen Gardens and to redevelop Fawters Close for older people’s housing to remain in Council ownership.

1.3By January 2016, with significant changes to the funding of local authorities, the Council sought to identify alternative revenue funding streams for the General Fund. The Council is currently exploring how garage site redevelopments could generate revenue funding for the General Fund.

1.4This financial assessment is ongoing. Whilst this is taking place, the procurement of a RP framework has been placed on hold pending the outcome of the assessment. It was the intention that the Council would invest the Right To Buy Capital Receipts with the RP framework partners. Since this is now on hold, consultants have been commissioned to prepare a specification and tender drawings to enable the Council to procure a building contractor for Fawters Close and Magdalen Gardens. This will contribute towards the Council meeting the December 2016 Right To Buy Capital Receipt expenditure target.

1.5A separate project management tender is to be undertaken to seek architectural advice, contracts administration and cost management throughout the construction process to completion and handover, as there is no in-house development team. 1.6 The third site identified in the garage site programme, Fielding Way has been assessed and is not considered viable for housing redevelopment. An alternative site is being identified as part of the next tranche of garage sites to be assessed for the programme.

2. Recommendation(s)

2.1That delegated authority is granted to seek tenders to procure a building contractor for the redevelopment Fawters Close and Magdalen Gardens.

2.2That delegated authority is granted to seek tenders to appoint consultants to provide architectural advice, contracts administration and cost management throughout the construction process to completion and handover, as there is no in-house development team.

2.3That delegated authority is granted to the Chief Executive and Finance Director in consultation with the Chair of Environment & Housing Management Committee to award the building contract to the successful building contractor within the approved budget.

3. Introduction and Background

3.1In September 15, the Council approved the procurement of a framework of RP developer partners to acquire and redevelop the freehold or long leasehold interest in the garage sites for affordable housing, with Fawters Close retained in Council ownership and managed by the Council.

3.2A RP framework was considered the preferred development option because RPs have the track record and capacity to deliver high quality new build affordable housing.

3.3However, by January 16, as a result of the changes to the funding of local authorities, the Council began to identify potential revenue funding sources for the General Fund.

3.4The procurement of a framework of RPs has been placed on hold pending the completion of a full financial assessment of the garage site redevelopment programme as a possible funding source. 4. Issue, Options and Analysis of Options

4.1A full assessment of the financial options is ongoing. The assessment will consider a number of options and their impact on revenue income generation for the General Fund.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ExemptAppendix A 42 KB Download
PDF
Brentwood Garage Sites UpdateReport 100 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 20 attended
CH
Councillor Chris HossackChair, present
CP
Councillor Cliff PoppyVice-Chair, present
JC
Councillor Jon ClokeCommittee Member, present
MA
Councillor Mrs Ann CoeCommittee Member, present
MV
Councillor Mrs Vicky DaviesCommittee Member, present
MA
Councillor Mrs Alison FulcherCommittee Member, present
WR
Councillor William RussellCommittee Member, present
MJ
Councillor Mrs Jo SquirrellCommittee Member, present
JT
Councillor James TumbridgeCommittee Member, present
MJ
Councillor Mrs Jill HubbardSubstitute, in attendance
DC
David CarterOfficer, present
MD
Mike DunOfficer, present

All 20 on the meeting page

On this subject at Brentwood

Search all
  1. Brentwood Garage Sites UpdateThis decision
  2. Application No: 23/01044/FUL Garages Highwood Close Brentwood EssexApproved
  3. Land adjacent to garages at 49 sir francis way brentwood essex creation of a grasscrete surface for car parking spaces on grass verge, with the inclusion of timber posts and flush concrete kerbing. application no: 14/01494/bbcApproved

More from Brentwood Environment and Housing Management Committee

All decisions
MeetingDecisionOutcome
9 Mar 2017 Housing StrategyRESOLVED UNANIMOUSLY that: The Committee formally approve the final “ 2017-2020” for immediate adoption (Appendix A o... Approved Open
9 Mar 2017 Empty HomesRESOLVED UNANIMOUSLY : 2.1 To produce a skeleton Empty Homes Strategy to provide direction of travel. 2.2 To produce ... Approved Open
9 Mar 2017 Street Care Updates and ActionsRESOLVED UNANIMOUSLY that: 1. The Committee agreed to the Chief Executive writing to the ECC Cabinet Member for Highw... Agreed Open
7 Dec 2016 Fees and Charges - Street Scene and HousingRESOLVED UNANIMOUSLY that: The proposed fees and charges attached in Appendix A and B of the report were agreed and i... Agreed Open
7 Dec 2016 Housing Strategy 2017-2020RESOLVED that Members: 1. Formally approved the draft Housing Strategy 2017-2020. 2. Formally approved the merger of ... Approved Open