General Fund and Housing Revenue Account (HRA) Budget 2017/2018
ApprovedFinance6 papers
Policy, Finance and Resources Committee approved this item on Wednesday 15 February 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED That the Committee recommends to Council on 1 March 2017: General Fund: 1. To approve the General Fund – Revised MTFP for 2017/18 as shown in Table 7.1 at paragraph 8.2 which includes the proposed savings target envelope as shown in Table 8 at paragraph 8.7 of this report. Housing Revenue Account (HRA) 2. To approve the HRA Business Plan for 2017/18 and beyond as shown in Appendix B of the report. 3. To approve a 1% decrease in rents for 2017/18 and for the following 2 years. 4. To recommend to apply the formula rent to all new tenancies from April 2017/18. Capital Programme 5. To approve the proposed Capital Programme and Funding totalling £33.9 million for 2017/18 to 2019/20 as set out in Tables 15 and 16 of this report. 6. To approve the Treasury Management and Investment Strategy as set out in Section 12 of the report. 7. To note the Section 151 Officer’s Assurance Statement as set out in Section 13 of the report. (Cllr Barrett declared a non-pecuniary interest under the Council’s Code of Conduct by virtue of being a Council leaseholder). Reason for recommendations The Council is required to approve the Budget as part of the Budget and Policy Framework.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1The Medium Term Financial Plan (MTFP) considered by Policy, Finance and Resources Committee on 29 November 2016 gave Members an update on the various significant changes that would impact on the Council’s financial position. Particular issues highlighted, relevant to the General Fund & HRA included the phasing out of the Revenue Support Grant (RSG), changes to the New Homes Bonus & the Business Rates Retention schemes.
The fundamental principles of the Council’s MTFP are to:
(i) Maintain a sustainable financial position against a background of unprecedented financial uncertainty and reduced government funding, including the delivery of efficiency targets.
(ii) Support the vision of our Borough through appropriate identification of resources required to deliver the key priorities outlined in the ‘Vision for Brentwood’.
(iii) Maximise opportunities and mitigate risks associated with the fundamental change to the way in which local government is financed.
1.2This report considers:
(i) The General Fund budget proposals for 2017/18 to 2019/20.
(ii) The Housing Revenue Account (HRA) budget proposals for 2017/18 onwards.
(iii) The Capital Programme 2017/18 to 2019/20.
(iv) The Treasury Management & Investment Strategy for 2017/18. 2. Recommendations
That the Committee recommends to Council on 1 March 2017: General Fund: 2.1 To approve the General Fund - Revised MTFP for 2017/18 as shown in Table 7 at paragraph 8.2 which includes the proposed savings target envelope as shown in Table 8 at paragraph 8.7 of this report.
Housing Revenue Account (HRA) 2.2 To approve the HRA Business Plan for 2017/18 and beyond as shown in Appendix E of this report.
2.3To approve a 1% decrease in rents for 2017/18 and for the following 2 years.
2.4To recommend to apply the formula rent to all new tenancies from April 2017/18.
Capital programme 2.5 To approve the proposed Capital Programme and Funding totalling £33.9 million for 2017/18 to 2019/20 as set out in Tables 15 and 16 of this report.
2.6To approve the Treasury Management and Investment Strategy as set out in Section 12 of this report.
2.7To note the Section 151 Officer’s Assurance Statement as set out in Section 13 of this report. 3. Introduction and Background
3.1The financial pressures that face Local Government are well known. Despite these pressures however, the Council remains committed to both the maintenance of service delivery and providing community outcomes that enhance the quality of life for the residents of Brentwood.
3.2The challenges that Brentwood face, from a finance perspective, are clearly shown in “Table 1 – Financial Position Statement” This table indicates the following results:- Table 1A – Summary of funding position reported 4 March 2015 Table 1B – Summary of funding position reported 2 March 2016. Table 1C – Summary of funding position in this report.
3.3The transformation that the Council is undergoing is both radical and moving at pace. It is focused on keeping a clear eye on our residents needs and delivering a legacy for the future. Projects such as the Town Hall Hub and refurbishment, the Town Centre (incorporating William Hunter Way), the delivery of the Local Develop Plan (LDP) are being delivered whilst the Council is changing its organisational structure, working with new partners and constantly looking at ways to improve its offering to residents.
3.4A comparison of the working balances In Table 1 for the three years (2016/17: 2017/2108: 2018/2019) show the positive result of the Council’s ability to turn around what is an unprecedented period in the financial life of Brentwood Borough Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy, Finance and Resources Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Brentwood Economic Strategy 2017-2020RESOLVED That Members approve the and agree that a 2017/18 Economic Work Plan is implemented to support the delivery ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.