Leisure Strategy - Phase 1 update and recommendations
AgreedScrutiny1 paper
Corporate Projects Scrutiny Committee agreed this item on Monday 25 September 2017. Below is the council's own wording, with the papers it was decided on.
It was agreed at the 3 July 2017 Corporate Project Scrutiny Committee to establish a Leisure Strategy Working Group (LSWG) to inform and assist the Community, Health and Housing Committee in agreeing recommendations on each of the three phases of the Leisure Strategy. These three phases were agreed by the Policy, Projects and Resources Committee on 20 June 2017. The report before Members was an update on the progress under Phase 1. The LSWG consisted of Cllrs Pound, Middlehurst, Murphy, Davies and Hubbard and met on 2 August and 6 September 2017. Members debated the content of the report and the recommendations contained therein and concluded that the report lacked sufficient detail and background information to enable scrutiny of the recommendations and findings of the working group. Cllr Hossack requested that officers contact two major leisure operators so that they can provide a presentation and information to members to assist with their deliberations. A motion was MOVED by Cllr Tumbridge and SECONDED by Cllr Trump to require a full report including accompanying information is provided to the next committee meeting in order to enable full scrutiny of the working groups findings. A vote was taken by a show of hands and it was RESOLVED UNANIMOUSLY : 1. That a full report from officers and th eLSWG with annexes to be able to scrutinise the recommendations. REASON FOR RECOMMENDATIONS The Council needs to ensure that its Leisure Facilities were fit for purpose, sustainable, accessible to the residents and visitors, and support the Council’s priorities of improving health and wellbeing of its residents.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1It was agreed at the 3 July 2017 Corporate Projects Scrutiny Committee to establish a Leisure Strategy Working Group (LSWG) to inform and assist the Community, Health and Housing Committee in agreeing recommendations on each of the three phases of the Leisure Strategy. These three phases were agreed by the Policy, Projects and Resources Committee on 20 June 2017. The report before Members is an update on the progress under Phase 1.
1.2The LSWG consists of Cllrs Pound, Middlehurst, Murphy, Davies and Hubbard and met on the 2 August and 6 September 2017.
Recommendations
2.1That Members agree the update on the progress of Phase 1 of the Leisure Strategy work and that the following recommendations are provided to a future Community Health and Housing Committee for consideration:
a) That officers work with partners to develop a unique selling point for Brentwood’s leisure facilities. b) That any development plans ensure that all facilities are accessible for all, including paths. c) That use is made of existing trails and paths to link the Council’s leisure facilities. d) That any building development considered will be sustainable/eco- friendly and sympathetic to its surroundings. e) That officers liaise with other authorities about their own leisure facilities to identify opportunities and issues. f) That officers explore potential external funding models. g) That representatives from Bellway Homes are invited to the official opening of the refurbished Warley Play Area. 3. Introduction and Background
3.1The Council commissioned a Value for Money and Options Appraisal of its Leisure and Cultural facilities. This was completed in February 2017 and a copy of the 4Global report was circulated to all Members after the Policy, Projects and Resources Committee in June 2017. 3.2. It was agreed at the Policy, Projects and Resources Committee that the Leisure Strategy work be split into three phases and that the Corporate Projects Scrutiny Committee would set up a cross party working group to scrutinize the work within each of those phases. 3.3. The report before Members is to update on the progress on, and any proposed work to be undertaken in each of those phases and come back to this committee with their recommendations. 3.4. The LSWG has met in August and September and the initial meeting set out the scope for the group in respect of the Leisure Strategy work, agreed the Terms of Reference of the group and the frequency of the meetings. The first phase looked at the areas of improvement proposed for King George’s Playing Fields and Warley Playing Fields, together with the Council’s Community Halls which are currently managed by Brentwood Leisure Trust and Brentwood Leisure Trading.
4. Issues, Options and Analysis of Options
4.1The 4Global report set out a number of options and recommendations which were not necessarily agreed by Members. In order to ensure that the Council makes sound decisions on the future of its leisure facilities it was proposed that the Corporate Projects Scrutiny Committee be set up to scrutinize the Council’s key projects, one of which is the progression of the Leisure Strategy.
4.2Phase 1 of the Leisure Strategy focusses on future leisure requirements in King George’s Playing Fields, Warley Playing Fields and the Council’s Community Halls.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.