Resolved
To approve the direction of the Asset Development Programme. Reason for the Recommendation To update the Committee on the progress of the Asset Development Programme.
Policy, Projects and Resources Committee approved this item on Tuesday 18 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
To approve the direction of the Asset Development Programme. Reason for the Recommendation To update the Committee on the progress of the Asset Development Programme.
1.1The aim of the Council’s Asset Development Programme (“ADP”) is to realise the potential of the Council’s property asset base so as to deliver improved revenue streams from the portfolio but at the same time securing the regeneration, economic development and housing objectives of the Council. This report provides an update on the work of the Asset Development Programme Project Board (“Project Board”) to date.
1.2This report outlines the progress made by the Project Board on a) the Joint Venture Partner Procurement, b) the wholly owned Company (Seven Arches Investments Ltd), c) the Early Successes Programme and other in-house items including the Memorial Wall project.
2. Recommendation(s)
2.1To approve the direction of the Asset Development Programme
3. Introduction and Background
3.1The Project Board advises on all projects relating to the ADP, which includes projects relating to Corporate Asset Management, Property Joint Venture Partnerships and Seven Arches Investments Ltd. It will in turn be informed by the work of the Corporate Asset Management Group.
3.2On 19 September 2017 this Committee approved a hybrid approach for delivering the asset development programme. The hybrid approach involves the self-development of simple sites by the Council, while more complex sites would be undertaken jointly between the Council and a procured joint venture partner. 3.3 To maintain a revenue stream for the Council the self-developed sites will be leased out on a commercial basis. The Localism Act 2011 allows local authorities to do anything an individual can do. However, section 4 of the act requires that any commercial activity must be undertaken through a company.
3.4Therefore, to comply with the requirements of the Localism Act 2011 the Council established a wholly owned company, Seven Arches Investments Ltd (“SAIL”) on 12th April 2018.
3.5The wholly owned company will seek to engage in a variety of commercial activities that will be asset based initially, and subject to appropriate business cases and financial sustainability could be extended into other areas such as service provision.
3.6Sites developed with a partner may also require the establishment of a separate company to comply with legislative requirements and to formalise the partnership. This will likely be in the form of a limited liability partnership (LLP) with ownership split 50:50. The best arrangement will be assessed through the procurement process, currently underway.
4. Loan Drawdown Facility
4.1The Project Board has received several initial investment opportunities that have been presented by the appointed property investment advisors. From these opportunities and the recommendations of the property investment advisors it became apparent that access to a loan drawdown facility would be more commercially appropriate than tranches of loans.
4.2The drawdown facility allows more than one potential investment to be pursued at a time, preventing lost opportunities for relatively small amounts and allowing greater diversification. It also allows the company to operate in a more commercially competitive manner. A facility of £30m was deemed appropriate at this stage.
4.3Approval for the increased drawdown facility was approved by this committee on the 19th June 2018 and subsequently ratified by Full Council on the 27th June.
4.4The first drawdown of this facility was for £6m being in respect of the purchase of SAIL’s first investment and for working capital going forward. 5. Progress to date – Joint Venture Partner Procurement
5.1Following the publication of an Official Journal of the European Union (OJEU) Notice and a dedicated website on 23rd March 2018 there were 15 organisations who submitted applications by the deadline of 4th May.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 87 KB | Download |
PDF |
Asset Development Programme UpdateReport | 290 KB | DownloadRead as text |
Follow Policy, Projects and Resources Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Sep 2018 | 2018/19 General Fund Revenue, Housing Revenue Account, Capital Budget Monitoring and Treasury Activity UpdateRESOLVED UNANIMOUSLY: 1. To agree the projected outturn position for 2018/19 of the Council’s General Fund Revenue bu... | Agreed | Open |
| 18 Sep 2018 | Department for Communities and Local Government (MHCLG) Pilot Programme for 75% Business Rates Retention - 2019/20RESOLVED UNANIMOUSLY: 1. Members note the content of the report and its potential implications for the forthcoming bu... | Agreed | Open |
| 18 Sep 2018 | Feasibility Study for Parking on Housing GreensRESOLVED UNANIMOUSLY: 1. To instruct officers to identify possible sites for parking on Housing Greens and undertake ... | Decided | Open |
| 18 Sep 2018 | Leisure StrategyThat Members agree the and action plan at Appendix A. Reasons for Recommendation As part of the Council’s due diligen... | Agreed | Open |
| 18 Sep 2018 | Data Protection OfficerShared arrangements that are currently in place with Thurrock Council to continue and are to be reviewed in September... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.