That the Joint Venture partnership contract and framework agreement be awarded to Morgan Sindall Investments Ltd through Seven Arches Investments Ltd, subject to agreement of final detailed terms between the parties in compliance with procurement regulatory requirements. 2. That the Director of Corporate Resources be given delegated authority in consultation with the Leader of the Council, to agree the final detailed terms and to enter into the Joint Venture partnership agreement and related contracts in compliance with procurement regulatory requirements. 3. That the three initial sites (William Hunter Way Car Park, Maple Close garage site and Westbury Road Car Park) have site development schemes worked up under the agreement by the Joint Venture. 4. That a funding facility of up to £60m at any one time be made available to provide equity and senior debt in relation to the Joint Venture with the use of the facility on the recommendation of the Section 151 Officer with the approval of Policy, Resources and Economic Development Committee. Reason for Recommendation Council approval is required to award a major contract.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1This report seeks approval to award the Joint Venture (JV) contract to the preferred bidder. The JV contract is for a 30 year 50:50 Joint Venture partnership between Seven Arches Investments Ltd (SAIL) and the preferred bidder.
1.2An initial 3 sites were selected to be the first to have site development schemes prepared by the JV and formal approval for this is sought.
1.3As a 50:50 partnership an equity cash contribution maybe required in addition to the land value to ensure funding remains matched between the partners. There is also opportunity to provide loan funding to the JV, which will provide an additional income stream.
2. Recommendation(s)
2.1That the Joint Venture partnership contract and framework agreement be awarded to Morgan Sindall Investments Ltd through Seven Arches Investments Ltd, subject to agreement of final detailed terms between the parties in compliance with procurement regulatory requirements.
2.2That the Director of Corporate Resources be given delegated authority in consultation with the Leader of the Council, to agree the final detailed terms and to enter into the Joint Venture partnership agreement and related contracts in compliance with procurement regulatory requirements. 2.3 That the three initial sites (William Hunter Way Car Park, Maple Close garage site and Westbury Road Car Park) have site development schemes worked up under the agreement by the Joint Venture.
2.4That a funding facility of up to £60m at any one time be made available to provide equity and senior debt in relation to the Joint Venture with the use of the facility delegated to the Section 151 Officer in consultation with Group Leaders.
3. Introduction and Background
3.1On 21 March 2018 Council approved a Competitive Dialogue Procedure under the Public Contracts Regulations 2015, to procure a Joint Venture partner. This followed a series of member engagement through previous Committee reports, Project Board, all member and ward member briefing sessions.
3.2Through advice from specialist consultants, use of soft market testing and member engagement it became apparent that a Joint Venture partner would be the best delivery option for the Asset Delivery Programme.
3.3At the Council meeting in March 2018 the procurement documentation was approved and since that meeting officers and specialist consultants have been carrying out the procurement process in accordance with those documents and the Public Contracts Regulations 2015.
3.4The procurement process with timescales was presented back in March 2018 and had remained on schedule until a preferred bidder was selected. 3.5 The procurement process is outlined in the following paragraphs:
3.6Qualification Stage – This was the first sift of bidders and identified early those who were most likely to be selected as a partner. Bidders responded to the Selection Questionnaire and were evaluated in accordance with their responses. Following this, five bidders were selected to go through to the next stage. Restricting the number to five provided the Council with a strong selection of partners and kept the assessment resources required at the next stage reasonable. The bidders also remained engaged knowing the competition had decreased when they progressed to the detailed solution stage.
3.7Detailed Solution Stage – The successful five bidders submitted their detailed solutions in accordance with the Council’s instructions. Solutions were discussed through a series of dialogue sessions between the bidders and the Council throughout June and July 2018. Bidders then submitted their responses to the evaluation questions. These were evaluated in accordance with the Council’s requirements, as determined by the scoring methodology outlined in the procurement instructions. The best 3 bids were taken through to the final stage.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of the Tier 2 Chief OfficerRESOLVED UNANIMOUSLY : R1 - To appoint the Strategic Director Finance (Section 151 Officer). Confidential recommended...
Brentwood Local Plan 2016-2033: AdoptionRESOLVED to: R1. Adopt the Brentwood Local Plan 2016-2033 (Appendix A), which incorporates the Main Modifications rec...
Exclusion of the Press and PublicRESOLVED UNANIMOUSLY that the press and public be excluded from the meeting as the next item of business to be consid...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.