RESOLVED UNANIMOUSLY . Members are asked to: R1. Approve the response to the Lower Thames Crossing Local Refinement Consultation, as set out in Appendix A. Reasons for Recommendation It is recommended that the issues set out in Appendix A be issued in response to the Lower Thames Crossing Community Impacts Consultation. The council has engaged with National Highways on the Lower Thames Crossing project to date. It is proposed that issues raised in previous consultation responses are maintained where relevant and/or unresolved.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
Report to Policy, Resources & Economic Development Committee
Summary
National Highways are inviting views on the Lower Thames Crossing, a proposed new motorway connecting Essex and Kent through a tunnel beneath the River Thames to provide additional road capacity. A Local Refinement consultation has been launched following several previous consultations. This precedes the expected submission of a Development Consent Order application for the scheme.
This consultation includes several technical refinements to the project, some of which directly impact on infrastructure or land within Brentwood borough. In addition to the ongoing discussion taking place with National Highways regarding outstanding issues impacting the borough, this report sets out a proposed response to the local refinements.
Recommendation(s)
Members are asked to:
R1. Approve the response to the Lower Thames Crossing Local Refinement Consultation, as set out in Appendix A.
Main Report
Introduction and Background
1. The Lower Thames Crossing is a proposed new motorway connecting Kent, Thurrock and Essex through a tunnel beneath the River Thames. On the south side of the Thames, the new road will link the tunnel to the A2 and M2 in Kent. On the north side, it will link to the A13 and junction 29 of the M25 in the London Borough of Havering, and areas for associated works in the south-west of Brentwood borough. According to National Highways it will provide much needed new road capacity across the river east of London with quicker and more reliable journeys locally, regionally and nationally.
2. This is the most ambitious project of its kind in the country. It is the largest single road investment project in the UK since the M25 was completed around 35 years ago. The crossing under the Thames will be the longest road tunnel in the country. At 16 metres in diameter, it will be one of the largest bored tunnels in the world. Current timescales for the project are for construction to commence from 1 January 2024 and be completed by 31 December 2029.
3. There have been several consultations held regarding the Lower Thames Crossing as the project has progressed, which the council has responded to. Most recently the council responded to the Community Impacts Consultation launched in July 2021 (Item 140 Policy, Resources and Economic Development Committee, 30 September 2021).
4. In October 2020, National Highways submitted a Development Consent Order (DCO) application to the Planning Inspectorate for examination. In November 2020, following feedback from the Inspectorate regarding the content of the application and supporting information, National Highways decided to withdraw the application.
5. Following the Community Impacts Consultation in July 2021 it was anticipated that the DCO would be resubmitted towards the end of last year. Since then further work has been undertaken by National Highways on localised changes to the project. The changes were in response to ongoing design work, engagement with stakeholders and feedback through previous consultations. It is expected that the DCO application will be submitted later this year following consideration of comments in response to the local refinement consultation.
Issue, Options and Analysis of Options
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy, Resources & Economic Development Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
Community Infrastructure Levy SubmissionRESOLVED to: 1. Note the outcomes of the Regulation 16 consultation on the draft Community Infrastructure Levy Chargi...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.