This report presents the Seven Arches Investments Limited (SAIL) quarterly update to shareholders and provides management updates on the owned and managed commercial properties.
Main Report
Introduction and Background
1. At an Extraordinary Council meeting held on 21 March 2018, the creation of Seven Arches Investments Limited (SAIL) was approved and the shareholder’s powers delegated to the Policy, Projects and Resources Committee. Subsequently SAIL was registered with Companies House on 12 April 2018.
2. In accordance with the Shareholder’s Agreement, a quarterly management and business update is to be provided to Policy, Resources and Economic Development Committee.
Quarterly update
3. In accordance with the requirements of the Shareholder’s Agreement, SAIL’s Quarterly report is included at Appendix A.
References to Corporate Plan
4. This fits with the Council’s ‘Delivering an efficient and effective council’ priority, to explore new income generating ideas and opportunities. Implications
Financial Implications Name & Title: Jacqueline Van Mellaerts, Corporate Director (Finance & Resources) and S151 Officer Tel & Email: 01277 312500/[email protected]
5. Although this report has no direct financial implications. It should be noted that Seven Arches Investments Limited will provide a substantial income stream to Council which is included within its Medium-Term Financial Strategy.
6. SAIL will deliver these returns by following two streams of activity. Securing Investments opportunities commissioned through a specialist property consultancy; as well as launching a Joint Venture partnership for medium to longer term investment with potentially higher yield returns from year 6. Investments do carry a degree of risk and SAIL has reviewed its business plan to demonstrate its sustainability. The Business Plan identifies that annual investment plans are carried out; quarterly health checks will be presented to their shareholders and individual assets management plans are completed for each asset.
7. SAIL has in place a loan facility agreement of £60m with the Council, which was approved in October 2019. Currently the full £60 has been utilised. This returns to the shareholder (Brentwood Council) approximately £2.4m per annum by providing loans to SAIL at a commercial rate, as well as a further £450k for provision of services. SAIL also undertakes the lettings of residential properties and returns the income to the Council less SAIL’s costs.
Legal Implications Name & Title: Claire Mayhew, Corporate Manager, Corporate Manager (Democratic Services) & Deputy Monitoring officer Tel & Email: 01277 312500/[email protected]
8. The Council has power under s1(1) of the Localism Act 2011 to do anything which individuals may do provided it is not prohibited by legislation and subject to public law principles (‘the general power of competence’). Further statutory powers exist to create and invest in SAIL and s1 of the Local Government Act 2003 permits the Council to borrow and lend. The recommendations set out in this report are in accordance with decisions previously taken by Council for establishing and implementing the business.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Exempt Appendix AAppendix | 33 KB | Download |
PDF |
Seven Arches Investments Limited Quarterly reportReport | 84 KB | DownloadRead as text |
Follow Policy, Resources & Economic Development Committee at Brentwood and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Mar 2023 | Response to Government Consultation on Reforms to National Planning PolicyRESOLVED to: 1. Approve the response to the Government’s consultation on reforms to national planning policy, as set ... | Approved | Open |
| 8 Mar 2023 | Community Infrastructure Levy SubmissionRESOLVED to: 1. Note the outcomes of the Regulation 16 consultation on the draft Community Infrastructure Levy Chargi... | Noted | Open |
| 8 Mar 2023 | EXEMPT - Less than Best for Nightingale Centre for SNAPRESOLVED. [Cllr Russell declared a pecuniary interest and left the meeting prior to the item being debated and did no... | Decided | Open |
| 8 Feb 2023 | UK Shared Prosperity Fund 2023-2025RESOLVED UNANIMOUSLY . | Decided | Open |
| 8 Feb 2023 | Dunton Hills Garden Village Supplementary Planning Document (SPD)RESOLVED UNANIMOUSLY . Members were asked to: R1. Adopt the Dunton Hills Garden Village Supplementary Planning Docume... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.