RESOLVED UNANIMOUSLY that: R 1. To agree the revised trial sites detailed below for rewilding and to agree the change in management for these areas during the trial period. REASON FOR RECOMMENDATION Officers have reviewed the sites bought to the committee by its members and have assessed the suitability of each site. The below information sets out what is achievable at minimal cost with negligible impact on resource for the Green Spaces operational teams. The sites have been assessed in line with the proposal of natural rewilding methods where grasses and flora are left to regenerate natively. These proposed sites as bought forward by ward members do not account for cultivation of specific wild flora, which is out of scope of the trial. It should be noted that these sites if accepted, can be easily reverted to formally mowed verges/greens using existing resource and machinery.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
COMMITTEE TITLE – Clean and Green Committee DATE – 26th February 2024
REPORT Clean and Green Rewilding Options and Trial Sites - Update TITLE: REPORT OF: Adam Aldridge, Corporate Manager - Green Spaces
REPORT SUMMARY This report provides revised options for sites bought forward by Clean and Green Committee for the trial of “rewilding” areas of parks and verges.
RECOMMENDATION 1. To agree the revised trial sites detailed below for rewilding and to agree the change in management for these areas during the trial period.
SUPPORT ING INFORMATION
1.0REASON FOR RECOMMENDATION 1.1 Officers have reviewed the sites bought to the committee by its members and have assessed the suitability of each site. 1.2 The below information sets out what is achievable at minimal cost with negligible impact on resource for the Green Spaces operational teams. 1.3 The below sites have been assessed in line with the proposal of natural rewilding methods where grasses and flora are left to regenerate natively. These proposed sites as bought forward by ward members do not account for cultivation of specific wild flora, which is out of scope of the trial. 1.4 It should be noted that these sites if accepted, can be easily reverted to formally mowed verges/greens using existing resource and machinery.
2.0BACKGROUND INFORMATION 2.1 A report was presented to the Clean and Green Committee on the 11th of September 2023 to propose the plans for relaxed mowing in certain areas within the borough. The management options for these sites included relaxed mowing, natural regeneration, tree planting and establishment of wildflowers. 2.2 To address concerns over rewilding in certain areas and as requested by members, certain sites are no longer deemed feasible as part of this trial. Should a further review be required at these sites, a further paper will be presented to Clean and Green Committee indicating a cost and resource implication, as these sites could not be reverted easily during a trial period. 2.3 To define the management type of each area, the table below provides some detail on how each management option could be implemented. It is important to note that options beyond Relaxed Mowing and match funded whip planting will bear a significant cost and resource implication to the Councils Green Spaces department:
Management Option Detail Implementation Period Relaxed Mowing Area will be left to form a Immediate natural meadow. Implementation Establishment 1 year Area will receive a “mower width” perimeter cut as part of routine maintenance to ensure the area is presentable and intentional. This will include a regular cut of a “mower width” around and footpath, desire line, obstacles, or hard surfaced area.
Naturalised area will be cut once per annum with a “cut and collect” machine or a flail machine where collection is not possible. Tree Planting (Whips) A whip is an unbranched Whip Planting November young tree approximately – February 50cm to 1m in size. These are low 10 Years Establishment maintenance and would not require additional watering. Whips would be sourced from a sustainable source and be of a native variety. Tree Planting (Standards) A standard tree is an Standard Planting established tree of a size November – February greater than 2m in height. These would provide an Immediate Establishment “instant impact” but would require regular watering. 3 Year Watering Program Wildflower Meadow An area will be cultivated September – October in the Autumn months Implementation with a perennial wildflower mix 1-3 Year Establishment Period Bulb Planting October Implementation
Bulbs will flower each spring.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Volunteering Litter Picking GuidanceRESOLVED UNANIMOUSLY . Resolutions: R1: The Committee approved the Volunteer Litter Picking Guidance as set out at Ap...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.