Assets, Projects & Strategy Committee approved this item on Wednesday 18 September 2024. Below is the council's own wording, with the papers it was decided on.
RESOLVED UNANIMOUSLY for: R1: To recognise updates on the redevelopment of the Baytree centre which support the creation of key work packages and associated phased delivery programme. R2: Approve the recommendation to commence Phase 1 immediately. R3: Approve the recommendation to carry out pre-feasibility and design work in respect of Phase 2 on the basis that a fully developed scheme for this phase will be brought back to committee in Spring 2025. R4: Approve the recommendation to commence the procurement of a development partner for Phase 3. If an appropriate partner is identified this will be brought back to a future committee for approval. Reason for Recommendation: To enable progress on the redevelopment of the Baytree centre to continue in a challenging economic environment with higher interest rates and build costs. To ensure the redevelopment of the Baytree centre is firmly part of wider town centre placemaking and infrastructure improvements.
Word for word from the decision Brentwood published for this meeting.Source: brentwood.moderngov.co.uk
1.1To enable progress on the redevelopment of the Baytree centre to continue in a challenging economic environment with higher interest rates and build costs. 1.2 To ensure the redevelopment of the Baytree centre is firmly part of wider town centre placemaking and infrastructure improvements.
2.0BACKGROUND INFORMATION 2.1 After the Council purchased the Baytree Centre in 2021, a redevelopment scheme was approved in November 2022 which gained planning permission in March 2023. 2.2 It was agreed that the Council would borrow against the Public Works Loan Board (PWLB) to fund the development on the condition that rates stayed below 4%. Significant changes in the national economic situation means that the current PWLB 50-year rate is around 5.27% and therefore it has been prudent as part of ongoing due diligence and in an environment of rising costs and interest rates to consider current scheme viability. 2.3 At the same time, the development proposals have been considered against wider Council commitments to enhance the vitality of the town as it is recognised that the success of the Baytree Centre will act a key economic driver for the wider regeneration of the High Street. 2.4 The review has recognised that several opportunities exist these are: 1. Opportunities to work more widely with the Business Improvement District (BID) and stakeholders, to embed any new development into the town but also to work in partnership to improve existing areas – discussions are already underway with Heritage England, Heritage Lottery, Church commissioners and ECC Highways to see how partnership working can support the Councils aspiration in terms of placemaking. 2. To consider a partnership approach to bring in additional skills to limit Council risk and exposure. 3. Opportunity to create a development which could attract higher quality tenants and become a magnet to draw spend back into the town centre. 4. Opportunity for more placemaking and rethinking Brentwood’s Town Centre to develop high quality public realm around the Baytree Centre (a Town Square approach) which can also act as a footfall driver, providing enhanced spaces to host events and exhibitions during the day and at night.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Brentwood Centre Progress UpdateRESOLVED UNANIMOUSLY. Resolutions: R1: Noted the progress to date on the redevelopment and refurbishment of the Brent...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.