What was decided
The Finance System Replacement Programme is established, with TechnologyOne approved as the preferred replacement, subject to the due diligence and controls set out in the report.
The Strategic Director Resources (Section 151 Officer), in consultation with the Chair of the Committee and the Chief Legal Officer, is authorised to complete the procurement and enter the contract, provided the final proposal stays within the parameters in exempt Appendix B, the procurement route is compliant, and no material adverse issue arises from due diligence.
Up to £150,000 from General Fund Reserves is approved for additional one off procurement, project management, implementation and transition costs, additional to the existing budget for the current system and the ongoing software subscription provision.
Why
The current finance system is being replaced, with Advanced identified as the existing supplier that may need transitional or continuation cover.
Implementation risk and service continuity concerns are to be managed through limited transitional arrangements and interim project and systems capacity.
What happens next
Complete due diligence and the procurement process, then enter the contract with TechnologyOne within the parameters in exempt Appendix B.
If required, agree a transitional or continuation arrangement with Advanced, limited to the minimum period necessary and within the financial parameters in exempt Appendix B.
Set up programme governance, an implementation plan and budget control arrangements, with expenditure on the additional £150,000 authorised and monitored by the Strategic Director Resources.
The money
- up to £150,000 From General Fund Reserves, for additional one off procurement, project management, implementation and transition costs of the Finance System Replacement Programme, additional to the existing system budget and ongoing software subscription provision.
Options considered
- Chosen: TechnologyOne as the preferred replacement finance system. Subject to due diligence, a compliant procurement route, and the parameters in exempt Appendix B.
Implications
- Financial: Up to £150,000 drawn from General Fund Reserves, separate from the existing finance system budget and the ongoing software subscription provision.
- Legal: Procurement route must be compliant; contract signed by the Section 151 Officer in consultation with the Chair of the Committee and the Chief Legal Officer.
- Risk: Any arrangement with the current supplier Advanced is limited to the minimum period needed to manage implementation risk or protect service continuity.
- Staffing: Use of appropriate interim project and systems capacity is approved to deliver the programme.
Who and where
- The Strategic Director Resources (Section 151 Officer), who is authorised to lead the procurement, contracting and budget control.
- The Chair of the Finance and Future Development Committee and the Chief Legal Officer, who must be consulted on procurement and contracting decisions.
- The current finance system supplier, Advanced, which may be retained under a short term transitional or continuation arrangement.
- Council services that rely on the finance system, which gain a new TechnologyOne platform subject to successful due diligence and implementation.
Plain English for the jargon
- Section 151 Officer: The local authority's statutory chief finance officer, responsible for proper administration of financial affairs.
- General Fund Reserves: The council's main unallocated savings, held to manage risk and fund one off costs.
- TechnologyOne: Software company selected as the preferred supplier for the replacement finance system.
- Advanced: The council's current financial management software supplier, named in the decision as the existing provider.
- Exempt Appendix B: A confidential appendix to the report setting out the financial parameters for the procurement and any transitional arrangement.