Resolved
That Council noted the drafting error made in recording the minutes of the Council meeting on the 3 rd July 2013 and agreed that the correct contribution to Affordable Housing should be £370,000 and the Highways contribution should be £63,136.32 to improve active travel access between Rest Bay and Porthcawl town centre in a staggered/phased payment plan which would see £30,000 being paid upon the occupation of the first unit of residential accommodation within the site, and the remaining £33,136.32 (or the remainder of the index linked sum) paid upon occupation of 50% of the apartments, or exactly three years receipt of the first instalment, unless otherwise approved in writing. The meeting closed at 4.00pm.