Resolved
That Cabinet recommend to Council the approval of the revised Capital Programme as set out in Appendix 1 to the report.
Cabinet approved this item on Tuesday 24 June 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet recommend to Council the approval of the revised Capital Programme as set out in Appendix 1 to the report.
1.1The purpose of this report is to obtain approval from Cabinet to present a report to Council for a revised capital programme for 2013-14 to 2023-24.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1Capital investment in our assets is a key factor in meeting the Improvement Objectives set out in the Council’s Corporate Plan.
3.1On 19th February 2014, Council approved a capital programme for the years 2013- 14 to 2023-24. This report proposes amendments to that programme to reflect changes that have occurred since the programme was approved.
4. Current situation / proposal
4.1Since the capital programme was approved by Council in February 2014 there have been a number of changes which require Council to approve a revised capital programme for the period 2013-14 to 2023-24.
Changes are required to:
• reflect additional funding required to support some projects.
• re-profile spend across financial years following slippage in 2013-14.
• reflect changes to funding profiles for various schemes. For example, the Welsh Government has now confirmed the element of funding for the 21st Century Schools Programme which will be met from the Local Government Borrowing Initiative and that which will be met from capital grant.
• reflect re-allocations of Special Regeneration Funding (SRF) to/from specific projects, within the overall annual SRF allocation.
• Recognise new schemes in the programme such as Vibrant and Viable places.
1 4.2 Special Regeneration Funding
The capital programme includes an SRF annual allocation of £540,000, up to and including 2016-17. This provides flexibility in the capital programme to enable the Council to take advantage of and maximise external funding opportunities; mitigate funding shortfalls which can occur between grant bid and offers stages and provide some contingency for additional spending pressures on regeneration projects.
4.3Capital Programme 2013-14
The Quarter 3 monitoring report presented to Cabinet on 4th February 2014 identified a number of schemes which had variances compared to budget. Since then the position has been revised to provide an updated position.
In summary, total expenditure on capital in 2013-14 was £36.912 million, £2.398 million less than budget. Of this, £2.221 million is proposed to be carried forward into 2014-15, resulting in an underspend of £177,000. The majority of the underspend relates to funding retained for potential outstanding internal fees on completed capital schemes. Only £65,000 was required, resulting in an underspend of £135,000.
Two of the projects included in the quarter 3 monitoring report were in relation to Porthcawl Harbour and Maesteg Town Centre Regeneration. The current position is as follows:
Porthcawl Harbour Development The original budget approved for the project was £3.350 million, comprising £1.076 million from Visit Wales Grant and £2.274 million from Council resources. The current projected spend is £3.867 million, as a result of additional costs of early warning notices issued by the contractor, and other unforeseen works. Negotiations with the contractor are on-going and it is not possible to provide a definitive outturn figure at this point. Since approval, grant funding reduced by £52,000 to £1.024 million, and the directorate has utilised £250,000 of unallocated SRF funding to part meet the shortfall, along with a £24,000 revenue contribution towards flood damage works. It is proposed to use £300,000 from capital receipts from the sale of the Jennings building to meet the balance. This results in a revised budget of £3.872 million.
The Internal Audit section is currently reviewing this project and will provide a report to Audit Committee when complete.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
140624 7 Capital Programme 2014-24 AppendixAppendix | 46 KB | Download |
PDF |
Capital Programme 2013-14 to 2023-24Report | 41 KB | DownloadRead as text |
Follow Cabinet at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Oct 2023 | Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... | Noted | Open |
| 17 Oct 2023 | Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... | Noted | Open |
| 17 Oct 2023 | Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... | Noted | Open |
| 17 Oct 2023 | Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... | Approved | Open |
| 17 Oct 2023 | Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.