RESOLVED : That Cabinet: (1) Noted the update on the collaboration between Bridgend County Borough Council and South Wales Police to provide a joint fleet maintenance capability. (2) Approved the detailed agreement, as set out in the report, of the terms and costs of occupation of the Joint Vehicle Maintenance facility at the old Fiskars building on Brackla Industrial Estate and give delegated power to the Corporate Director – Communities in consultation with the S151 Officer and Assistant Chief Executive – Legal and Regulatory Services to agree any amendments or additions ... view the full minutes text for item 620.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1To provide a further update to Members in respect of the collaboration between Bridgend County Borough Council (BCBC) and South Wales Police (SWP) to provide a joint fleet maintenance (JVM) capability at the ex Fiskars building on Newlands Avenue, Brackla Industrial Estate.
2. Connection of Corporate Improvement Plan/ Other Corporate Priority
2.1The proposed amalgamation links to the Corporate Priority ‘Making Better Use of Resources’. It includes all aspects of the fleet operation including procurement, safe management/maintenance and disposal of vehicles. It also meets the requirements of the emerging collaboration agenda of the Welsh Government.
Background
3.1BCBC and SWP identified an opportunity to amalgamate their fleet maintenance operations at a shared location. This approach should provide a number of financial and non-financial benefits for each organisation:
• Reducing the aggregate cost of fleet maintenance • Improving fleet maintenance facilities and equipment • Improving customer service and transparency of the value for money offered by the fleet management and fleet maintenance service • Improving opportunities for staff development and a greatly improved working environment • Meeting the Welsh Government (WG) agenda for shared services • Enabling the potential sale of land on the SWP Headquarters site and the implementation of the draft Waterton Masterplan within the Parc Afon Ewenni programme
Both organisations are currently operating from facilities that are beyond their economic life, requiring significant capital investment to bring them up to a standard that supports efficient and modern fleet maintenance operations. Relocating both operations to a single new site would also unlock the potential of the current locations for development opportunities.
3.2A report was approved by Cabinet in July 2013 setting out the principles of the Heads of Terms agreement between the parties. It was agreed that work would continue with SWP to develop detailed cost estimates and an implementation plan. This matter was reported to Cabinet for update in December 2014. 3.3 A number of sites have been investigated to locate the JVM workshop, including the option of constructing a new facility at the Council’s Bryncethin depot. Unfortunately this option was halted following ground surveys that identified risks associated with mine workings and ground contamination, resulting in potential increased costs over and above the available budget. As a result the project board agreed that Bryncethin depot no longer represented a viable site for the new shared facility and that alternative options would need to be sought.
3.4The estates teams from both SWP and BCBC again reviewed the properties available to identify a building to be purchased and adapted within the available budget. A number of potentially suitable buildings were identified amongst which included the Fiskars building in Brackla Industrial Estate. A review of each available option was completed and the Fiskars premises were deemed the most suitable.
3.5SWP purchased the Ex-Fiskars property in May 2014 at a cost of £1.2 million. In addition to this they have committed to an alteration and improvement programme of approximately a further £800k for the development of the JVM, including supplying equipment. The JVM will occupy approximately half of the building, SWP are utilising the remainder of the building for other operations.
4. Current Situation
4.1As part of the design and refurbishment of the JVM, layout plans have been drawn up and agreed by BCBC and SWP Fleet Managers. These plans have been communicated to all staff affected.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies