RESOLVED : That Cabinet: (1) Agreed and authorised that the Council enter into the Development Agreement with Coastal Housing Group Limited to deliver the Rhiw Gateway Project and any ancillary contracts and agreement ancillary thereto, including collateral warranties and licences, and authorise the sale of the land in respect of the relevant housing element of the project to Coastal Housing Group Limited in accordance with the final terms of the Development Agreement. (2) Delegated authority to the Corporate ... view the full minutes text for item 677.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
To seek Cabinet approval to enter into a Development Agreement with Coastal Housing Group Limited (CHGL) to deliver the Rhiw Gateway project under the Welsh Government’s (WG) Vibrant & Viable Places (VVP) Programme in light of the grant award of £5.98 million for Bridgend town centre and to authorise the sale of land to Coastal Housing Group Limited for the housing element of the scheme.
2. Connection to Corporate Improvement Plan/Other Corporate Priority
2.1The New Regeneration Framework links to the following corporate themes:
• Corporate Plan (2013-2017) Priority 1 – Working Together to Develop the Local Economy • Corporate Regeneration Strategy (Fit for the Future) Theme - Realising the potential of our major towns; and • Corporate Regeneration Strategy (Fit for the Future) Theme - A diverse and sustainable economy.
Background
3.1In March 2013, WG announced its new Regeneration Framework for Wales, “Vibrant and Viable Places”.
3.2Bridgend town centre was among the 11 approved bids and £5.98 million of grant funding has been secured. A previous report to Cabinet in May 2014 identified the positive impact that this resource could have in the town centre, as a result of redeveloping the Rhiw Car Park, to provide new town centre housing and a modern, fit for purpose car parking facility. The report also highlighted the delivery risks and issues. Cabinet authorised officers to accept the grant and progress the scheme, including the sale of Council owned land, subject to there being a further report to Cabinet seeking the approval to enter into a Regeneration Collaboration Agreement, land sale contractual agreement(s), with the relevant Registered Social Landlord, and any ancillary documentation, including any agreements with the contractors undertaking the actual construction works.
4. Current Situation / Proposal
4.1Substantial progress has been made to deliver the Rhiw Gateway scheme since the last Cabinet report. The scheme is currently on schedule and all key milestones for delivery and grant drawdown for the financial year 2014-15 have been met to date. Governance arrangements have been established and are working effectively. This has been confirmed by a Gateway Zero review, undertaken by independent consultants appointed by WG. The project has been awarded an amber-green rating, the highest awarded to any local authority implementing a VVP project. A Project Board, chaired by the Corporate Director Communities, is meeting regularly, with representation from Finance, Property, Regeneration, Welsh Government and Coastal Housing Group Limited. There is a detailed project delivery plan, which identifies critical activities and milestones. The design of the scheme is complete, and a planning application is awaiting determination.
4.2A number of alternative car-parking options have been identified for Council staff, in order to maximise the number of spaces available for shoppers and town centre businesses during the construction phase. Survey work has been undertaken to obtain up-to-date information on usage levels in existing car parks, in order to determine how much alternative parking needs to be commissioned on a temporary basis.
Development Agreement
4.3The Development Agreement will be entered into by the Council and CHGL, subject to approval of this report. The Contractor will be appointed by CHGL in accordance with the Public Contract Regulations 2006 to undertake the project works. There will be no direct contract between the Council and the Contractor although there will be a number of collateral warranties with the Council and relevant contractors including consultants.
4.4Work has been underway for several months on negotiating the Development Agreement, so that the development itself and the responsibilities of both parties are clearly defined.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.