That Cabinet approved that the Capital Programme is submitted to Council for approval and if there was insufficient funding from clawback the £250k for the provision of a temporary classroom at West Park Primary School be funded from the School Modernisation Retention budget.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1The purpose of this report is to update Cabinet on the current capital programme and to seek approval to present a report to Council for a revised capital programme for 2015-16 to 2024-25.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1Capital investment in our assets is a key factor in meeting the Improvement Objectives set out in the Council’s Corporate Plan.
Background
3.1In February 2015 Council approved a capital programme for 2014-15 to 2024-25 of £153.014 million. The capital programme as approved by Council in February 2015 is attached as Appendix 1 for information. Since then the programme has changed to reflect funding changes to some schemes, slippage from 2014-15, additional external funding approvals and changes to expenditure profiles.
3.2The main reasons for the difference between the programme approved by Council in February and the current programme are:
• Additional funding of £6.584 million from Welsh Government in respect of the Community Care Information Solution project (CCIS).
• Additional grant approvals and capitalisation of revenue minor works.
• Slippage of £1.63 million in respect of the depot rationalisation into 2015-16.
• Slippage on Disabled Facility and Private Sector Housing Grants of £987,000 to meet anticipated demand in 2015-16.
• Slippage of £669,000 in respect of the maximising space and technology programme into 2015-16, along with the incorporation of the Domestic Abuse Grant.
• Slippage on a number of 21st Century School projects, including Additional Learning Needs at the former Ogmore Comprehensive, and the Mynydd Cynffig School amalgamation. 4. Current situation / proposal
4.1A number of schemes, for which funding has already been identified, need approval for inclusion in the capital programme. Further detail on the individual schemes is provided below:
Shopmobility
Cabinet agreed on 11th November 2014 to relocate the Shopmobility service from the Rhiw car park to Brackla 1 multi-storey car park. Whilst it was agreed that the cost would be met from the budget for the Rhiw Car Park it has since been considered more appropriate to fund this from Council resources, and not from the VVP grant, to enable the permanent relocation of the service without putting the grant funding at risk. The cost of this is estimated to be £105,000 and funding has been reserved for this within the Council’s earmarked reserve to fund revenue contributions to capital expenditure.
Joint Vehicle Maintenance
The fleet service moved into the ex-Fiskars property in February 2015 upon the establishment of the collaborative Joint Vehicle Maintenance facility with South Wales Police. Whilst the facility has a number of vehicle lifts for smaller vehicles, it has become apparent that the service needs a 30 Tonne lift ramp to enable it to fulfil a wider range of operations. The proposed new lift will have radius plates fitted to it to enable the checking of axle movement both vertically and laterally, which is currently being undertaken using the inspection pit at Waterton Depot until it is decommissioned. The estimated cost of this equipment is £46,000. The Council has previously set aside an earmarked reserve to meet the costs associated with the establishment of the Joint Vehicle Maintenance facility and there is sufficient funding in this reserve to meet this cost.
West Park Primary School
A temporary classroom is required at the school to accommodate rising pupil numbers and increased demand for places from September 2015. The estimated cost of the scheme is £250,000 and this will be funded from revenue, from excess surplus balances clawed back from schools at the end of the 2014-15 financial year in accordance with the School Funding (Wales) Regulations 2010.
4.2Studio 34
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.