Resolved
That Council approved the Capital Programme and if there was insufficient funding from clawback the £250k for the provision of a temporary classroom at West Park Primary School be funded from the School Modernisation Retention budget.
Council approved this item on Wednesday 15 July 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That Council approved the Capital Programme and if there was insufficient funding from clawback the £250k for the provision of a temporary classroom at West Park Primary School be funded from the School Modernisation Retention budget.
1.1The purpose of this report is to obtain approval from Council for a revised capital programme for 2015-16 to 2024-25.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1Capital investment in our assets is a key factor in meeting the Improvement Objectives set out in the Council’s Corporate Plan.
3.1In February 2015 Council approved a capital programme for 2014-15 to 2024-25 of £153.014 million. The capital programme as approved by Council in February 2015 is attached as Appendix 1 for information. Since then the programme has changed to reflect funding changes to some schemes, slippage from 2014-15, additional external funding approvals and changes to expenditure profiles.
3.2The main reasons for the difference between the programme approved by Council in February and the current programme are:
• Additional funding of £6.584 million from Welsh Government in respect of the Community Care Information Solution project (CCIS). • Additional grant approvals and capitalisation of revenue minor works. • Slippage of £1.63 million in respect of the depot rationalisation into 2015-16. • Slippage on Disabled Facility and Private Sector Housing Grants of £987,000 to meet anticipated demand in 2015-16.
• Slippage of £669,000 in respect of the maximising space and technology programme into 2015-16, along with the incorporation of the Domestic Abuse Grant. • Slippage on a number of 21st Century School projects, including Additional Learning Needs at the former Ogmore Comprehensive, and the Mynydd Cynffig School amalgamation.
4. Current situation / proposal
4.1A number of schemes, for which funding has already been identified, need approval for inclusion in the capital programme. Further detail on the individual schemes is provided below: Shopmobility
Cabinet agreed on 11th November 2014 to relocate the Shopmobility service from the Rhiw car park to Brackla 1 multi-storey car park. Whilst it was agreed that the cost would be met from the budget for the Rhiw Car Park it has since been considered more appropriate to fund this from Council resources, and not from the VVP grant, to enable the permanent relocation of the service without putting the grant funding at risk. The cost of this is estimated to be £105,000 and funding has been reserved for this within the Council’s earmarked reserve to fund revenue contributions to capital expenditure.
Joint Vehicle Maintenance
The fleet service moved into the ex-Fiskars property in February 2015 upon the establishment of the collaborative Joint Vehicle Maintenance facility with South Wales Police. Whilst the facility has a number of vehicle lifts for smaller vehicles, it has become apparent that the service needs a 30 Tonne lift ramp to enable it to fulfil a wider range of operations. The proposed new lift will have radius plates fitted to it to enable the checking of axle movement both vertically and laterally, which is currently being undertaken using the inspection pit at Waterton Depot until it is decommissioned. The estimated cost of this equipment is £46,000. The Council has previously set aside an earmarked reserve to meet the costs associated with the establishment of the Joint Vehicle Maintenance facility and there is sufficient funding in this reserve to meet this cost.
West Park Primary School
A temporary classroom is required at the school to accommodate rising pupil numbers and increased demand for places from September 2015. The estimated cost of the scheme is £250,000 and this will be funded from revenue, from excess surplus balances clawed back from schools at the end of the 2014-15 financial year in accordance with the School Funding (Wales) Regulations 2010.
4.2Studio 34
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
150715 Capital Programme 2015-16 to 2024-25 Appendix 1Appendix | 30 KB | Download |
PDF |
150715 Capital Programme 2015-16 to 2024-25 Appendix 2Appendix | 37 KB | Download |
PDF |
Capital Programme 2015-16 to 2024-25Report | 32 KB | DownloadRead as text |
Follow Council at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Sep 2023 | Approval of MinutesThat the minutes of a meeting of Council dated 19 July 2023, be approved as a true and accurate record. | Approved | Open |
| 20 Sep 2023 | South-East Wales Corporate Joint Committee Overview and Scrutiny ArrangementsCouncil agreed to defer this item in order to receive further information at the next scheduled meeting of Council. | Agreed | Open |
| 20 Sep 2023 | Appointment of Registered Representatives to the Overview and Scrutiny Subject CommitteesThat Council noted the report and approved the appointment of the following individuals as Registered Representatives... | Noted | Open |
| 20 Sep 2023 | Information Report for NotingThat Council acknowledged the publication of the report referred to in paragraph 3.1 of the report. | Decided | Open |
| 19 Jul 2023 | Approval of MinutesThat the minutes of the 21/06/2023 be approved as a true and accurate record. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.