Resolved
That the Ysgol Bryn Castell Development and Planning Brief be approved as Development Control guidance, to be used as a material consideration in the determination of future planning applications for the site.
Development Control Committee approved this item on Thursday 1 September 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Ysgol Bryn Castell Development and Planning Brief be approved as Development Control guidance, to be used as a material consideration in the determination of future planning applications for the site.
1.1To consider the Ysgol Bryn Castell (Phase 2) Development and Planning Brief and approve its content as a material consideration in the determination of future planning applications.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1The approval of the Development and Planning Brief will contribute to the Council’s Corporate Improvement priorities of working together to develop the local economy and working together to make smarter use of our resources.
3.1As part of the Council’s School Modernisation Programme, the former Ysgol Bryn Castell School has been relocated to the re-modelled Ogmore Comprehensive School site in Bryncethin. Part of the former Ysgol Bryn Castell school site has already been released and residential development is currently under construction on Phase 1.
3.2To assist in the future development process and the disposal of Phase 2, a Development and Planning Brief has been commissioned by Property Services and undertaken by planning consultants Bilfinger GVA.
4. Current Situation
4.1The whole of the former Ysgol Bryn Castell site is allocated for residential development in the adopted Bridgend Local Development Plan by Policy COM2(7).
4.2The Development and Planning Brief for Phase 2 of the site is attached at Appendix 1. The purpose of the document is to provide a framework for the redevelopment of the site and to demonstrate that there are no significant technical constraints that cannot be overcome with respect to its future development.
4.3The document has been developed in consultation with officers of the Council, including highways officers who are satisfied that the highway and access arrangements proposed are appropriate.
4.4The contents of the Development and Planning Brief is summarised as follows:-
Version 2.0 • Section 1 – Introduction.
This sets out the context for the release of the site and the brief’s overall purpose and structure.
• Section 2 – The Site.
This provides overview of the site, its location and key characteristics.
• Section 3 – Planning Policy.
This summarises the relevant planning policy context against which any future proposals will be considered. This includes policies in the adopted Bridgend LDP, Planning Policy Wales and Supplementary Planning Guidance (SPGs).
• Section 4 – Constraints / Opportunities and Technical Investigations.
This section identifies the key constraints from a range of technical studies and reports commissioned to support the development of the site, including for example protected trees, access arrangements and highway capacity, ecology, drainage and ground investigations. It suggests how, where concerns are identified, these can be addressed.
• Section 5 – Design Principles and Parameters.
This section sets out the overarching design principles and parameters for the site, including scale, mix and housing density; landscape setting and trees; the provision of on-site recreational open-space; accessibility, movement and active travel; drainage and biodiversity.
• Section 6 – Planning Obligations.
This outlines the key S106 requirements that are likely to be sought in connection with the site when a planning application is submitted.
5. Effect upon Policy Framework& Procedure Rules
5.1The Development and Planning Brief will represent a material consideration in the determination of any future planning applications for the site.
6. Equality Impact Assessment
6.1An Equality Impact Assessment Screening has been undertaken and the proposed recommendation is unlikely to have an impact on equality issues.
7.1There will be a capital receipt for the sale of the site and its future development could generate Section 106 contributions.
Version 2.0 8. Recommendation
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Ysgol Bryn Castell, Bridgend Phase 2 Development and Planning BriefReport | 21 MB | DownloadRead as text |
Follow Development Control Committee at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Oct 2023 | Site VisitsThat a date for any site visits agreed by the Committee or identified in advance of the next meeting by the Chairpers... | Agreed | Open |
| 19 Oct 2023 | Approval of MinutesThat the Minutes of a meeting of the Development Control Committee dated 7 September 2023, be approved as a true and ... | Approved | Open |
| 19 Oct 2023 | Amendment SheetThe was accepted by the Chairperson as an urgent item under Part 4, paragraph 4 of the Council Procedure Rules. | Decided | Open |
| 19 Oct 2023 | Development Control Committee GuidanceThat the report of the Corporate Director – Communities, outlining the be noted. | Noted | Open |
| 19 Oct 2023 | P/23/147/FUL - Rear of 82 Merthyr Mawr Road, Bridgend, CF31 3NSThat the above application be granted, subject to the Conditions contained in the report of the Corporate Director – ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.