CABINET - TUESDAY, 6 SEPTEMBER 2016
MINUTES OF A MEETING OF THE CABINET HELD IN COMMITTEE ROOMS 1/2/3, CIVIC OFFICES ANGEL STREET BRIDGEND CF31 4WB ON TUESDAY, 6 SEPTEMBER 2016 AT 2.30 PM
Present
Councillor MEJ Nott OBE – Chairperson
CE Smith HM Williams CL Reeves
Officers:
Kelly Watson Group Manager Legal & Democratic Services Julie Ellams Democratic Services Officer - Committees Darren Mepham Chief Executive Deborah McMillan Corporate Director Education & Family Support Mark Shephard Corporate Director - Communities Mark Galvin Senior Democratic Services Officer - Committees Jackie Davies Head of Adult Social Care Andrew Thomas Group Manager – Sports and Physical Activity
964. APOLOGIES FOR ABSENCE Apologies for absence were received from the following Councillors and Officers:-
Councillor HJ David Councillor H Townsend Councillor PJ White Sue Cooper Andrew Jolley Randal Hemingway
965. DECLARATIONS OF INTEREST
None
966. APPROVAL OF MINUTES
RESOLVED: That the Minutes of a meeting of Cabinet dated 26 July 2016, be approved as a true and accurate record.
967. PROPOSED COMMUNITY ROUTE BETWEEN PENCOED AND HEOL Y CYW
The Corporate Director Communities submitted a report, that sought Cabinet approval for the creation of a community route between Pencoed and Heol y Cyw, and the subsequent adoption of the proposed route as a highway maintainable at the public expense. The report also informed Cabinet of the current position in respect of Section 106 Agreement funding received pursuant to a Section 106 Agreement dated 10 October 2007, and the use of this funding for the proposed route.
By way of background information, the Corporate Director Communities advised that in 2006 Rockwool Ltd submitted a planning application to increase the size of its operational facility in Wern Tarw near Pencoed.
1 CABINET - TUESDAY, 6 SEPTEMBER 2016
During subsequent discussions between Rockwool Ltd and the Council, it was agreed that Condition 12 of planning consent P/06/1588/FUL would be superseded by a Section 106 Agreement requiring the provisions as outlined in paragraph 3.2 of the report.
Paragraph 3.3 of the report explained that due to issues regarding land ownership rights, ie that some of the original community route initially proposed, could not be used as it was common rather than Council owned land, in April/May 2012 the Heol y Cyw Community Access Group approached the Council about the proposal to construct a community route from Pencoed to Heol y Cyw that was also acceptable to the Commoners Association by means of an alternative Scheme being submitted to the one that was originally proposed.
Paragraph 3.6 of the report, also gave details of the stretch of route to be provided and information regarding Section 106 funds. The Corporate Director Communities expanded upon this, by confirming that it was proposed that the remaining Section 106 monies would be used exclusively on construction of the works between Pencoed and Wern Tarw Cross. The remaining Section 106 monies were not sufficient to construct all of the proposed route between these areas. Rockwool had conditioned that, in order for the Section 106 monies to be used to fund part of the construction of the route, the Community Group had to gain access to sufficient additional monies to construct the section from Pencoed to Wern Tarw Cross before a build contract was entered into.
The Corporate Director Communities added that it was proposed that when the route had been completed to a satisfactory standard it would be adopted by the Council as a highway maintainable at the public expense. This would in all likelihood involve phased dedication of sections of the proposed route.
Paragraph 4.1 then outlined the current situation regarding the proposed route.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Approval of MinutesMinutes | 99 KB | DownloadRead as text |
Follow Cabinet at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Oct 2023 | Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... | Noted | Open |
| 17 Oct 2023 | Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... | Noted | Open |
| 17 Oct 2023 | Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... | Noted | Open |
| 17 Oct 2023 | Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... | Approved | Open |
| 17 Oct 2023 | Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.