That Cabinet: (1) Approved a waiver under Rule 3.2.3 of the Council’s Contract Procedure Rules from the requirement to obtain quotes or tenders by open competition for the supply of equipment to upgrade the existing Council Suite systems from analogue to digital connectivity; Authorised the Corporate Director Operational and Partnership Services to enter into a contract with Auditel Rental and Services Limited on behalf of the Council for the supply of digital connectivity as detailed in the report.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
REPORT OF THE CORPORATE DIRECTOR – OPERATIONAL AND PARTNERSHIP SERVICES
COUNCIL SUITE INFRASTRUCTURE UPGRADE
1. Purpose of Report.
1.1The purpose of the report is to:
a) seek a waiver under Rule 3.2.3 of the Council’s Contract Procedure Rules from the requirement to obtain quotes or tenders by open competition for the supply of equipment which will enable the enhancement of the existing Council Chamber infrastructure.
b) seek approval to enter into a contract with Auditel Rental and Services Limited.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1This report assists in the achievement of all the Corporate Priorities by enabling the effective use of the technology for public meetings of Council and other committees.
1. Supporting a successful economy – taking steps to make the County a good place to do business, for people to live, work, study and visit, and to ensure that our schools are focused on raising the skills, qualifications and ambitions of all people in the County.
2. Smarter use of resources – ensuring that all its resources (financial, physical, human and technological) are used as effectively and efficiently as possible and support the development of resources throughout the community that can help deliver the Council’s priorities.
3. Background.
3.1Following a competitive tender for the refurbishment of the Council Chamber in 2006 a number of systems were installed to modernise the facilities and provide compliance with the then Disability Discrimination Act. The systems included the microphones, cameras, display systems and electronic voting. When the work was completed Bridgend was considered as having one of the most modern and effective Council Chambers in Wales.
3.2The development of ICT and audio visual systems has progressed significantly since the initial installation and in October 2014 Cabinet approved the upgrading of the systems in preparation for the implementation of webcasting. 3.3 The webcasting system using the Council Chamber’s systems has enabled greater openness and transparency of the Council’s decision making processes. The 16 formal meetings which were webcast between 01 January 2016 and 01 September 2016 were viewed by a total of 5069 times which equates to 317 viewers per meeting.
3.4The ongoing use of the webcasting system has identified the shortcomings of the existing infrastructure within the Council Chamber. These primarily relate to its age and the increased use of digital functionality with the original analogue connectivity.
4. Current situation / Proposal.
4.1The current systems are suitable for basic meetings but do not effectively support the complex demands expected in this digital age. The effectiveness and quality of High Definition (HD) inputs and displays which are currently installed in the Council Chamber are significantly reduced when using the existing analogue infrastructure.
4.2To address this issue and to optimise the effectiveness of the single integrated system used for the display and control of the audio visual and webcasting facilities, it is proposed that an upgrade to the infrastructure within the Council Suite (Council Chamber/Committee Rooms/Member’s Room and Cabinet Meeting Room) be undertaken to provide HDMI (High-Definition Multimedia Interface) connectivity and data switching between the existing installed devices. The proposed upgrade will also provide an element of future proofing to enable the infrastructure to support the up and coming digital technologies including 4K which are becoming more available and cost effective.
4.3The proposed upgrade of the infrastructure will provide:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.