The minutes of the meeting held on 27 th April 2017 were approved as a true and accurate record subject to the following amendments: a. The inclusion of J Williams as an attendee at the meeting b. That minute 302 be revised: Paragraph 1 be revised to read: The Financial Audit Manager, Wales Audit Office presented the External Auditor’s Annual Audit Plan 2016-17. Paragraph 2, line 3 be revised to read: work to be undertaken by the Auditor General at Bridgend CBC under the Public Audit Paragraph 3 following “Audit Work to be undertaken” to delete “and a schedule of authorised grant signatories”. Paragraph 7 line 4 be amended to read: Wales Audit Office would need to know the leave commitments of key finance staff as it would need Resolution to read: That the content of the External Auditor’s Annual Audit Plan 2016-17 be noted.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
MINUTES OF A MEETING OF THE AUDIT COMMITTEE HELD IN COUNCIL CHAMBER, CIVIC OFFICES ANGEL STREET BRIDGEND CF31 4WB ON THURSDAY, 27 APRIL 2017 AT 10.00 AM
Present
Councillor CA Green – Chairperson
JR McCarthy JE Lewis CL Jones G Davies R Williams RC Jones
Apologies for Absence
M Gregory
Officers:
Janice Jenkins Benefits and Financial Assessments Manager Andrew Rees Senior Democratic Services Officer - Committees Helen Smith Chief Internal Auditor Nigel Smith Finance Manager Mary Williams Chief Accountant
Representing the Wales Audit Office
Steve Barry - Performance Audit Manager Mark Jones - Financial Audit Manager John Llewellyn - Financial Audit Team Leader
300. DECLARATIONS OF INTEREST
None.
301. APPROVAL OF MINUTES
RESOLVED: That the minutes of the meeting of the Audit Committee of 26 January 2017 be approved as a true and accurate record.
302. EXTERNAL AUDIT ANNUAL AUDIT PLAN 2016-17
The Financial Audit Manager, Wales Audit Office presented the External Auditor’s Annual Audit Plan 2016-17, together with a schedule of authorised grant signatories for the Council for the Committee to note.
The Annual Audit Plan Outline had been prepared by the Council’s External Auditor to meet the requirement of the auditing standards and proper audit practices. It sets out the work to be undertaken by the Appointed Auditor at Bridgend CBC under the Public Audit (Wales) Act 2004, the Local Government (Wales) Measure 2009 (the Measure), the Local Government Act 1999 and the Code of Audit Practice.
The Financial Audit Manager informed the Committee that the Financial Audit 2016-17 element of this plan had been prepared by Wales Audit Office, the purpose of which is to set out the proposed work, when it will be undertaken, how much it will cost and who will undertake it. He stated that the Plan also outlined the Performance Audit, the Certification of Grant Claims and Returns and other Audit Work to be undertaken and a schedule of authorised grant signatories.
1 AUDIT COMMITTEE - THURSDAY, 27 APRIL 2017
The Financial Audit Manager reported on the audit approach to be taken which consists of the three phases of Planning; Execution and Concluding and reporting. He set out the risks of material misstatement which he considered to be significant and which require special audit consideration and the work intended to address them in relation to:
Financial Challenges Cardiff Capital Region City Deal Financial Audit Risk Changes to the Comprehensive Income and Expenditure Statement and new disclosures Significant capital projects
The Committee referred to the risk of management override and questioned whether this was a risk unique to this Council or was it common to all Councils generally. The Financial Audit Manager informed the Committee that this was a risk which is common to all Councils and is an auditing requirement and not a risk specifically to this Council.
The Performance Audit Manager informed the Committee that a report on Governance would be presented to the next meeting of the Committee.
The Committee questioned the burden placed on officials in relation to all appropriate officials being available within reasonable notice during the audit. The Financial Audit Manager informed the Committee that the burden would fall on Finance staff in that the Wales Audit Office would need to know the leave commitments of staff as it would need to give reasonable notice of their intention to test a number of transactions. The Performance Audit Manager informed the Committee that the performance audit programme placed more emphasis on local risks. He stated that there is a possibility that the WAO could alleviate the burden on Internal Audit in carrying out audits on their behalf.
RESOLVED: That the content of the External Auditor’s Annual Audit Plan 2016- 17 and the schedule of authorised grant signatories be noted.
303. CERTIFICATION OF GRANTS AND RETURNS 2015-16
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.