Resolved
RESOLVED That the Committee gave due consideration to the Internal Audit Outturn Report covering the period April to August 2017 to ensure that all aspects of their core functions were being adequately reported.
Governance and Audit Committee decided this item on Thursday 28 September 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Committee gave due consideration to the Internal Audit Outturn Report covering the period April to August 2017 to ensure that all aspects of their core functions were being adequately reported.
3.1The 2017/18 Internal Audit Plan was submitted to the Audit Committee for consideration and approval on the 27th April 2017. The Plan outlined the assignments to be carried out and their respective priorities.
3.2The Plan provided for a total of 1,085 productive days to cover the period April 2017 to March 2018.
4. Current situation / proposal
4.1The following table shows an analysis of productive days achieved against the plan for the five months of this financial year. A more detailed analysis as extracted from the Internal Audit Shared Service management information system is shown at Appendix A.
2017/18 Proportion of 2017-18 Full Year Plan Days April to Directorates Plan Days Available for August April to August Actual Days 2017 delivered
Max. Min. CEX - Finance 130 54 54 24 Operational & Partnership Services 110 46 46 37 Education & Family Support 160 67 52 43 Communities 130 54 54 10 Social Services & Wellbeing 170 71 71 42 Cross Cutting including: 385 160 138 70 External; Contingency unplanned and Fraud & Error TOTAL PRODUCTIVE DAYS 1,085 452 415 226
4.2The figures show that 226 actual days have been achieved, which is significant less than that expected.
4.3At present the overall structure of the Section is based on 18 Full Time Equivalent Employees (FTE’s). However, at the end of the Financial Year 2016/17, the Section was carrying 7.5 FTE vacant posts, which has subsequently increased to 9.5 FTE vacant posts.
4.4At the end of the period, 13 reviews / jobs have been completed and closed, 11 of which has provided management with an overall substantial / reasonable audit opinion on the internal control environment for the systems examined. Of the remaining 2 reviews, 1 identified significant weakness to such an extent that only limited assurance could be placed on the overall control environment and one, although necessary, was closed with no opinion being provided due to the nature of the work undertaken.
5. Effect upon Policy Framework& Procedure Rules.
5.1There is no effect upon the policy framework and procedure rules.
6. Equality Impact Assessment.
6.1There are no equality implications arising from this report.
7. Financial Implications.
7.1Effective audit planning and monitoring are key contributors in ensuring that the Council’s assets and interests are properly accounted for and safeguarded.
8. Recommendation.
8.1That Members give due consideration to the Internal Audit Outturn Report covering the period April to August 2017 to ensure that all aspects of their core functions are being adequately reported.
Helen Smith Chief Internal Auditor 28th September 2017
Contact Officer: Helen Smith – Chief Internal Auditor
Telephone: (01656) 754901
E-mail: [email protected] Postal Address Bridgend County Borough Council Internal Audit Innovation Centre Bridgend Science Park Bridgend CF31 3NA
Background Documents
None
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
INTERNAL AUDIT: OUTTURN REPORT: APRIL TO AUGUST 2017Report | 67 KB | DownloadRead as text |
PDF |
Internal Audit Outturn Report Appendix BAppendix | 102 KB | Download |
PDF |
Internal Audit Outturn report Appendix AAppendix | 146 KB | Download |
Follow Governance and Audit Committee at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Sep 2023 | Approval of MinutesThe Minutes of the meeting on 26 July 2023 were approved as a true and accurate record. | Approved | Open |
| 28 Sep 2023 | Governance and Audit Committee Action RecordThe Committee noted the Action Record and provided comments, as appropriate. | Noted | Open |
| 28 Sep 2023 | Code of Corporate GovernanceGovernance and Audit Committee considered and, subject to some minor changes, approved the Council’s Code of Corporat... | Approved | Open |
| 28 Sep 2023 | Ethical Investment PolicyThe Governance and Audit Committee considered the and agreed its inclusion in future Treasury Management Strategies. | Agreed | Open |
| 28 Sep 2023 | Progress Against the Internal Audit Risk Based Plan 2023-24Members of the Committee noted the content of the report and the progress made against the 2023-24 Internal Audit Ris... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.